Full workflow for preparing the tender bill of quantities: preparing entity and object, the seven bases of preparation, itemisation with the five elements and item description, the four-part BOQ composition, deliverables and appendix forms, error liability, and the interface with the tender price ceiling
Chapter 4 of GB/T 50500-2024 provides: the bill of quantities is prepared by a tenderer with preparation capability or by a construction cost consultant commissioned by it (4.1.1); it is itemised with the contract object or a single project or individual structure as the object and forms part of the tender documents (4.1.2); the deliverables comprise the cover, signature page, explanatory notes of the estimate, notes on measurement rules, and the BOQ and pricing forms (4.1.3), in forms B.1.1, C.1.1, D.4.1, E.1.1/E.2.1/E.2.3/E.3.1/E.4.1 to E.4.5/E.5.1 and G.1.1. The BOQ is prepared and priced in four parts -- the work-item BOQ, the preliminaries BOQ, the other items BOQ and VAT (3.1.2) -- and the current edition no longer carries a statutory levies and taxes section; the all-in unit rate and the sum are fully inclusive pre-tax prices excluding VAT, tax is entered under VAT, and the provisional sum for nominated specialist subcontract works already includes VAT and must not be taxed again (3.1.6).
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.1.2、3.1.6、3.1.8 条,第 4.1.1~4.1.7 条,第 4.2.1~4.2.7 条,第 5.1.1、5.2.1、5.2.3、5.2.6、5.2.10 条,第 6.1.7 条,第 7.2.1 条,第 8.2.1、8.2.3 条,第 8.9.1~8.9.2 条
- GB/T 50500-2024 App. B Table B.1.1、App. C Table C.1.1、App. D Table D.4.1、App. E Table E.1.1/E.2.1/E.2.3/E.3.1/E.3.2/E.3.4/E.4.1/E.4.2/E.4.3/E.4.4/E.4.5/E.5.1、App. G Table G.1.1
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works 第 4.1.2、4.1.4、4.2.1、4.2.2、4.2.4、4.2.5 条及App. A~App. Q
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第 9.4 节(项目特征不符)、第 9.5 节(工程量清单缺项)——已废止,规则并入现行 8.2 节
Scope of the topic
Following Chapter 4 of GB/T 50500-2024, this card walks the tender BOQ preparation chain clause by clause: governing clause numbers, deliverables and appendix forms, accuracy-and-completeness liability at review, the interface with the tender price ceiling, and the adjustment clauses matching common preparation errors. It is written for building and decoration works (with GB/T 50854-2024); other disciplines follow their own measurement standards.
Core conclusions
1. Preparing entity and object (4.1.1, 4.1.2)
- 4.1.1: 'The bill of quantities shall be prepared by a tenderer with preparation capability or by a construction cost consultant commissioned by it.'
- 4.1.2: 'The tender BOQ shall be itemised and prepared per the requirements of the tender documents and the works delivery scope, taking the contract object or a single project or individual structure as the object of preparation, and shall form part of the tender documents.' Where the works are constructed and taken over as a whole, itemising by the contract object is preferred.
2. Bases of preparation (4.2.1, seven items) 1 This standard and the national and industry measurement standards for the relevant works; 2 provisions on measurement and pricing of works issued by the national, provincial and sectoral construction authorities, plus supplementary measurement rules added as the works require; 3 the tender documents, the draft contract terms and related materials; 4 the tender drawings for the works and related materials; 5 technical codes and standards relevant to the construction works; 6 site conditions, relevant geological and hydrological data, works characteristics and delivery standards; 7 other relevant materials.
3. BOQ composition and the tax calibre (3.1.2, 3.1.6)
- 3.1.2: 'The bill of quantities shall be prepared and priced separately as the work-item BOQ, the preliminaries BOQ, the other items BOQ and VAT. Where other BOQ formats are used for pricing, the rules of this standard still apply ...' The work-item BOQ represents the physical works.
- 3.1.6: 'The all-in unit rate and the sum of each BOQ item shall be fully inclusive pre-tax prices excluding VAT, composed of labour cost, material cost, plant and small tools cost, overheads, profit and the like, including the agreed or reasonably attributable risk costs and the costs of indispensable auxiliary work; the tax of a BOQ item shall be entered under VAT, but the provisional sum for nominated specialist subcontract works already includes VAT and shall not be charged again in the VAT of the BOQ.'
4. Deliverables and forms (4.1.3 + appendices)
- 4.1.3: 'BOQ deliverables shall include the cover, signature page, explanatory notes of the estimate, notes on measurement rules, and the BOQ and pricing forms. The explanatory notes shall state the project overview, the tender (or contract) scope and the bases of preparation ...'
- 4.1.3 also requires: 'The BOQ shall be prepared per the national and industry measurement standards for the relevant works; where the standards are silent or rules are supplemented ..., the supplemented or adjusted rules shall be stated in the measurement notes.'
- Form mapping:
- tender BOQ cover, form B.1.1; tender BOQ title page, form C.1.1;
- notes on measurement rules, form D.4.1 (note 1: where national and industry measurement standards are adopted, their names and numbers shall be identified; note 2: where rules are supplemented, the detailed rules shall be listed);
- project BOQ summary, form E.1.1 (note 1: the provisional sum for nominated specialist subcontract works is a tax-inclusive price and shall not enter the VAT base; note 2: suited to works itemised by the contract object; single project or individual structure itemisation may also use this form);
- work-item BOQ pricing form, form E.2.1; provisional material unit rates and adjustment form, form E.2.3 (the tenderer fills the provisional rate and identifies the BOQ items using provisional-priced materials, which tenderers absorb into their all-in rates);
- preliminaries pricing form, form E.3.1 (cost composition at form E.3.2; mobilisation and demobilisation of major plant at form E.3.4);
- other items pricing form, form E.4.1; provisional sums schedule, form E.4.2 (a lump figure may be entered, or a base and a percentage rate then computed; tenderers absorb it into the tender total, and at settlement the confirmed amount is entered per the contract); nominated specialist works provisional sum schedule, form E.4.3; dayworks form, form E.4.4; main contractor's attendance and coordination pricing form, form E.4.5 (percentage pricing C1=A1xB, settlement C2=A2xB);
- VAT pricing form, form E.5.1; schedule of employer-supplied materials, form G.1.1.
5. Itemising the work-item BOQ and the five elements (4.1.7, 4.2.2, 4.2.3, 4.2.4 + GB/T 50854-2024)
- Five elements (4.1.7): 'Whether a unit-rate or a lump-sum contract is used, the item code, item name, item description, unit of measurement and work content of the work-item BOQ shall be prepared per the national and industry measurement standards and the supplementary measurement rules ...' Where the preliminaries or other items BOQ cannot carry an item description, work content and item name may be listed instead; chapters and item order may follow the normal construction sequence.
- GB/T 50854-2024 Clause 4.2.1: the BOQ 'shall be prepared per the item codes, item names, item descriptions, units of measurement and measurement rules prescribed in Appendices A to Q of this standard' -- none of the five elements may be missing; Clause 4.2.5 likewise follows Appendices A to Q.
- Coding rules (GB/T 50854-2024 Clause 4.2.2): 'Item codes in the BOQ shall be twelve Arabic digits; digits one to nine shall follow the appendices, digits ten to twelve shall be set per the item names and item descriptions of the proposed works, and item codes within the same single project of the same tendered works shall not duplicate.' Discipline codes: 01 building and decoration, 02 historic-style buildings, 03 general installation, 04 municipal, 05 landscape and greening, 06 mining, 07 structures, 08 urban rail transit, 09 blasting; digits three and four are the appendix sequence code, five and six the sub-division sequence code, seven to nine the work-item name sequence code. Where individual structures are the preparation object and one single project contains several, digits ten to twelve must not duplicate (e.g. 010401002001 / 010401002002 / 010401002003).
- Supplementary items (GB/T 50854-2024 Clause 4.1.4): items not in the appendices may be added; 'the code of a supplementary item consists of the code 01 of this standard, the letter B and three Arabic digits, numbered sequentially from 01B001'; the supplementary listing shall carry item name, item description, unit of measurement, measurement rule and work content; non-measurable preliminary items carry item name, work content and scope of inclusion.
- Item description (GB/T 50854-2024 Clauses 4.2.4 and 4.1.2): describe per the item descriptions prescribed in Appendices A to Q read with the actual proposed works, so as to 'reflect both the design details on the drawings and the code-compliant construction requirements'; 'the work content of items in Appendices A to R of this standard lists principal content only; unless otherwise provided or noted, it shall be deemed to include all work necessary to complete the BOQ item' -- unlisted auxiliary content (e.g. plant movement, materials transport) is included and shall not be split into separate BOQ items. Item descriptions shall be prepared from the design documents read with the completion delivery requirements (Clause 4.2.2).
- Unit-rate contracts (Clause 4.2.2): work-item listings and their item descriptions shall be fixed, and quantities computed, from the tender drawings, the technical codes, the measurement standards and the supplementary rules; items compiled as measured per item shall show 'item' as the unit of measurement; where the tendered works require, items and descriptions not reflected in the tender drawings but likely to arise in construction may be listed by reference to similar works, with provisional quantities fixed from comparable data.
- Lump-sum contracts (Clause 4.2.3): items whose description is determinable from the tender drawings and technical codes but whose quantities cannot be computed accurately may be listed with provisional quantities, so stated in the item description.
- Employer-supplied materials and provisional prices (Clause 4.2.4): items involving employer-supplied (free-issue) materials shall be identified in the tender documents per Section 3.6, with the item description stating that the main material is supplied by the employer; items with provisional material prices shall state the amount in the item description and list material details and provisional unit rates separately per form E.2.3; employer-supplied materials shall be described in the technical codes by material name, grade, specification and model, delivery method and place, and acceptable brand range.
6. Preparing the preliminaries BOQ (4.2.5) Prepare with the actual conditions of the tendered works and the provisions of the authorities concerned, based on conventional construction methods and sequences and the non-physical requirements of welfare, safety, environmental protection, temporary facilities and site order, following the preliminary-item classification rules of the relevant measurement standards and supplementary rules; statutory safety provision items are listed per national, provincial and sectoral requirements and the actual works. Preliminaries are affected by hydrology, weather, environment, safety, the construction scheme and management level; tenderers may inspect the site and decide whether to add items and price them.
7. Itemising the other items BOQ (4.2.6, 4.2.7) 4.2.6 provides: 1 provisional sums shall be listed per the tender documents and the works characteristics, either as 'provisional sums for works or services not yet defined or not describable in detail' or as 'provisional sums for contract price adjustment' -- the former with item and service names, estimated from similar works; the latter estimated from the design depth of the tender drawings, the implementation period and similar works; 2 provisional sums for nominated specialist subcontract works shall be listed by category and (or) discipline with a schedule of details, estimated from similar works prices or the preliminary estimate amount; 3 directly awarded specialist works shall be listed separately per discipline, with schedules of details; 4 employer-supplied materials may be listed separately for those the contractor does and does not install, with material details and provisional unit rates per form G.1.1; 5 dayworks shall state in the item description the trades likely to occur, the names of materials and plant, sundry work and demolition-and-make-good items, and list names, units and reasonable provisional quantities; 6 main contractor's attendance and coordination provisions for employer-supplied materials and specialist subcontract works shall be listed separately, measurable per item or by percentage rate; rate-measured items preferably priced on provisional prices as the base, directly awarded specialist works preferably per item. 4.2.7: items outside 4.2.6 may be added per the tender documents read with the actual works.
8. Review: accuracy-and-completeness liability and the consequences of defects (3.1.8, 4.1.4, 4.1.5, 4.1.6)
- 3.1.8: 'For works under unit-rate contracts, the accuracy and completeness of the work-item BOQ shall be the employer's responsibility; under lump-sum contracts, the accuracy and completeness of the priced work-item BOQ shall be the contractor's. Whether a unit-rate or lump-sum contract is used, the completeness and accuracy of preliminaries compiled per item shall be the contractor's responsibility.' Under unit-rate contracts tenderers must not alter the BOQ at tendering; under lump-sum contracts they may add items and price them; for preliminaries they decide and bear their own pricing risk.
- 4.1.4: where the tender BOQ serves a lump-sum contract, its items and quantities are deemed to conform to the tender drawings and technical codes; any BOQ errors are for the contractor to complete and remedy, with no adjustment per Clause 6.1.7; where it serves a unit-rate contract, itemisation, work content and quantities are deemed to conform to the tender drawings and technical codes, work-item BOQ errors being the employer's to bear, adjusted per Section 8.2. In lump-sum contracts where the tender drawings cannot support accurate itemisation and measurement, the item description shall state 'provisional quantity' with provisional quantities given, actual quantities adjustable per the unit-rate provisions; lump-sum items within unit-rate contracts are listed and priced per item.
- 4.1.5: under unit-rate contracts the work-item quantities are provisional; in performance they are fixed by re-measurement from the actual construction drawings issued by the employer and the agreed measurement standards and supplementary rules -- except that the preliminaries BOQ and per-item work items are computed under the lump-sum pricing provisions.
- 4.1.6: under lump-sum contracts, price changes caused by BOQ errors are deemed included in the contract total and are not adjusted during performance; but items and quantities stated as provisional shall be re-measured under the unit-rate pricing rules, adjusting the related contract prices and total.
- 8.2.1: unit-rate contracts re-measure all work-item BOQ items and quantities of the contract drawings per Clause 7.2.1; where errors cause item changes or quantity movements no greater than 15% (inclusive) of the contract BOQ quantity for the item, adjust per Clause 8.9.1; beyond 15% (exclusive), per Clause 8.9.2. 8.2.3: for lump-sum contracts 'the contract price and contract time shall not be adjusted for BOQ errors'; only provisional-quantity unit-priced items may be adjusted per Clauses 7.2.1 and 8.2.1, and preliminaries, save for such items, do not adjust for errors.
9. The interface with preparing the tender price ceiling (5.1.1, 5.2.1, 5.2.10)
- 5.1.1: where a tender price ceiling is set, it shall be prepared per the relevant national provisions by a capable tenderer or a commissioned construction cost consultant, under this standard and the measurement standards, 'and the total of the tender price ceiling and the basis and method of its preparation shall be published when the tender documents are issued'; the ceiling is the highest price the tenderer can accept for the tendered works.
- Boundary: the tender BOQ is the pricing object and precondition of the ceiling (ceiling basis item 2 of Clause 5.2.1 already includes the tender BOQ, the contract terms, the tender drawings and the technical codes); the BOQ settles 'items and quantities', the ceiling settles 'price' -- the BOQ itself carries no price column or VAT amount, prices being entered at ceiling preparation or tender pricing; provisional sums and nominated specialist works provisional sums are priced at ceiling stage at the amounts listed in the tender BOQ, and dayworks are priced per the work content and requirements listed in the BOQ (5.2.6).
- 5.2.10: where addenda, Q&A, objection clarifications or corrections change the ceiling, the tenderer shall correct and republish it per the relevant requirements and procedures.
10. Common preparation errors and their consequences
| Common error | Directly breaches | Consequence (unit-rate / lump-sum) |
|---|---|---|
| Missing or omitted work items | 4.1.4, 4.2.2 | Unit-rate: a BOQ error borne by the employer, adjusted per 8.2.1 (within 15% per 8.9.1, beyond per 8.9.2); lump-sum: the error price is deemed included in the total, no adjustment per 4.1.6 and 8.2.3 (provisional-quantity items excepted) |
| Item description mismatched or inaccurate | 4.1.7; GB/T 50854-2024 Clauses 4.2.4 and 4.1.2 | Unit-rate: borne by the employer, the all-in unit rate re-determined and adjusted per Section 8.2; lump-sum: borne by the contractor |
| Duplicate or short item codes | GB/T 50854-2024 Clause 4.2.2 | Item codes within one single project of one tender must not duplicate; a preparation error requiring re-coding, it impairs unique item identification and quantity reconciliation at settlement |
| Units or rules inconsistent with the measurement standard appendices | GB/T 50854-2024 Clauses 4.2.1 and 4.2.5; GB/T 50500-2024 Clause 4.1.3 | Where the standard is silent or rules are supplemented, they must be stated in the measurement notes; unstated means a preparation error |
| Missing preliminary items | 4.2.5 | Under either contract type, the completeness and accuracy of per-item preliminaries are the contractor's (3.1.8); tenderers add items and price them at their own risk |
| Lump-sum drawings too shallow, no provisional-quantity flag | 4.2.3, 4.1.4 | The re-measurement channel via unit-rate pricing is lost; the error price is deemed included in the contract total |
| VAT double-charged on the nominated specialist works provisional sum | 3.1.6; form E.1.1 note 1 | The VAT base must not include the tax-inclusive nominated works provisional sum |
Applicable boundaries
- Edition boundary: all clauses above follow GB/T 50500-2024 (effective 2025-09-01, replacing GB 50500-2013; changed from mandatory GB to recommended GB/T). GB 50500-2013 Section 9.4 'item description mismatch' and Section 9.5 'omitted BOQ items' are absorbed into the Section 8.2 'BOQ errors' mechanism and must not be cited by the old clause numbers; the 2013 'statutory levies and taxes' section has become the VAT section, and the general notes have been split into explanatory notes of the estimate plus notes on measurement rules.
- Discipline boundary: the five coding elements and the measurement rules follow the appendices of the discipline's own national or industry measurement standard. The twelve-digit coding, the 01B001 supplementary-item rule and Appendices A to Q here come from GB/T 50854-2024; other disciplines consult their own appendices, substituting the discipline code segment.
- Pricing-mode boundary: unit-rate and lump-sum contracts differ in itemisation precision, provisional-quantity handling and error-adjustment paths -- fix the contract pricing mode before applying clauses.
- Estimating employer-supplied materials, nominated specialist works provisional sums and provisional sums relies on similar-works prices or preliminary estimate amounts; it is preparer judgement, the standard fixing no percentage or ratio.
- Operational defect-checking steps sit in the BOQ review topic; the edition history of error liability in the liability topic.
Further reading
- GB/T 50500-2024: Clauses 3.1.2, 3.1.6, 3.1.8, 4.1.1 to 4.1.7, 4.2.1 to 4.2.7, 5.1.1, 5.2.1, 5.2.3, 5.2.6, 5.2.10, 6.1.7, 7.2.1, 8.2.1, 8.2.3, 8.9.1 to 8.9.2 (15% quantity deviation split).
- Appendix forms: B.1.1, C.1.1, D.4.1, E.1.1, E.2.1, E.2.3, E.3.1 (E.3.2, E.3.4), E.4.1 to E.4.5, E.5.1, G.1.1 (full mapping in section 4 above).
- GB/T 50854-2024: Clauses 4.1.2, 4.1.4 (supplementary items from 01B001), 4.2.1, 4.2.2 (twelve-digit codes), 4.2.4, 4.2.5; Appendices A to Q.