Rules on the significant decimal places of the summarised quantity of each item when measuring the works: t and km keep three decimal places, m, m2, m3 and kg keep two, count units such as number, piece, bar, seat and set are taken whole, plus the clause numbers and unit-group differences across the 2013 and 2024 editions of each sector volume
When measuring the works, the significant decimal places of the summarised quantity of each item follow the sector volume: quantities in 't' (plus 'km' for urban rail transit) keep three decimal places, the fourth rounded off; quantities in 'm', 'm2' and 'm3' (plus 'kg' in the 2013 building volume and the 2024 urban rail volume) keep two decimal places, the third rounded off; quantities in natural count units such as number, piece, bar, seat, set, group or system are whole numbers. Clauses: GB 50854-2013 clause 3.0.4, GB/T 50854-2024 clause 3.0.3, GB/T 50861-2024 clause 3.0.3.
Applicable Codes
- GB 50854-2013 · Code for Measurement of Quantities of Building and Decoration Works 第 3.0.4 条
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works 第 3.0.3 条
- GB/T 50861-2024 · Standard for Measurement of Quantities of Urban Rail Transit Works 第 3.0.3 条
Topic positioning
The rounding rules for significant decimal places when measuring the works (summarising BOQ quantities): how many decimals to keep - or whether to take whole numbers - for mass, length, area, volume and natural count units, with clause numbers marked by sector volume; and a note that this rule sits in the 'measurement of the works' chapter of each sector quantity take-off standard, not in the body of the GB 50500 pricing standard.
Core conclusions
1. Building and decoration works - GB 50854-2013 clause 3.0.4, verbatim:
'When measuring the works, the significant decimal places of the summarised quantity of each item shall comply with the following: 1 In t, three decimal places shall be kept, the fourth decimal place rounded off. 2 In m, m2, m3 and kg, two decimal places shall be kept, the third decimal place rounded off. 3 In number, piece, bar, group and system, whole numbers shall be taken.'
Commentary: 'This clause provides the significant decimal places of the summarised quantity of each item when measuring the works.'
2. Building and decoration works - GB/T 50854-2024 clause 3.0.3, verbatim:
'When measuring the works, the significant decimal places of the summarised quantity of each item shall comply with the following: 1 In t, keep three decimal places, the fourth decimal place rounded off; 2 In m, m2 and m3, keep two decimal places, the third decimal place rounded off; 3 In number, bar, seat, set, bore and truss, take whole numbers.'
Commentary: 'This clause provides the significant decimal places of the summarised quantity of each item when measuring the works.'
3. Urban rail transit works - GB/T 50861-2024 clause 3.0.3, verbatim:
'When measuring the works, the significant decimal places of the summarised quantity of each item shall comply with the following: 1 In t and km, keep three decimal places, the fourth decimal place rounded off; 2 In m, m2, m3 and kg, keep two decimal places, the third decimal place rounded off; 3 In number, piece, bar, group, machine, set, location, block, station, system, item, etc., take whole numbers.'
4. Edition and sector differences (error-prone points)
- The place of kg changed: GB 50854-2013 puts kg in the two-decimal group; GB/T 50854-2024 lists only m, m2 and m3 in the two-decimal group and no longer lists kg (kg is covered elsewhere in that volume); GB/T 50861-2024 (urban rail) still puts kg in the two-decimal group. So the statement 'kg keeps two decimals' cannot be quoted unconditionally across volumes and editions; judge by the measurement standard actually in force and its unit grouping.
- The three-decimal group widened: GB/T 50861-2024 adds km alongside t at three decimals.
- The whole-number group widened: the 2024 building volume moves from number, piece, bar, group and system to number, bar, seat, set, bore and truss; urban rail further takes in machine, set, location, block, station, system and item.
- The rounding method is uniform round-half-up: at three decimals look to the fourth digit, at two decimals to the third.
Applicability boundaries
- The rule binds only the point of 'summarising each item' (the summarised BOQ quantity of each item); the clause itself does not set the precision of intermediate sub-calculations, and intermediate rounding requirements must not be inferred from it.
- Quote clause numbers by sector volume and edition: GB 50854-2013 clause 3.0.4 / GB/T 50854-2024 clause 3.0.3 / GB/T 50861-2024 clause 3.0.3; other sectors (municipal, landscape, highway, railway, etc.) may group units differently in the 'measurement of the works' chapter of their own standards, and clause numbers must not be carried across volumes.
- Significant decimal places settle rounding only; they do not change the measurement basis (measurement on design-shown dimensions, and deduction or merging rules, are separate clauses).
Further reading
GB 50854-2013 'Code for quantity take-off of building and decoration works', clause 3.0.4; GB/T 50854-2024 'Standard for quantity take-off of building and decoration works', clause 3.0.3; GB/T 50861-2024 'Standard for quantity take-off of urban rail transit works', clause 3.0.3. The overall framework of quantity take-off (basis, measurement from drawings, deduction thresholds, the twin BOQ and quota quantity tracks) is covered by the knowledge card 'Overview of quantity take-off for construction works'.
Keywords
- 有效位数
- 汇总工程量
- 保留小数点后三位
- 四舍五入
- 取整数
- measurement of the works
- GB 50854-2013 第3.0.4条
- GB/T 50854-2024 第3.0.3条
- GB/T 50861-2024