measurement of the works
- 01
GB 50500-2013 terms for measurement of the works and construction payment settlement (final account): definitions, clause anchors, side-by-side comparison, and the rules that carry confirmed measurements into the settlement summary, with the corresponding clauses of GB/T 50500-2024
GB 50500-2013 clause 2.0.43 defines 'measurement of the works' as the ca…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.34、2.0.35、7.1.1、7.1.4、7.1.5、7.1.7、7.1.8、8.11.22、9.4.1、9.4.13、10.1.4、10.2.1、10.2.3、10.2.7、10.3.1、10.3.2、10.3.3、10.3.4、10.3.7、10.3.8、10.3.10、10.3.11、10.3.16条、Ch. 11GB/T 50875-2013 · Standard glossary of project costs 第3.4.3、3.4.9条GF-2017-0201《建设工程施工合同(示范文本)》第12.3.2、12.3.3、12.3.4项、第12.4.2、12.4.3、12.4.4项2026-11-01 - 02
How quantities actually executed but not certified by the supervising engineer or the employer are measured at settlement: the GB 50500-2013 Chapter 8 measurement procedure, the 'deemed approval' rule where verification is overdue, hard cases of non-measurement, and the routes of evidence reinforcement and construction cost expert assessment
Quantities not certified under the standard procedure are in principle n…
GB 50500-2013 建设工程工程量清单计价规范 Ch. 8 工程计量(8.1.1、8.1.2、8.1.3、8.2.1、8.2.3、8.2.4、8.2.5、8.2.6)GB/T 50500-2024 建设工程工程量清单计价标准 第7.1.5、7.1.8、12.2.1条GB/T 51262-2017 建设工程造价鉴定规范 第5.4.2、5.9.2、5.9.3条2026-10-25 - 03
Measurement of the works rules in Chapter 8 of GB 50500-2013: measurement basis and mandatory provisions, verification of completed-works quantity reports and deemed approval upon lapse of the period, notice procedure for on-site measurement and consequences of absence, and review of objections to measurement results
Chapter 8 of GB 50500-2013: quantities must be calculated under the rule…
GB 50500-2013 建设工程工程量清单计价规范(第8.1.1、8.2.1、8.2.3、8.2.4、8.2.5条)GB/T 50500-2024 建设工程工程量清单计价标准(第7.1.7、7.1.8条)2026-10-25 - 04
Rules on the significant decimal places of the summarised quantity of each item when measuring the works: t and km keep three decimal places, m, m2, m3 and kg keep two, count units such as number, piece, bar, seat and set are taken whole, plus the clause numbers and unit-group differences across the 2013 and 2024 editions of each sector volume
When measuring the works, the significant decimal places of the summaris…
GB 50854-2013 · Code for Measurement of Quantities of Building and Decoration Works 第 3.0.4 条GB/T 50854-2024 · Standard for measurement of building construction and fitting out works 第 3.0.3 条GB/T 50861-2024 · Standard for Measurement of Quantities of Urban Rail Transit Works 第 3.0.3 条2026-10-25 - 05
Overview of quantity take-off for construction works: basis, general rules and per-trade calculation methods
Quantity take-off rests on the four-tier basis "contract agreement -> de…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准GB 50861-2013 城市轨道交通工程工程量计算规范2026-09-25 - 06
Preventing over-settlement and duplicate settlement of subcontracted quantities: dual-signature locking of measurement + interim settlement by construction stage merged into the final account + the list of items not measured
Preventing over-settlement/duplicate settlement relies on procedural con…
GB/T 50500-2024 第7.1.7、7.1.8、7.5.5、9.1.13、10.2.3、10.3.12条TB 10402-2019 第6.0.1~6.0.8条DB37/T 5028-2022 第6.2.4条2026-09-25 - 07
Determining quantity calculation rules in cost authentication: contract agreement -> national standard -> industry/local standard, and handling version disputes (T/ZBD 100.4-2023)
Quantity calculation rules are the foundation of measurement: where the…
T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.3.1、4.3.2条GB 50861-2013 城市轨道交通工程工程量计算规范 第4.2.5条GB/T 50353-2013 建筑工程建筑面积计算规范2026-09-25 - 08
The relation between measurement and payment: quantities fixed before payment (the causal chain of GB/T 50500-2024 Chapters 7 and 9)
Measurement is the precondition and quantitative basis of payment, and p…
GB/T 50500-2024 建设工程工程量清单计价标准 Ch. 7/Ch. 9/Ch. 10GB/T 50319-2013 建设工程监理规范 第5.3.1条DB13(J)/T 8161-2019 建设工程监理工作标准 第8.2.2条2026-09-25 - 09
Detecting mismatch between reported progress output value and actual quantities: a three-layer mutual-verification method — procedure, evidence, data
The benchmark for judging mismatch is "reported output value vs measured…
DB37/T 5028-2022 第6.2.3条DB13(J)/T 8161-2019 第8.2.2条GB/T 50522-2019 第6.4.2条2026-09-25 - 10
Differences among plan completion rate, output-value completion rate, and physical image progress, and root-cause analysis of their inconsistency
The three indicators are three different rulers: plan completion rate me…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50326-2017 建设工程项目管理规范DB37/T 5028-2022 建设工程监理工作规程2026-09-25