Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Determining quantity calculation rules in cost authentication: contract agreement -> national standard -> industry/local standard, and handling version disputes (T/ZBD 100.4-2023)

Quantity calculation rules are the foundation of measurement: where the contract expressly agrees, the agreement governs; absent agreement, use the national measurement standard consistent with the contract category, and where the national standard is silent, current industry/local standards. On version-update disputes one may not simply use the current code — for unit-rate contracts, apply in turn the rules used by the tender BOQ and by the maximum bid price; for lump-sum contracts, measure by the rules used in bid pricing; where still undeterminable, follow the client's instruction or professional judgment with explanation (T/ZBD 100.4-2023 clauses 4.3.1, 4.3.2).

Applicable Codes

  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.3.1、4.3.2条
  • GB 50861-2013 城市轨道交通工程工程量计算规范 第4.2.5条
  • GB/T 50353-2013 建筑工程建筑面积计算规范

Topic Positioning

The handling order for determining the applicable source and version of the method of measurement in construction cost expert assessment (judicial appraisal) and final account review, resolving two typical problems: "the contract is silent on the method of measurement" and "disputes over rule-version updates".

Core Conclusions

(1) Where the contract expressly agrees the method of measurement, the expert measures per the agreed rules (T/ZBD 100.4-2023 clause 4.3.1). (2) Absent agreement, apply the national standard method of measurement consistent with the contract category; where the national standard does not provide, the corresponding rules of current industry or local standards. Determine the contract category before choosing the standard: construction contracts apply GB/T 50353 "Code for calculation of gross floor area"; real-estate sale contracts apply GB/T 17986 "Specification for real-estate surveying". (3) Where parties dispute a rule-version update (clause 4.3.2), measurement under the current code may not simply be imposed: where the contract fixes a version, that version governs; where not fixed or inconsistent, the rules specified in whichever document has priority under the contract-interpretation order; where still undeterminable — re-measurable (unit-rate) contracts measure in turn by the rules used in the BOQ issued by the tenderer and in the tender price ceiling compiled by the tenderer; lump-sum contracts measure by the rules used in the bidder's tender (priced offer); where none can be determined, measure per the client's instruction or the expert's professional judgment, with explanation. Rationale: under re-measurable (unit-rate) contracts quantities are the tenderer's responsibility, under lump-sum contracts the bidder's — whoever is responsible for measurement, their rules apply; the expert should verify the rules actually used in the tender BOQ and tender price ceiling, by recomputation where not stated.

Applicable Boundaries

Applies to determining "rule application" in construction cost expert assessment (judicial appraisal) and final account disputes; at preparation of the bill of quantities, quantities follow the method of measurement set out in the appendices to the BOQ-based pricing standard (GB 50861-2013 clause 4.2.5, mandatory provisions of codes) — outside this dispute scope; contract agreement always prevails, and quantities jointly signed by both parties are determined per the signed content.

Further Reading

T/ZBD 100.4-2023 "Guidelines for construction cost expert assessment (judicial appraisal) practice" clauses 4.3.1, 4.3.2 and their commentary; GB 50861-2013 "Code for quantities of urban rail transit works" clause 4.2.5 (mandatory provisions of codes); GB/T 50353-2013 gross floor area calculation; GB/T 17986 real-estate surveying; contract-price provisions of GB/T 50500-2024.

Keywords