Adjustment of contract prices of signed works upon quota revision or updates of measurement and pricing rules: pure version updates are not adjusted; policy-based rates, government pricing and mandatory standard changes are adjusted

Where a party seeks a contract price adjustment solely on the ground that the measurement rules or pricing rules have been updated, the expert appraiser maintains the pricing principles of the original price determination or tender in the contract and makes no adjustment (T/ZBD 100.4-2023 Article 4.4.8). The exception is Article 4.4.1: where government-fixed and government-guided price items, policy-based rates or national mandatory standards change after the tender deadline, the appraiser adjusts the price of the works executed after the time of change, whatever the contract says, issuing alternative opinions with explanations; but where the contract has expressly agreed the risk allocation for such element prices, the contract governs. Under BOQ pricing, price changes caused by laws, regulations and policy changes after the base date (newly added, amended or repealed provisions, changed government interpretations) are adjusted per GB/T 50500-2024 Article 8.8.1, and the overheads and profit within the total price and unit rates are not adjusted (8.8.5); where national fiscal and tax policy changes the VAT rate, VAT is computed at the new rate and the price adjusted by the difference between the old and new rates (8.8.6). The appraisal method is also chosen by contract type (T/ZBD 100.4-2023 Article 4.2.4).

Applicable Codes

  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.4.1条、第4.4.8条、第4.2.4条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.8.1条、第8.8.5条、第8.8.6条
  • 国家标准管理办法(国家市场监督管理总局令第59号)第三十五条
  • 《价格法》第十二条
  • 《民法典》第一百五十三条、第四百六十五条
  • https://zfcxjst.hebei.gov.cn/hbzjt/xwzx/sxdt/101772191565271.html
  • https://zfcxjst.guizhou.gov.cn/ztzl_69/gczjzl/202601/t20260120_90164510.html
  • https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1765333864808116224.html
  • https://www.mohurd.gov.cn/xinwen/gzdt/art/2026/art_7dec586cbdf947c7b46617e76c7bb7a9.html

Scope of the question

Whether the contract price of signed (including under-construction) works can be adjusted when the quota is revised or the measurement or pricing rules are updated - the core being to separate pure pricing-rule / quota version updates from policy-based rates, government-fixed and guided price items and national mandatory standard changes, with the supporting adjustment and VAT rules under BOQ pricing.

Core conclusions

1) Pure pricing-rule / quota version update - maintain the original pricing principles, no adjustment. T/ZBD 100.4-2023 Work Guidelines for Construction Cost Expert Assessment, Article 4.4.8: where a party requests a contract price adjustment on the ground that the measurement rules or pricing rules have been updated, the appraiser shall maintain the pricing principles of the price determination or tender in the contract and make no adjustment, except as provided in Article 4.4.1 of these guidelines.

2) Exception: policy-based rates, government-fixed and guided price items, national mandatory standards changing after the tender deadline - adjusted. Article 4.4.1: under lump-sum or re-measurable (unit-rate) contracts alike, where a party requests adjustment because government-fixed and government-guided price items, policy-based rates or national mandatory standards changed after the tender deadline, the appraiser seeks the client's view; where the client holds the contract covers the situation and should govern, the appraiser proceeds as instructed; where the client is not specific, the appraiser adjusts the price of the works executed after the time of change, issuing alternative opinions with explanation. Commentary points: Article 12 of the Price Law - operators shall abide by laws and regulations and comply with lawfully set government-guided prices, government-fixed prices and statutory price intervention and emergency measures. Article 153 of the Civil Code - civil juristic acts violating mandatory provisions of laws and administrative regulations are void; Article 465 - contracts lawfully formed are protected by law. Accordingly, when such items change after the tender deadline, whatever the contract provides, the appraiser adjusts the price of the works after the change; but where the parties have expressly agreed the risk allocation for government-fixed and guided element prices, that agreed allocation governs and is noted in the opinion.

3) BOQ pricing basis (GB/T 50500-2024 Section 8.8): Article 8.8.1: during performance, where the following laws, regulations and policy changes after the base date cause price or time changes, the parties adjust per the contract and the rules published by national, provincial or industry construction authorities: 1 newly added provisions; 2 amended provisions; 3 repealed provisions; 4 changed government interpretations of relevant laws and regulations. Article 8.8.5: where laws and policy changes adjust the contract price, the overheads and profit within the total price and unit rates are not adjusted; save as otherwise agreed, they do not move with such adjustments. Article 8.8.6: where national fiscal and tax policy changes the VAT rate during performance, pricing and payment after the new rate takes effect carry VAT at the new rate, the difference against VAT at the base-date rate adjusting the contract price; the relevant prices and adjustment amounts in the total price paid after the change likewise carry VAT at the new rate.

4) The appraisal method follows the contract type (T/ZBD 100.4-2023 Article 2.4). For lump-sum or lump-sum-priced contracts, following relative fixity of the total price, adjust only the contents expressly adjustable, variations and claims; for re-measurable (unit-rate) contracts, following relative fixity of the all-in unit rates, adjust only expressly adjustable contents, quantities, variations and claims; for cost-plus contracts, compute direct costs per the agreed measurement and pricing rules and fee per the agreed percentage or amount. A version update alone therefore cannot overturn the fixed total price or all-in unit rates.

5) Transition periods of new standards: Article 35 of the Measures for the Administration of National Standards (SAMR Order No. 59): a reasonable transition period shall be left between issue and implementation of a national standard; between issue and implementation, enterprises may execute either the old or the new standard; on implementation of the new standard the old one is repealed. Transitions for local quota revisions are set by provincial housing and construction authorities.

Applicability limits

  • Applies to adjustment disputes and settlement review of signed / under-construction works; not to repricing of unsigned works under a new quota (see the old-to-new quota migration card).
  • The triggering cause must fall after the tender deadline (BOQ basis: after the base date); prices before the change point are not adjusted.
  • Where the contract expressly allocates the risk of government-fixed and guided element prices, the contract governs; conversely, even without contract provision, Article 4.4.1 situations are adjusted.
  • A pure quota or pricing-rule revision is not of itself a price-adjustment ground; check whether it also amounts to a policy-rate or mandatory-standard change.
  • Version disputes over the measurement rules themselves (re-measurable contracts: tender BOQ then ceiling-price rules in turn; lump-sum: tender pricing rules) are a separate question - see the referenced card.
  • Liability for extension caused by laws and policy changes and the list of adjustment matters: the other articles of Section 8.8 and Section 8.1 of GB/T 50500-2024.