GB/T 50500-2024 clause set 8.8: adjustments of contract price and duration for changes in laws, regulations and policies - scope, the one-way adjustment rule during extended durations, and no adjustment of overheads and profit
GB/T 50500-2024 clause 8.8: for laws, regulations, policy provisions or government interpretations newly enacted, amended or repealed after the contract base date, price and/or duration adjust per the contract and the rules published by the authorities; policy changes during contractor-caused extension adjust downward only (8.8.2), during employer-caused extension upward only (8.8.3); where policy change causes material extension and subsequent abnormal market price moves, the price-fluctuation rules apply (8.8.1/8.8.2/8.8.3); overheads and profit inside the total and unit prices never adjust for policy changes (8.8.5).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第8.8.1条
- GB/T 50500-2024 第8.8.2条
- GB/T 50500-2024 第8.8.3条
- GB/T 50500-2024 第8.8.5条
- GB/T 50500-2024 第8.7节(物价变化)
- GB/T 50500-2024 第8.11节(工程索赔)
Positioning
The rules of GB/T 50500-2024 clause 8.8 on price and duration adjustment for legal and policy change: scope (four classes after the base date), the one-way direction of adjustment during extended durations (the party causing the delay bears the risk), the route for policy-induced abnormal market moves, and the no-adjustment boundary for overheads and profit.
Core conclusions
1. Scope: four classes of change after the base date (8.8.1)
"During performance, where the following changes after the contract base date increase or decrease the contract price and/or delay the works, the parties shall adjust per the contract and the rules published by national, provincial or industry authorities: 1 newly enacted laws and policies; 2 amended laws and policies; 3 repealed laws and policies; 4 changed government interpretations." Enactment, amendment, repeal and interpretive change are all adjustable events; the basis is the contract plus the authorities' published rules, not fresh bargaining.
2. One-way adjustment during extended durations (8.8.2, 8.8.3)
- Contractor-caused extension (8.8.2): "upward adjustments are not allowed; downward adjustments are made."
- Employer-caused extension (8.8.3): "downward adjustments are not allowed; upward adjustments are made." Summary: the party causing the delay bears the policy risk of the extension - a delayed contractor takes only cuts, a delayed employer only rises. Changes within the normal duration adjust both ways under 8.8.1.
3. Policy change triggering abnormal market moves
8.8.1 closing (repeated by 8.8.2/8.8.3): "Where legal or policy change causes material extension of duration and the works after the planned progress date meet market price changes and abnormal fluctuation, the parties shall adjust the affected contract price under the price-fluctuation rules." The policy change itself adjusts under 8.8; its knock-on price swings go to clause 8.7 (scope, base prices, risk band, formulas per 8.7 and Appendices A and G) - the two channels never double-claim the same money.
4. Overheads and profit never adjust (8.8.5)
"Where laws and policies cause price adjustment, the overheads and profit within the total and unit prices are not adjusted." The commentary: "save as otherwise agreed, the overheads and profit included in the total and unit prices do not adjust owing to legal or policy change." Only the directly affected labour, material, plant and rate costs adjust - never a further overhead or profit load on the adjustment.
Applicable boundaries
- The contract base date is the time line: changes published or effective before it are outside 8.8.
- The 8.8.5 bar is a default - express contract terms govern.
- The one-way rules presuppose a fixed responsibility for the extension - apportion delay first, then direction; no extension or undetermined responsibility means two-way adjustment under 8.8.1.
- Policy-induced price swings go to 8.7 - no double application of 8.8; ordinary price moves, BOQ errors, variations and claims run under 8.7, 8.2, 8.9 and 8.11 respectively.
- This card covers adjustment rules only; at settlement the policy adjustment is listed as item 8 of clause 10.3.2.
Further reading
- GB/T 50500-2024 clauses 8.8.1~8.8.5; clause set 8.7 with Appendices A and G; clause 8.11; clause 10.3.2 item 8.
- Related: the base-date definition and contract type jointly fix the practical boundary of policy adjustment.
Keywords
- 法律法规及政策性变化
- base date
- 第8.8条
- 工期延长期间调价
- 管理费利润不调整
- cost fluctuation
- adjustment of the contract price