Setting overheads and profit in repricing variations and other price adjustments (GB/T 50500-2024 Articles 3.6.6, 8.4.6, 8.8.5, 8.9.1)

On repricing (no identical or similar rates), GB/T 50500-2024 Article 8.9.1 negotiates a market-reasonable all-in unit rate - by reference to the pricing rules and pricing level of analogous contract rates or to analogous items of similar works; the expert-assessment basis is reasonable cost plus the contract overheads and profit rates (T/ZBD 100.4-2023 Article 4.6.2), the supervision basis the cost-plus-profit principle (GB/T 50319-2013 Article 6.3.3). Similar-rate conversion (tier 2) swaps only the differing elements, the original overheads and profit preserved. Where employer-supplied materials become contractor-purchased, add to the original all-in unit rate the material cost (with reasonable wastage) plus overheads and profit, at the rates of the item's rate build-up or the nearest analogous item (Article 3.6.6). Reverse rules: on laws and policy changes, the overheads and profit within the total price and unit rates are not adjusted (8.8.5); provisional-sum materials adjust only the pre-tax provisional material price, nothing else (8.4.6); fluctuation differentials carry VAT only, no overheads or profit (3.3.5).

Applicable Codes

  • GB/T 50500-2024 第3.3.5条、第3.6.6条、第8.4.6条、第8.6.3条、第8.8.5条、第8.9.1~8.9.3条
  • T/ZBD 100.4-2023 第4.6.2条
  • GB/T 50319-2013 第6.3.3条

Scope of the question

How overheads and profit within all-in unit rates are set in variations and price adjustments - chiefly the charging basis when repricing is needed (no applicable or similar rates), and whether overheads and profit move with legal changes, fluctuation, or the pricing of provisional-sum materials. Per GB/T 50500-2024 and the companion assessment and supervision bases.

Core conclusions

1) Repricing basis (Article 8.9.1 tiers 3-4). Items executed under identical conditions but with differing item descriptions (or vice versa) may negotiate a market-reasonable all-in unit rate per the works as executed, by reference to the pricing rules and tender level of analogous contract rates; items differing in both - by reference to analogous items of similar works. The repriced level thus returns to the contract's pricing rules and analogous tender levels, never detached from the original pricing system. Where the contract has neither identical nor analogous items, the assessment basis (T/ZBD 100.4-2023 Article 4.6.2 item 3): a new rate from reasonable cost per the contractor's appraisal records plus the contract overheads and profit rates, or from the local or industry pricing basis plus those rates; the supervision basis (GB/T 50319-2013 Article 6.3.3): failing agreement, the chief supervising engineer sets the reasonable rate on the cost-plus-profit principle. Both share: reasonable cost as base, the rates from the contract (or from analogous items within it). 2) Similar-rate conversion preserves overheads and profit. Tier 2 converts the contract rate of an analogous item adjusting only the differing elements (materials, method, conditions); the original overheads and profit levels stand - no re-quoting; they reset only on repricing (tiers 3-5). 3) Employer-supplied materials becoming contractor-purchased (Article 3.6.6). After the contractor's written acceptance, add to the original item's all-in unit rate the material cost fixed by both parties (including reasonable wastage) plus overheads and profit, forming the corrected rate; overheads and profit may reference the charging standard of the rate build-up of the nearest analogous item; the rates may follow the build-up table, wastage following Article 3.6.2. Where the total price already carries attendance and coordination provisions for those materials, deduct per Section 8.5. 4) Laws and policy changes (Article 8.8.5). The overheads and profit within the total price and unit rates are not adjusted for such changes; save as otherwise agreed, they do not move with the resulting price adjustments. 5) Provisional-sum materials (Article 8.4.6). Adjustments touch only the provisional material price within the rate (pre-tax); the other cost elements of the rate are not adjusted - overheads and profit unmoved. 6) Fluctuation differentials (Article 3.3.5). Differentials of labour, materials and fuel-power carry VAT, not overheads or profit; the overheads-profit risk is priced by tenderers as risk fees. 7) Dayworks all-in unit rates (Article 8.6.3). Absent priced dayworks items or applicable rates, labour, material and plant prices come from the contract's agreed published price sources or, failing that, the net-of-tax market prices published locally or by the industry and the detail prices of analogous rate build-ups - overheads and profit sit inside the resulting dayworks rates, never added on top.

Applicability limits

Applies to BOQ-priced building and similar works in variations, provisional sums, fluctuation and legal changes. The core premise is contract first: rates take the contract values or the build-up tables of analogous contract items; only absent agreement do the assessment / supervision fallbacks (reasonable cost plus contract rates) apply; contracts expressly linking overheads and profit to policy or prices govern. Not for production equipment procurement or independent fees; highway and railway works follow their industry standards. This card does not cover the preliminaries adjustment procedure (see the preliminaries card).

Further reading

GB/T 50500-2024: Articles 3.3.5, 3.6.6, 8.4.6, 8.6.3, 8.8.5, 8.9.1 to 8.9.3; with T/ZBD 100.4-2023 Article 4.6.2 and GB/T 50319-2013 Article 6.3.3; the make-up of all-in unit rates per Article 2.0.9.