Three-tier re-rating of all-in unit rates after changes in item description/work content: retain the contract unit rate, convert the contract unit rate, or negotiate a new rate (GB/T 50500-2024 Clause 8.9.1)
Changes in item description/construction conditions are handled in three tiers: identical -> retain the contract unit rate; similar -> convert and adjust the contract unit rate (replace only the price differential of the differing factor, keeping management fee and profit); different -> negotiate a rate on the reasonable-cost-plus-profit principle. Judgment factors include materials, construction methods, foundation/height/member specifications, season, transport mode, etc.; where accompanied by quantity changes beyond 15%, the unit rate is reasonably reduced for increases and reasonably raised for decreases; contractual agreement takes precedence.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.2.1条、第8.9.1条、第8.9.2条、第8.9.3条、第8.10.3条
- T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.4.4条
- GB/T 50319-2013 · Code for Construction Project Supervision 第6.3.3条
Topic Positioning
Answers "after the item description / work content / construction conditions of a billed (BOQ) item change, can the original all-in unit rate still be used and how should it be re-rated" — the three-tier judgment framework (retain / convert / negotiate) per GB/T 50500-2024 Clause 8.9.1, applicable to re-rating of unit rates arising from variations and errors and omissions in the BOQ.
Core Conclusions
Three-tier rules: (1) identical construction conditions + identical item description -> directly adopt the corresponding contract unit rate, no adjustment; (2) similar item description or similar construction conditions -> use the contract unit rate of a similar billed (BOQ) item after conversion and adjustment, most commonly for material changes: new all-in unit rate = original all-in unit rate - original material cost + new material cost (per the consumption in the original rate build-up x the new material price), keeping the levels of management fee, profit, and risk cost and replacing only the differing factor; (3) different item description or different construction conditions -> negotiate a market-reasonable all-in unit rate combining similar-item pricing rules and bid levels; where no identical/similar item unit rate exists, determine it on the reasonable-cost-plus-profit principle (DB37/T 5028-2022 Clause 9.3.2). Judge the degree of change by two factor groups: description-related (materials, construction methods, impact on other divisional/sub-divisional works, etc.) and condition-related (foundation, height, member specifications, construction season, material transport mode, machinery usage, etc.). Linked rules: where BOQ quantities increase or decrease by more than 15% simultaneously, the unit rate is reasonably reduced for increased quantities (procurement discounts) and reasonably raised for decreased quantities (Clause 8.9.2); for lump-sum contracts, whether the contract unit rate applies to valuation of variations decides adjustment or negotiation (Clause 8.9.3); under re-measurable (unit-rate) contracts, where contract drawings and the priced BOQ are inconsistent during performance, the BOQ governs (Clause 3.4.5); under fixed unit-rate contracts the all-in unit rate must not be adjusted except for agreed adjustable situations (T/ZBD 100.5-2023 Clause 3.1.6).
Applicable Boundaries
Applies to valuation of variations and BOQ errors/omissions under BOQ-priced unit-rate/lump-sum contracts; where the contract explicitly agrees on the valuation of variations (e.g., only material price differential conversion, no adjustment within the risk band), the contract governs. Whether a change is "similar" or "different" should first be confirmed in writing by both parties before deciding to retain, convert, or re-price. Not applicable to adjustment for cost fluctuation (Section 8.7), determination of provisional sums (Section 8.4), or other independent price-adjustment rules. The 2024 edition is more flexible than the 2013 edition — contractual agreement takes precedence over the national standard's default rules.
Further Reading
See GB/T 50500-2024: Clause 2.0.27 (errors and omissions in the BOQ), Clause 3.4.5 (drawings inconsistent with the BOQ — the BOQ governs), Clause 4.1.7 (five elements of a billed (BOQ) item), Clause 8.2.1 (re-measurement of errors and omissions and the 15% boundary), Clauses 8.9.1-8.9.3 (three-tier re-rating and the beyond-15% linkage), Clause 8.10.3 (differing factors for additional works retaining contract unit rates); companion standards T/ZBD 100.4-2023 Clause 4.4.4 (judicial-appraisal caliber), T/ZBD 100.5-2023 Clause 3.1.6 (final account review), DB37/T 5028-2022 Clause 9.3.2 (supervision valuation of variations), GB/T 51262-2017 Clause 5.6.1 (appraisal of variation disputes).
Keywords
- 综合单价确定
- derivation of new (built-up) rates
- 类似单价换算
- 项目特征变化
- 施工条件变化
- 15%边界
- 8.9.1
- GB/T 50500-2024
Cited By
- ←
Judging the code non-compliance of 'cut only, never add' in final account review, the clause basis for the contractor's claim to symmetric upward review (the full-review method, objective and fair deliverables, two-way quantity-difference pricing, BOQ errors on the employer), and the entrances for upward adjustment and the written-objection remedy
'Cut only, never add' has no code basis: GB/T 51095-2015 clause 8.3.5 requires the full-review method for final account review, barring key, sampling or analogy methods, and clause 1.0.3 requires fair stand, conduct, procedure, method and deliverables; T/ZBD 100.5-2023 clause 4.2.3 requires the review report to state the disallowed and the added prices and rates with item-by-item reasons. The quantity-difference rules are themselves two-way: GB 50500-2013 clause 9.6.2 lowers the all-in rate on the added part beyond +15% and raises it on the remaining part beyond -15%; GB/T 50500-2024 clause 8.2.1 splits at 15% (inclusive / exclusive) with the mirrored pricing of clauses 8.9.1 and 8.9.2. The accuracy and completeness of unit-rate work-item lists rest on the employer (clause 3.1.8) - the normative entrance for upward review - but the contractor must file itemised written objections within the agreed time, silence being deemed acceptance (clauses 10.3.8, 10.3.10).
- ←
Documents for re-verifying quantities after pipes (M&E, water and drainage) change position on site, the interlocking requirements with site instruction records, and the outsourced-surveying and construction cost expert assessment routes for disputes, with standards citation
Quantity re-verification after pipe position changes is variation measurement, not a re-survey of the site: under GB/T 50500-2024 clause 7.4.2 (unit-rate contracts) the bill items and quantities are re-computed from the variation instruction issued or confirmed by the Employer and the actual construction drawings and compared with the defect-corrected bills to fix the differences; under clause 7.4.3 (lump-sum contracts) the variation instruction and actual construction drawings are compared with the contract drawings, the differing part being the variation items. Nine document sets are required: variation instruction or order, plans before and after the change (isometrics at complex pipeline nodes), site measurement records, supervision confirmation opinions, before-and-after quantity comparison tables (differences only, formulas attached), images and concealed-work acceptance records, acceptance certificates and material ledgers, and as-built drawing annotation. Records interlock with variation orders through bidirectional number cross-reference, attached difference formulas, complete attachment sets, signature levels and time limits - the iron rule being order first, record after. Pipe-position adjustments from the Contractor's own detailing do not adjust the price (clause 3.3.9). Disputes follow joint re-survey, third-party measurement (results not directly guiding construction), qualified testing, site inspection in expert assessment, and a five-grade opinion path.
- ←
Re-measurement and price splitting after rebar substitution: re-measure from the variation drawings, count the quantity once only (lap and wastage coverage), the splitting formula of the quantity difference at the contract rate plus the material price difference carrying VAT only, and the 15% clause boundary among adopting the contract rate / converting an analogous rate / building up a new rate (GB/T 50500-2024 cl. 7.4.2, 8.2.1, 8.9.1, 8.9.2 and 3.3.5)
After a rebar substitution, re-measure from the variation instruction and the as-built construction drawings (GB/T 50500-2024 cl. 7.4.2) and count the quantity once only (laps only where shown by the design or by codes; erection wastage enters the quota content). Price splitting: dC = dQ x P1 + Q2 x dp - the quantity difference is priced at the contract (or re-banded) all-in unit rate, and the material price difference carries VAT only, with no overheads or profit (cl. 3.3.5). Rate banding takes 15% as the line: where the billed quantity change does not exceed 15% (inclusive), the five bands of cl. 8.9.1 apply (same conditions and same item description -> the contract rate; analogous description or analogous conditions -> a converted analogous rate; otherwise a negotiated rate build-up); beyond 15% (exclusive), cl. 8.9.2 applies and the rate is lowered or raised for the change in procurement discounts brought by the quantity gain or loss. Routine grade and size substitutions mostly land in the 'adopt the contract rate / convert an analogous rate' bands, not in a new rate build-up.
- ←
Differences in final account adjustment between lump-sum contracts (fixed total price) and unit-rate contracts (fixed unit rates): treatment rules for quantity changes, BOQ errors, design changes and cost fluctuation, mapped to GB/T 50500-2024 clause numbers
GB/T 50500-2024 uses 'lump-sum contract / unit-rate contract' rather than 'fixed total price / fixed unit rate'; the substantive difference lies in the allocation of quantity and price risk. A lump-sum contract wraps up both quantities and prices - the measured-works BOQ items need not be re-measured, and price changes arising from BOQ errors are deemed included in the contract total and are not adjusted during performance (clauses 4.1.6, 7.2.2, 8.2.3); only 'provisional quantity' unit-rate-priced items and variations may be adjusted. A unit-rate contract fixes the rates and re-measures the quantities - all BOQ items and quantities of the measured works must be re-measured, BOQ errors fall on the employer, and quantity changes are priced under clause 8.9.1 or clause 8.9.2 depending on the 15% (inclusive / exclusive) boundary (clauses 2.0.6, 4.1.4, 8.2.1). The adjustment rules for cost fluctuation (where no band is agreed, adjustment under Annex A is allowed once the movement exceeds 5%, the differential bearing VAT only, with no overheads or profit) and for changes in laws and regulations and policy are identical for both contract types.
- ←
Trigger table for the +/-15% quantity deviation threshold: the three outcomes of retaining the original price, adjusting the rate and deriving new rates, and the dividing lines between them (GB/T 50500-2024 Articles 8.2.1, 8.9.1, 8.9.2 and 8.9.3)
Under GB/T 50500-2024 the 15% mark is only a threshold on quantity, and it decides only between 'retain the original price' and 'adjust the rate': where the billed quantity of a BOQ item increases or decreases by no more than 15% (15% included) of the quantity contained in the contract BOQ for that item, the all-in unit rate is set under Article 8.9.1 (item 1: same conditions plus same item description, adopt the contract rate, that is, retain the original price; item 2: similar item description or similar conditions, convert the contract rate of an analogous BOQ item; items 3 to 5: negotiate a market-reasonable all-in unit rate, in substance deriving new rates); where the change exceeds 15% (15% excluded), Article 8.9.2 applies: with an increase, the contract rate and the new all-in unit rates are reasonably reduced to reflect the discounts on labour and material procurement prices; with a decrease, they are reasonably increased to reflect the loss of those discounts. A change of exactly 15% (inclusive) does not trigger the rate-adjustment tier. 'Deriving new rates' is triggered not by quantity but by changes in the item description or the construction conditions; the two lines are independent and can combine.
- ←
Classifying divergence between the design earthwork balance and the actual site balance, allocating responsibility among the four parties, and the cost adjustment pathway (with the chain of evidence and the normative basis)
GB 50201-2012 clause 4.1.3 sets the division-of-duty baseline: the balance figures are 'basic balance data put forward by the designer, on which the contractor then performs balance calculations according to the actual situation ... with multiple balance adjustments further made during construction'; hence divergence between the actual and the design table does not of itself constitute a variation or ground a claim. The divergence must first be characterised into three types - measurement-basis type (conversion factors not unified; whoever miscalculated corrects it), factual type (original ground levels / geology / design omissions; allocated by cause) and fault type (the defaulting party bears it, including enlarged losses) - and responsibility then allocated item by item by cause: erroneous original data from the employer, adverse physical conditions, instructed variations and insufficient design documents are borne externally by the employer (which may recover from the investigator or designer), while the contractor bears its own method adjustments, over-excavation and what it should have foreseen.
- ←
Constituent requirements of BOQ item descriptions and the three common defects (vague description / missing measurable parameters / disconnect from the work process), with corrected drafting (GB/T 50500-2024 clauses 2.0.5, 2.0.27, 4.1.7, 4.2.2, 4.2.4; GB/T 50854-2024 clause 4.1.2)
An item description, by definition (GB/T 50500-2024 clause 2.0.5), is 'a textual description stating the nature and requirements of the BOQ item itself ...'; a description written wrongly falls under clause 2.0.27, BOQ errors (including 'mismatched item description'), and enters the price-adjustment channel rather than mere textual polish. The hard yardstick of accurate description is GB/T 50854-2024 clause 4.1.2 - 'item descriptions must be given accurately and comprehensively ... sufficient to satisfy the need to determine the all-in unit rate' - and they must be 'prepared on the basis of the design documents and in combination with the completion and handover requirements' (GB/T 50500-2024 clause 4.2.2); any parameter whose variation would change labour, material and plant consumption or the basis of percentage charges must be stated, while decorative words that do not change the price are useless if stated.
- ←
Four-axis distinction among variations, additional works, dayworks and claims under GB/T 50500-2024 (triggering events / procedure / time limits / pricing basis) and the fallback positioning of claims
GB/T 50500-2024 clause 8.1.1 lists contract price adjustment matters in eleven categories (including dayworks, variations, additional works and claims) and does not list 'site instruction records' separately - matters signed and certified during construction must be priced through one of these four channels. Boundaries of the four channels: variation = a change of content or conditions within the scope of the contract works (term 2.0.28); additional works = physical works outside the contract scope (2.0.30); dayworks = minor work unsuited to pricing under the measurement and pricing rules (2.0.16; clause 7.5.2 lists ten situations); claim = the fallback channel - clause 8.11.1 provides that only events 'not within the adjustment scope of sections 8.2 to 8.10' are handled as claims, and 'where the price adjustment of an event has already been calculated under the contract price adjustment provisions (excluding claims), no further claim shall be calculated'.
- ←
Whether the employer may refuse to pay for additional works when the actual investment in a government-funded project exceeds the approved estimate: the estimate as an administrative control instrument, who bears the duty to apply for an estimate adjustment, attribution of the causes of overruns, and risk allocation under an EPC lump-sum contract
In principle it may not. The verified investment estimate is an administrative investment-control indicator for a government-funded project, not a cap on the civil contract price nor a condition of payment. Article 23 of the Regulation on Government Investment Projects (State Council Decree No. 712) places the duty to apply for an estimate adjustment on the project unit (the employer); its failure to file the application cannot be turned against the contractor. Whether the price can be adjusted truly turns on the cause of the overrun: employer-instructed variations, raised standards, errors in basic data, and major policy, price or geological changes are payable; contractor design defects, omissions and pricing errors are borne within the lump sum. Failure of the audit or the government fiscal review likewise does not automatically ground a defence ([2008] Min Yi Ta Zi No. 4; Fa Shi [2026] No. 12 Art. 13).
- ←
Allocating the works cost saved through design optimisation in EPC (engineering, procurement and construction) contracting between employer and contractor: the Particular Conditions entry on 'value engineering benefit sharing' is the sole basis of a claim, and no statutory sharing ratio exists absent agreement; the saving must be verified through valuation of variations and stripped of price differentials and similar factors on a like-for-like basis, and under a fixed lump-sum contract the saving usually settles directly as the contractor's cost surplus
No statutory sharing - only contractual sharing: General Conditions of GF-2020-0216, Sub-Clause 13.2.3, reads 'Where a value engineering proposal reduces the contract price, shortens the time for completion or improves the economic benefit of the works, the parties may share the benefit as agreed in the Particular Conditions' - 'may' plus 'as agreed in the Particular Conditions' means there is no sharing claim without agreement; a blank, a slash, or 'to be negotiated separately' in that Particular Conditions entry is presumed to be no variation under Civil Code, Article 544. Sharing amount S = (C0 - C1) x r x k, where r is the contractually agreed ratio (r = 0 if not agreed; the industry '30/70 or 50/50' splits are negotiating convention, not a standard), C0 and C1 must share the same scope, VAT status and base period, and C1 is determined under the variation valuation rules of Sub-Clause 13.3.3.1. Under a fixed lump-sum contract (the default form under Sub-Clause 14.1.1) the contract price is not reduced for optimisation, the saving settles as the contractor's surplus, and no 'allocation' generally arises.
- ←
Price adjustment for quantity increases caused by the contractor's construction-stage design development under an EPC lump-sum contract: no adjustment in principle; adjustment only where the difference constitutes an employer-required variation or arises from employer causes
No adjustment in principle; adjustment only by exception. Where the contractor, as required by the contract, carries out construction-stage design development of the contract drawings and the design development drawings differ from the contract drawings, the contract price shall not be adjusted unless otherwise agreed in the contract or otherwise required by the employer (GB/T 50500-2024 Clause 3.3.9); however, where the difference constitutes a variation required by the employer, the additional costs affected shall be calculated and adjusted under Clauses 7 to 9 of the standard. The construction cost expert assessment position is consistent: where the contractor carries out design development and requests adjustment of the all-in unit rate, the expert assessor generally will not adjust it, unless the contract provides that the contractor's design development drawings serve as the basis for construction payment settlement (T/ZBD 100.4-2023 Clause 4.4.6). Where the difference arises from employer causes (errors in the Employer's Requirements or in base data, changes in laws, regulations and policies, or employer-approved variations) or constitutes additional works outside the contract scope, the price may be adjusted as prescribed.
- ←
Rules for fixing the scope and items of construction cost expert assessment on the variation part of the works: admission filtering of court-commissioned assessment, slicing of the scope, the valuation basis for variations, and cross-examination of assessment materials (Civil Procedure Law Article 79; Fa Shi [2020] No. 25 Articles 29/32/33/34; Fa [2020] No. 202 Articles 1-5; GB/T 51262-2017 Articles 5.5.2/5.5.3/5.6.1)
Assessment resolves only specialised issues in the ascertainment of facts, and the scope must be cut narrow and precise: assessment scope = disputed variation items x within specialised issues (computing money only) x not locked by a settlement agreement or express contractual agreement x assessment materials established through cross-examination. Whether a variation is established, how liability is apportioned, how the contract is interpreted, and the application of law must never be referred to the assessment institution. Where a lump-sum contract has a measurement dispute and no agreed measurement standard, assessment covers the variation part of the works only (GB/T 51262-2017 Article 5.5.3); valuation of variations follows a three-tier path: contract provides -> follow the agreement / provision unclear -> price per actual performance / no provision -> refer the decision to the commissioning party, and where it withholds its decision, an opinion may be issued under the current national pricing standard (Article 5.6.1).
- ←
Deciding claims to adjust the contract price for omitted items in the tender BOQ (BOQ errors) during performance: risk is allocated by the contract pricing method and the BOQ section in which the omission falls - omission from the work-section bills under a unit-rate contract may rest with the employer and be adjusted under section 8.2; a lump-sum contract is in principle not adjusted (except provisional quantity items); the bill of preliminaries is always the contractor's responsibility - with judicial limits and points of procedure and proof
Whether adjustment is possible depends not on the omission itself but on the contract pricing method and the BOQ section in which the omission falls: GB/T 50500-2024 cl. 3.1.8 provides that under a unit-rate contract the accuracy and completeness of the work-section BOQ rest with the employer (adjustment by re-measurement under section 8.2 may be claimed, with a 15% increase or decrease in quantities as the divide between cl. 8.9.1 and 8.9.2); under a lump-sum contract they rest with the contractor, and save for unit-priced items in provisional quantities the contract price and contract time are not adjusted for BOQ errors (cl. 6.1.7 and 8.2.3); the bill of preliminaries compiled on a per-item basis is always the contractor's responsibility, with only statutory safety provisions and similar exceptions adjustable. Where the contract provides settlement at a fixed price and adjustment is claimed for major changes in labour cost or key material prices, the court will not support it (Article 9 of Fa Shi [2026] No. 12).
- ←
Whether a supervising engineer's variation instruction alone, without a formal design change order, can serve as the basis for increasing the contract price - three-layer testing of the supervising engineer's authority, the employer's intention and the factual quantities, with a graded scale of effect
It cannot serve, alone and directly, as the basis for increasing the contract price. A supervising engineer's instruction can prove only the layer that 'the employer consented to the work being carried out'; three further tests must be passed: (1) authority - whether the supervising engineer was authorised by the employer (the construction unit) to confirm the variation (Civil Code Article 170: acts within the scope of duties bind the juristic person, and limits on that scope cannot be set up against a counterparty in good faith; Construction Law Article 31: the supervising engineer is engaged by the employer under a written supervision contract); (2) intention - the employer's sign-off or ratification, or a 'constructed consent' set by the contract (GF-2017-0201 clause 10.4.2; Cai Jian [2004] No. 369 Article 10, deemed approval after 14 days of lapse); (3) fact - the varied quantities are verifiable (Fa Shi [2020] No. 25 Article 20: absent signed site records, the quantities actually incurred may be established from other evidence; T/ZBD 100.4-2023 clause 4.3.6, five-step expert assessment rule). The amount of the price is then calculated separately under the contract or under the pricing standard of the local administrative department in charge of construction (Article 19 of the same interpretation). Where the agreement on the variation is unclear, Civil Code Article 544 presumes that no variation has been made.
- ←
The boundary and pricing routes between BOQ errors and omissions and variations: distinguished by the two comparison benchmarks 'contract BOQ vs contract drawings' and 'contract drawings vs actual construction drawings', mapping respectively to BOQ-error price adjustment under Section 8.2 and variation valuation under Section 8.9 of GB/T 50500-2024
GB/T 50500-2024 Article 7.2.1 draws the line by benchmark: 'a discrepancy between the divisional and sub-divisional work item lists in the contract BOQ and the contract drawings constitutes an error or omission in the bill of quantities' (routed to Section 8.2 - under a re-measurable contract, re-measure under Article 8.2.1 and adjust under Articles 8.9.1/8.9.2 at the 15% threshold; under a lump-sum contract, no adjustment under Article 8.2.3), while 'a difference between the contract drawings and the actual construction drawings constitutes a variation' (quantities computed under Article 7.4.2 and priced under Section 8.9, unaffected by the lump-sum no-adjustment rule for BOQ errors). Mis-characterisation derails both the claim route and the adjustment basis; and once a BOQ error is corrected, no preliminary items other than statutory safety provisions and those under Article 7.2.1(2), and no contract period, shall be adjusted.
- ←
Preliminaries — the "lump sum, no adjustment" principle and the full landscape of adjustable exceptions (GB/T 50500-2024 cl. 3.3.7, 7.3.1)
Under GB/T 50500-2024, the China national pricing standard for BOQ (Code of Valuation with Bill of Quantities of Construction Works), preliminaries follow a lump-sum no-adjustment principle, reflected at three levels: (1) the construction method statement reported at tendering is deemed reasonable and feasible, the cost is priced as a lump sum, and the contractor bears the risk of cost increases arising from adjusting its own method statement (cl. 3.3.7); (2) preliminary items in the priced BOQ shall not be re-measured or adjusted (cl. 7.3.1); (3) preliminaries are not adjusted for changes in costs (cl. 8.7.6 item 3). Exception channels: preliminary works listed as billed (BOQ) items and items the contract requires to be measured (cl. 7.2.1, 7.2.2); statutory safety provisions (per contract); variations (measured per cl. 7.4.4, priced per cl. 8.9); errors and omissions in the BOQ (cl. 8.2.2, 8.2.3); unforeseeable works within provisional sums (cl. 7.7.2); delayed use, removal/re-installation, increase or duplicated provision of the contractor's preliminary items due to the employer, and material changes to the time for completion (costs borne by the employer, cl. 3.3.7). Under re-measurable (unit-rate) contracts, only the statutory safety provisions and BOQ-listed formwork/temporary works etc. are adjustable for BOQ errors and omissions (cl. 8.2.2). Adjustments require "submitting the method statement for confirmation before implementation" (cl. 8.9.6); late submission is deemed waiver, and the other party's late confirmation is deemed acceptance (cl. 8.9.7).
- ←
Recognising preliminaries costs of repeated scaffold erection and dismantling caused by the employer (instructions changing construction sequence): lump-sum exceptions, measurement anchors, pricing methods and procedural requisites (GB/T 50500-2024 clauses 3.3.7, 7.3.1, 7.4.4, 8.9.4~8.9.7, 8.11.10; GB/T 50854-2024 Appendix R, code 011601)
Preliminaries are lump-sum and unadjusted in principle, but clause 3.3.7 lists the exception: 'employer-caused extended use, reworking, addition or re-provision of preliminaries increasing their cost adjusts under chapter 8' - scaffolds re-erected after an employer instruction changing the sequence fall squarely under 'reworking' and 're-provision', with no need to prove excess over the bid scheme's assumptions, though a bid-versus-instructed scheme comparison must show the instruction caused it. Increments measure per 7.4.4 on the employer-approved scheme or actual content (extended use of existing preliminaries and management on non-critical paths never measures); material duration changes price per 8.9.4 as 'extended (shortened) duration x mid-term running costs', new plant and temporary works per 8.9.5; the scheme must be confirmed before execution (8.9.6), silence forfeiting (8.9.7). Codes: GB/T 50854-2024 Appendix R preliminaries run 011601 (scaffolds 011601001, unit 'item', no area rules at BOQ level); 011701 is the 2013 code - area / vertical-projection bases now serve only as increment pricing anchors, never to re-measure the whole scaffold list.
- ←
Pricing clash-detour increments of MEP services: the attribution boundary of detailing versus variation, the valuation entries (8.9.1 / 8.9.2 and 2013's 9.3.1), the material and labour increments of cable-tray extended metres, bends and supports, and the separate claim channel for stoppage and the site-record anchors
Three gates before pricing a detour: (1) difference nature - contract versus actual drawings = variation; refinement within one drawing set is no variation; (2) attribution - the employer's design errors and base-data faults are employer risk; the contractor's routine detailing avoidance is contractor risk, generally unadjusted (T/ZBD 100.4-2023 clause 4.4.6) save contracts settling on the contractor's detailing drawings; (3) the entry - variations with quantity moves within 15% price on the five bands of 8.9.1, beyond 15% on 8.9.2 with purchase-discount adjustments. Quantity magnitude fixes 'how to price', never 'whether to pay'. Stoppage, waiting and idle losses claim separately under 8.11.9 / 8.11.10 - never merged into variation rates.
- ←
Tender BOQ versus priced BOQ - relationship and effect compared: preparing and pricing parties, document status, content differences, accuracy responsibility (2013 edition clause 4.1.2 versus 2024 edition clause 3.1.8 split by unit-rate and lump-sum contracts), benchmark role in settlement (quantity variance under 9.6.2, variation valuation under 9.3.1), effect of unilateral amendment, and the order of precedence of contract documents
The two bills are not two documents but two stages of one bill: the tender BOQ is prepared by the tendering employer stating 'quantities and item descriptions' and issued with the tender documents as the common basis of tender pricing (GB 50500-2013 clauses 2.0.2, 4.1.2 (mandatory provision) and 4.1.3); the priced BOQ is the priced version in which the bidder enters all-in unit rates and lump sums and which becomes part of the contract documents after award (2013 edition clause 2.0.3; the 2024 edition calls it the 'contract bill of quantities', clauses 2.0.18 and 3.4.5), its all-in unit rates being the contract unit rates used for settlement and contract price adjustment. Responsibility follows the basic split 'quantities by the tendering employer (employer), prices by the bidder': clause 4.1.2 of the 2013 edition puts it on the tendering employer in all cases; GB/T 50500-2024 clause 3.1.8 changes course - under unit-rate contracts the employer answers for the measured-works bill (bidders may not alter it; defects are repriced under section 8.2), under lump-sum contracts the contractor answers, and preliminaries are always the contractor's. In settlement, quantity variance follows clause 9.6.2 of the 2013 edition (deviation beyond 15%: the all-in unit rate is lowered for the portion of quantity increase above 15%, and raised for the remaining portion after a decrease beyond 15%), and variation valuation follows the three-tier cascade of clause 9.3.1 (applicable -> analogous by reference -> a rate proposed by the contractor from the pricing methods and published price information combined with the tender price fluctuation rate, submitted to the employer for confirmation).
- ←
GB 50500-2013 Chapter 9 'Adjustment of the Contract Price' at a glance: the 15 adjustable events, their five-category grouping and clause order, the trigger conditions and direction of price adjustment for each event, submission time limits and confirmation (deemed approval) procedures, the order of application when several events coincide, and a clause mapping to GB/T 50500-2024
Clause 9.1.1 of GB 50500-2013 lists 15 adjustable events, and the official commentary groups them into five categories: changes in laws and regulations (9.2); variations (9.3 variation, 9.4 item description mismatch, 9.5 omitted BOQ items, 9.6 quantity deviation, 9.7 dayworks); changes in costs (9.8 changes in costs, 9.9 provisional prices); claims (9.10 force majeure, 9.11 earlier completion, 9.12 delay damages, 9.13 claims); and others (9.14 site instruction records plus other adjustment events agreed by both parties). Clause numbers are easily shifted: changes in costs is 9.8 (not 9.7, which is dayworks); force majeure 9.10; earlier completion 9.11; delay damages 9.12; claims 9.13; site instruction records 9.14. Direction of adjustment: under 9.6.2, where a quantity deviation exceeds 15%, the all-in unit rate of the increased portion beyond 15% is reduced, and where the quantity decreases by more than 15% the all-in unit rate of the remaining portion is increased (reverse correction); 9.3.1 sets a four-tier pricing ladder for variations (an applicable item takes the original rate; a similar item is referenced within a reasonable range; where neither applies, the contractor proposes a rate from published price information x its quoted floating rate for the employer's confirmation; where the published price information carries no price, a lawful market price from market survey is proposed for confirmation); under 9.8.2, where no band is agreed and a unit rate changes by more than 5%, the portion beyond 5% is adjusted. Where events coincide: if a variation also causes a quantity deviation above 15%, that item's rate is adjusted under 9.6.2 (clause 9.3.1 paragraph 1), preliminaries move in linkage under 9.6.3/9.3.2, and cost fluctuation is separately adjusted under Annex A for the price differential only, without double counting.
- ←
Contract price adjustment caused by missing items in the tender bill of quantities: the clause chains of the three entries of GB 50500-2013 section 9.5 (9.5.1 to 9.3.1, 9.5.2 / 9.5.3 to 9.3.2), the four-tier valuation of all-in unit rates for new divisional and sub-divisional works items, the three-tier determination of new preliminaries, the itemisation test between unit-rate and lump-sum preliminaries, and the distinction from the quantity-deviation preliminaries linkage trigger path of clause 9.6.3
GB 50500-2013 splits 'missing BOQ items' into three mutually non-substitutable clause chains: 9.5.1 (missing divisional and sub-divisional items) fixes the rate under the four tiers of 9.3.1; 9.5.2 (new works items bringing changes to preliminaries) adjusts under 9.3.2 after the implementation plan is approved; 9.5.3 (missing preliminaries items themselves) both fixes rates under 9.3.1 and adjusts preliminaries under 9.3.2, and the plan must be submitted to the employer for approval first. The three tiers of 9.3.2: mandatory HSE provisions are calculated per 3.1.5; unit-rate preliminaries have their rates set per 9.3.1; lump-sum (or factor-based) preliminaries follow the actual adjustment amount x the contractor's quoted-price fluctuation rate. Failure to submit the plan in advance is deemed no adjustment of the preliminaries or waiver of the right to adjust. Missing items go through 9.5 / 9.3; only quantity deviations of original BOQ items over 15% (exclusive) go through 9.6.2 to adjust the all-in unit rate, with 9.6.3 adjusting factor-based or single lump-sum preliminaries up or down - the two paths must not be mixed.
- ←
Price adjustment findings for 'mismatching item descriptions' under GB 50500-2013 Section 9.4: the elements of cl. 9.4.1/9.4.2, re-determining the all-in unit rate per the as-executed item description using the cl. 9.3 method, and the clause mapping after the 2024 edition merged this event into 'errors and omissions in the BOQ'
GB 50500-2013 cl. 9.4.2 provides: where, during performance, the design drawings (including design changes) mismatch the item description of any item in the tender BOQ and that change causes an increase or decrease in the cost of the item, the all-in unit rate shall be re-determined per the item description as actually executed, under the relevant clauses of Section 9.3, and the contract price adjusted. The four findings elements are: the comparison base is the pair of tender drawings / tender BOQ; any item; a cost increase or decrease is caused; pricing per the actual description with the method borrowed from Section 9.3. The responsibility basis is cl. 4.1.2 (a mandatory provision of codes): the accuracy and completeness of the tender BOQ are the tendering employer's responsibility. The 2013 edition has been superseded by GB/T 50500-2024, which merges mismatching item descriptions, erroneous and omitted items and quantity deviations into 'errors and omissions in the BOQ' (cl. 2.0.27), entering through cl. 8.2.1 and priced through cl. 8.9.1/8.9.2.
- ←
The 'implement first, complete the formalities later' rule for administrative procedures in emergency rescue and urgent repair situations: breaking into urban roads first for urgent repair of pipeline faults with the approval formalities completed within 24 hours, written reporting of design changes caused by emergency rescue within 10 working days, cost-plus-fee contracts recommended for emergency rescue works, and prior implementation not exempting the variation quotation obligation
'Implement first, complete the formalities later' is allowed in emergency rescue situations: where a pipeline buried under an urban road fails and urgent repair is required, the road may be broken into for repair first while the municipal engineering administrative department and the public security traffic management department are notified at the same time, and the approval formalities shall be completed within 24 hours as required (Regulations on Urban Road Management, Article 34); design changes of port engineering projects caused by emergency rescue may be organised and implemented first, but shall be reported in writing to the design change approval department within 10 working days and the change formalities completed in time (Provisions on the Administration of Port Engineering Construction, Article 37); for emergency rescue, disaster relief or particularly complex works, cost-plus-fee contracts are recommended (GB/T 50500-2024 clause 3.4.3). Prior implementation does not exempt the quotation, record-keeping and settlement obligations at the contract price level.
- ←
Procedures for handling contract price adjustment matters under GB/T 50500-2024 section 8.1: the five steps submission - checking - re-checking - further review - confirmation, the two-way forfeiture rules under which each party's silence is deemed approval, the link between signing the output documents and concurrent payment with progress payments / stage settlement payments, and the boundaries against the prior scheme submission for preliminaries and the price review for additional works
Under GB/T 50500-2024 section 8.1, contract price adjustments are handled through 'submission - checking - re-checking - further review - confirmation': the contractor measures the quantities under chapter 7, prices the adjustment under sections 8.2 to 8.11 and submits both with the supporting documents to the employer for checking within the agreed time (8.1.2); the employer verifies within the agreed time and either notifies confirmation in writing or replies in writing with checking comments, and if it neither confirms nor comments, the contractor's report is deemed accepted (8.1.3); after receiving the checking comments the contractor re-checks within the agreed time, and if it neither confirms nor comments, the employer's comments are deemed accepted (8.1.4); the parties sign the measurement and pricing output documents, which become the payment basis under chapters 9 and 10, and the adjusted additional (reduced) price is paid concurrently with the progress payments and the interim settlement payments by construction stage (8.1.6). All periods run 'within the agreed time'; the standard sets no uniform number of days.
- ←
Recasting the concrete volume increment and the formwork contact-area increment after section-size changes to concrete members, why the two move out of step (volume is quadratic in size, formwork linear), the layered order of computation for linked rebar costs, and the tie-in with the 15% quantity-deviation clauses
Concrete is measured by design volume (m3) and formwork by contact area with the concrete (m2) - two independent BOQ items and two geometric functions, so they cannot move in step. With length unchanged, the concrete increment dV = (A_c1 - A_c0) x L; the formwork increment dA = (C1 - C0) x L + (A_b1 - A_b0). The section area b.h is homogeneous of degree 2 in the sizes while the section perimeter 2(b+h) is degree 1: scale the section by k on both sides and volume grows by k^2 but formwork by k - a column with both sides enlarged 5% gains about 10.25% volume but only 5% formwork. After the change, measurement = original BOQ quantity plus or minus the increment; whether the quantity change triggers rate renegotiation follows the 15% bands of GB/T 50500-2024 clauses 8.9.1/8.9.2.
- ←
Characterisation, variation and site-record procedures, the variation valuation ladder, the additional-haul cost formula and the no-double-counting rule when the spoil site (spoil point / waste reception site) is changed and haul distance and disposal costs move
A spoil site changed for reasons not attributable to the contractor (a government dumping ban, expropriation of the site, a different site nominated by the employer, or insufficient capacity of the original site) is a variation under GF-2017-0201 cl. 10.1 item (4), 'changing the baselines, levels, positions and dimensions of the works'; it may proceed only after a variation instruction countersigned by the employer is received, and the unit rate is fixed by the four progressive items of GB 50500-2013 cl. 9.3.1 (an applicable rate is adopted; with no applicable but an analogous rate, reference within a reasonable range; with neither, the contractor proposes from documents, measurement and pricing methods, published price information and its price fluctuation rate for employer confirmation; where the published price information lists no price, a market price with a lawful basis applies). A haul distance change is not a quantity deviation and the 15% rule does not apply; spot site swaps and temporary double-handling instructed on site by the employer are handled as site instruction records under Section 9.14 (record report submitted within 7 days, employer verifies within 48 hours, silence past the limit means deemed approval, pricing within 7 days of completion and payment with the same-period progress payment). Note that site instruction records sit in Section 9.14 -- Section 9.10 is force majeure; the same facts may be priced through either variation or site record, never both.
- ←
Classification basis and table numbers for soil and rock on site (soft rock / hard rock / boulders), the threshold position on measuring boulders as rock, and the price adjustment boundary where the actual class differs from the BOQ item description
BOQ item descriptions are entered per Table A.4.3-1 of GB/T 50854-2024 (soil classes 1-4, judged by soil name plus excavation method) and Table A.4.3-2 (extremely soft rock through extremely hard rock); where classes cannot be fixed precisely, describe from the geotechnical investigation report. The quota-system classes 'loose rock / sub-hard rock / ordinary hard rock / extra-hard rock' (Protodyakonov I-XVI) are not listed in the BOQ classification tables and must not be entered as item descriptions. Boulders: the building works position has only a qualitative boundary - clearance of natural obstructions 'removable together with the earthworks' is already inside the earthwork items, while boulders needing separate breaking or crushing are listed separately as rock or handled as missing items or variations; the water sector position expressly measures boulders larger than 0.7 m3 as rock excavation. Where the class differs from the BOQ description, under a unit-rate contract the all-in unit rate is re-determined on the item description actually constructed (GB 50500-2013 clause 9.4.2), with a 15% quantity deviation as the boundary for rate adjustment (clause 9.6.2).
- ←
Whether a site instruction record confirming quantities equals approved payment: layered test of evidentiary force, routes for fixing the unit rate, agency effect of sign-off beyond authority, and the settlement treatment of ratification or refusal (including the clause requirements of GB 50500-2013 section 9.14)
It does not. A site instruction record confirming quantities settles only the factual layer of what was done and how much; payment is the contractual and legal result of quantity x price (including percentage charges and taxes), and needs a separate price confirmation or re-determination under the variation valuation rules. Basis: GB/T 50500-2024 clause 12.2.1 anchors the force of such records as 'written documents signed and confirmed within the scope of duties shall be valid vouchers for construction pricing, except where other valid evidence proves them false' - evidence, and rebuttable; the commentary to GB 50500-2013 clause 9.1.1 states that 'depending on their content, site instruction records may fall under variations, under claims, or may not involve adjustment of the contract price at all'; where only the quantity is recorded, the price falls back to the variation valuation tiers of clause 9.3.1 (applicable rate -> conversion from similar rates -> derivation of new rates). Sign-off beyond authority is judged under Civil Code articles 170 to 172: acts within the scope of duties bind the legal person, and limits on that scope cannot be set up against a counterparty in good faith; unauthorised or ultra vires agency binds the principal only after ratification, the counterparty may demand ratification within 30 days and silence counts as refusal; where the counterparty has reason to believe the actor has authority, the act is effective.
- ←
Attribution of quantity gaps between BOQ quantities and quota quantities, and the rate conversion: all-in unit rate P = Sum(Tn) / Q, four destinations of quantity gaps (into the BOQ quantity / into the rate / into quota consumption / into the risk allowance), and conversion points for typical work items
BOQ quantities and quota quantities must be kept on two separate tracks and never swapped: first attribute each quantity gap to one of four classes - content already built into the measurement rules (working space for earthworks) goes into the BOQ quantity; content listed under 'work content' but given no quantity (battering, shoring boards, base trimming and clearing) goes only into the ancillary-works cost or risk allowance inside the all-in unit rate; content carried by the quota through wastage rates or contents (material wastage, rebar wastage plus construction bars at 5%, permissible overbreak in rock works, 0.50m over-concreting of bored piles) goes into the numerator, the quota line-item totals; whatever neither the BOQ nor the quota provides can only go into the rate risk allowance. The conversion formula is P = Sum(Tn) / Q (P rounded to 2 decimal places, Tn kept at full precision without rounding, Q rounded to 3 decimal places). Quoting with quota quantities passed off as BOQ quantities is an explicit error: the dimensional bases differ, the all-in unit rate is understated (omission ratio = 1 - quota rate / all-in rate), and it blurs the parties' respective responsibilities for BOQ accuracy.
- ←
Re-derivation of the all-in unit rate when a changed construction method makes the quota machine-shift consumption inapplicable: the three-path quota conversion test, the hierarchy of bases for recalculating plant consumption, the requirements for recasting the all-in unit rate analysis sheet, and the procedure for confirmation by the employer
Changes of construction method and plant usage are factors expressly listed in GB/T 50500-2024 Clause 8.9.1 as changes of item description or construction condition that can trigger adjustment of the all-in unit rate, but conversion must step down level by level: a conversion line item within the same chapter (DL/T 5468-2013 Clause 4.1.4 item 1: 'where the technical conditions prescribed by the quota (index) differ materially from the actual conditions of the works, the applicable quota (index) may be adjusted and applied according to the technical conditions of the works and the provisions of the quota') -> an express quota coefficient -> borrowing a similar process -> building up a rate from supplementary consumption (GB/T 51095-2015 Clause 5.3.12; TB 10801-2024 Clause 2.4.3); with no express coefficient, none may be invented. The hierarchy for recalculating machine-shift consumption is: contractor's in-house norms (GB/T 50875-2013 Clause 2.3.3) -> construction quotas (Clause 2.3.5) -> budgets or final accounts of similar works, or site measurement records certified by both parties (DL/T 5468-2013 Clause 4.1.4 item 2). After conversion, the all-in unit rate analysis sheet must be recast (GB/T 51095-2015 Clause 5.3.9; GB/T 50500-2024 Clause 6.2.12 and Annex E Table E.2.2-1) and submitted to the employer under the 'submission, checking, review, re-examination and confirmation' procedure (Clauses 8.1.2 and 8.1.3; for additional works, the project execution plan or implementation scheme and the priced offer must also be submitted before execution, Clause 8.10.2). The original quota line item must never be applied in departure from the approved construction scheme.
- ←
Re-measurement and price adjustment rules after quantity changes caused by variations or BOQ errors: recalculating from the variation instruction and the actual construction drawings, the separate track for BOQ errors, the 15% banded unit-rate adjustment, and the scheme-approval precondition for pricing preliminaries and new preliminary items (GB/T 50500-2024 clauses 7.4.2-7.4.4, 8.2.1, 8.9.1-8.9.2; GB 50500-2013 clauses 9.3.1, 9.3.2, 9.6.2)
Re-measurement after a variation takes as its basis the quantities recalculated from 'the variation instruction issued or confirmed by the employer and the actual construction drawings', compared with the BOQ quantities after the BOQ errors have been corrected, to determine the added or deleted variation items and their quantities; differences between the contract drawings and the contract BOQ are BOQ errors (corrected under unit-rate contracts, not adjusted under lump-sum contracts). Where the quantity difference is within 15% (15% inclusive), the unit rate is set under GB/T 50500-2024 clause 8.9.1; beyond 15% (exclusive), clause 8.9.2 adjusts downward on increase and upward on decrease in light of labour and material purchase concessions (the 2013 edition corresponds to the four tiers of clause 9.3.1 and clause 9.6.2). Preliminaries adjustment requires prior submission of the proposed scheme confirmed by the employer and the contractor; failure to submit is deemed to cause no preliminaries adjustment or a waiver of the right to adjust. New preliminary items take the added temporary works and plant machine-shifts priced from the approved scheme; the added cost of extended use of existing preliminaries and supervisory staff from variations off the critical path need not be measured.
- ←
Whether increased pipeline quantities caused by BIM coordinated layout can adjust the work quantities: determined by attribution in the deepening design (contractor's own deepening design — no adjustment; only where it constitutes a variation is adjustment made)
Whether the quantities of pipelines increased by BIM coordinated layout can be adjusted depends on attribution: differences arising from the contractor's own deepening design are generally not adjusted (GB/T 50500-2024, Clause 3.3.9; T/ZBD 100.4-2023, Clause 4.4.6), except where the contract provides for settlement on the basis of the deepened drawings; where the employer so requires, or where it constitutes a variation confirmed upon review by the original designer, adjustment is made per Chapters 7/8/9, and where the quantity difference exceeds 15%, the unit rate is adjusted per Clause 8.9.2.
- ←
Whether varied works may be given newly built-up rates when the priced BOQ already contains an applicable rate: the three-tier decision table for variation valuation, the tests for 'applicable' and 'similar', and a clause-by-clause comparison of GB 50500-2013 clause 9.3.1 with GB/T 50500-2024 clause 8.9.1
For BOQ items whose applicable rate already exists in the contract, varied works may not be re-rated with newly built-up rates; the original contract all-in unit rate applies directly (GB 50500-2013 clause 9.3.1 item 1: 'the rate of that item shall be adopted'; GB/T 50500-2024 clause 8.9.1 item 1: 'for BOQ items executed under the same construction conditions with the same item descriptions, the corresponding contract unit rate shall be adopted'). The three tiers of variation valuation step down in order and stop once one is hit: (1) an applicable rate exists - apply the contract rate directly (only where the quantity deviation exceeds 15% is the rate adjusted up or down under clause 9.6.2 / clause 8.9.2, which is price adjustment, not new rate build-up); (2) only a similar rate exists - convert by reference to the similar item's rate (the 2024 edition: 'the all-in unit rate converted and adjusted from the contract rate of a similar BOQ item', converting only the differing elements while the levels of overheads and profit are retained); (3) neither applicable nor similar - the contractor proposes a new rate on the basis of the variation documents, executed after the employer confirms it (the 2024 edition: negotiate a market-reasonable all-in unit rate). Quantity-only changes and minor adjustments of secondary item description elements do not constitute re-rating; only substantive changes of material specification, construction method or construction conditions (differing in both the description and the conditions dimensions) trigger new rate build-up.
- ←
The source definition, pricing basis and final account aggregation of the three kinds of quantities (contract BOQ quantities / variation quantities / dayworks record quantities), including the comparison baselines for BOQ errors - variation - additional works and the one-gateway-only rule against double measurement (GB/T 50500-2024 clauses 7.2, 7.3, 7.4, 7.5, 8.2, 8.6, 8.9, 8.10, 8.11, 10.3; compared with GB 50500-2013 clauses 9.3, 9.14, 11.2)
Clause 7.4.1 of GB/T 50500-2024 draws the boundary with three comparison baselines: the difference between the contract drawings and the contract BOQ = errors and omissions in the BOQ (corrected under unit-rate contracts, not adjusted under lump-sum contracts); the difference between the contract drawings and 'variation instructions + as-executed drawings' = variation; work outside the contractual scope of works completed at the employer's request = additional works (8.10.1); sundry items and events not attributable to the contractor are measured on dayworks vouchers (7.5.3 to 7.5.6). In-contract quantities are re-measured under 7.2.1 (BOQ items priced per item are not re-measured or adjusted); deviations within 15% (inclusive) go to 8.9.1 and beyond 15% to 8.9.2, the rate progressing 'contract rate -> converted similar rate -> negotiated market-reasonable all-in unit rate'; dayworks take the contract dayworks all-in unit rate under 8.6.2, or where no such BOQ item or no applicable rate exists the published price information under 8.6.3 and, failing that, the contractor's purchase price as confirmed by both parties, the rate already covering the sporadic extra costs and preliminaries of dayworks (8.6.4). Settlement aggregates in the 13-item order of 10.3.2, with preliminaries and the main contractor's attendance and coordination provisions recalculated at final account (10.3.3). No double measurement: variation quantities are determined only after comparison with 'the BOQ items and quantities as corrected for BOQ errors' (7.4.2), and what has already been adjusted under 8.2 to 8.10 may not be claimed again under the claims provisions (8.11.1).
- ←
Re-decomposition and re-pricing of cost when a design variation moves wire-in-conduit wiring to cable-tray wiring: choosing the variation valuation clause (2013 edition clause 9.3.1 four tiers / 2024 edition clauses 8.9.1~8.9.3 five tiers); the deduction basis for the original conduit and wiring quantities; itemisation and measurement of tray, supports and hangers, and wiring; attribution of demolition of work already done and material write-off, and the rework confirmation procedure
Changing wires from conduit to cable tray is a change of 'item description + construction method': the original conduit rate does not apply to the tray (under the 2013 edition, clause 9.4.2 first re-determines the all-in unit rate on the description actually built, then the four tiers of clause 9.3.1 apply - the contract rate where an applicable item exists, an analogous rate by reference where a similar one exists, and where neither exists the contractor proposes a rate built from published price information and its tender float rate for employer confirmation, or from market-enquiry prices where the published information lacks the item); conduit and wiring quantities are recalculated from the variation instruction and the drawings as actually built and set against the original BOQ for deduction (conduit deducted by length, the length occupied by junction boxes not deducted); the added tray is measured by length (m); whether supports and hangers are listed separately depends on the consumption standard applied (DB11/T 2382-2024 includes support erection, fabrication of non-finished supports being listed separately; SJG 111.3-2022 expressly excludes support fabrication and erection); wiring is recalculated as single-wire length including reservations; demolition and material write-off for rework must rest on a rework confirmation sheet or site instruction record raised within the contractually agreed time - borne by the employer where the cause is not attributable to the contractor, and serving as the basis for rework pricing under chapter 8; raised late, the work is deemed to have caused no rework and is not measured.
- ←
The rate build-up path from quota line items to the all-in unit rate of a BOQ item and the cost calculation procedure: divisional work item cost as BOQ quantity x all-in rate, sum of quota line item amounts / BOQ item quantity (3 decimal places for quantities, 2 for rates), the three pricing methods, the analysis sheet identical to the BOQ rate, and the taxed versus tax-exclusive cost structures
The all-in unit rate of a BOQ item is converted as 'sum of quota line item amounts / BOQ item quantity' (item amounts at full precision with no rounding, BOQ quantities to 3 decimals, all-in rates to 2), and divisional work item cost = sum of (item quantity x all-in rate); the rates and prices in the all-in unit rate analysis sheet must exactly match those in the BOQ (GB/T 50500-2024 clause 3.1.7); pricing methods are unit-rate, lump-sum and percentage-rate, with divisional items and dayworks best priced at unit rates and preliminary items by lump sum or percentage; the taxed cost follows 'tax-exclusive cost of works = (divisional items + unit-rate preliminaries) + lump-sum preliminaries + other charges, and VAT = tax-exclusive cost x rate'; the scope of the all-in rate must be confirmed first - GB/T 50500-2024 clause 2.0.9 excludes VAT, while GB/T 51095-2015 clause 5.3.8 and article 5 of Ministry of Construction Order No. 107 are full-cost scopes including statutory levies and taxes.
- ←
Rate build-up basis and confirmation procedure when a BOQ omission or new item has neither an applicable nor an analogous rate: GB 50500-2013 Section 9.5 (citing the four tiers of cl. 9.3.1) mapped against GB/T 50500-2024 Sections 8.2/8.9/8.10, plus the time limits for adjustment reports
GB 50500-2013 cl. 9.5.1 provides that 'where, during performance, new divisional and sub-divisional works BOQ items arise because of omissions in the tender BOQ, the unit rates shall be determined per cl. 9.3.1 of this code and the contract price adjusted'. Tier 3 of cl. 9.3.1 reads 'where the priced BOQ contains neither an applicable nor an analogous item for the varied work, the contractor shall propose a unit rate for the varied work based on the variation documents, the measurement rules and pricing methods, the published price information issued by the government construction cost administration and the contractor's price fluctuation rate, and adjustment follows employer confirmation'; tier 4 switches, where the published price information lists no price, to a rate based on 'market prices with a lawful basis obtained through market enquiry and other means', again subject to employer confirmation -- so published price information comes first and a lawful market price only fills gaps, and tier 3 must carry the contractor's price fluctuation rate. GB/T 50500-2024 no longer has a stand-alone 'omission' section: erroneous and omitted items are folded into 'errors and omissions in the BOQ' (cl. 8.2.1 -> cl. 8.9.1/8.9.2), additional works outside the contract scope follow Section 8.10 (cl. 8.10.2 requires the contractor to submit the project execution plan or execution scheme, the programme and the priced offer to the employer for review and approval before executing the additional works), the adjustment procedure is unified as 'submission, checking, re-checking, review and confirmation' (cl. 8.1.2 to 8.1.4), and employer silence past the time limit counts as deemed approval of the contractor's report.
- ←
Boundary determination and clause routing among quantity deviation, variation and omitted BOQ items: sections 9.4/9.5/9.6 of the 2013 edition are merged into 'BOQ errors' in GB/T 50500-2024, sorted by three comparison tests (contract drawings vs contract BOQ; contract drawings vs actual construction drawings; inside vs outside the contract works scope), with an anti-double-counting rule that one matter goes through one route only
The routing test is unique: a difference between the contract drawings (including the contract specifications) and the priced BOQ equals BOQ errors; a difference between the contract drawings and the actual construction drawings (including variation instructions issued or confirmed by the employer) equals a variation; physical works outside the contract works scope and the completion delivery requirements are additional works. GB/T 50500-2024 has merged 2013 edition Section 9.4 (item description mismatch), Section 9.5 (omitted BOQ items) and Section 9.6 (quantity deviation) into 'BOQ errors' (Clause 2.0.27), with quantity differences tiered at 15%: up to and including 15% goes to Clause 8.9.1, above 15% (exclusive) goes to Clause 8.9.2. The key anti-duplication procedure: varied quantities must be determined by comparison with the BOQ items and quantities 'after the BOQ errors have been corrected' -- the same quantity difference must not be adjusted once as an error correction and again as a variation increase or decrease.
- ←
Adjusting all-in unit rates at the +/-15% quantity boundary: GB/T 50500-2024 Clauses 8.9.1-8.9.3 and the reading of the wording change from repealed GB 50500-2013 Clause 9.6.2's "tiered pricing"
Under GB/T 50500-2024 (unit-price contracts): within 15% (inclusive) per 8.9.1's five tiers (same characteristics + same conditions -> contract rate; similar -> converted; different -> negotiated market rate); beyond 15% per 8.9.2, "accounting for the purchase-price discounts gained by increased quantities (or lost when decreased), reasonably lower (or raise) the contract rate and new composite rates" - more quantity lowers the rate, less raises it. The repealed 2013 Clause 9.6.2 explicitly said "the rate of the increased portion shall be lowered; the rate of the remaining portion after decrease shall be raised" (tiered: within +/-15% unchanged); 2024 drops "portion" and does not say whether the tiered or whole-quantity repricing applies - a genuine ambiguity; being a recommended standard, contract terms govern - lock the tiered basis in the special conditions.
- ←
Identifying and pricing additional works from the settlement-review and construction cost expert assessment perspective: supplementary agreements first, no supplementary agreement does not automatically bind the original contract's pricing principles, rate build-up classified by the original pricing method, and the burden of proof (T/ZBD 100.5-2023 clause 3.1.10; T/ZBD 100.4-2023 clause 4.8.3)
Per T/ZBD 100.5-2023 clause 3.1.10 and T/ZBD 100.4-2023 clause 4.8.3: works executed by the contractor at the employer's instruction outside the contractual scope are reviewed and priced as additional works; where both parties jointly determine the cost, it adjusts as determined; otherwise identification follows the contract-scope level (project or single project -> an added single project; single project -> ancillary works outside scope or independently tenderable specialist works; specialist subcontract -> other specialist works outside scope). Pricing: a supplementary agreement fixing the principles governs; without one and without evidence of agreed principles, the original contract's principles do not automatically apply - additional works lie outside the contract and are free of its price and duration terms, in principle priced at negotiated rates, the contractor bearing the burden of explaining and proving them.
- ←
Setting overheads and profit in repricing variations and other price adjustments (GB/T 50500-2024 Articles 3.6.6, 8.4.6, 8.8.5, 8.9.1)
On repricing (no identical or similar rates), GB/T 50500-2024 Article 8.9.1 negotiates a market-reasonable all-in unit rate - by reference to the pricing rules and pricing level of analogous contract rates or to analogous items of similar works; the expert-assessment basis is reasonable cost plus the contract overheads and profit rates (T/ZBD 100.4-2023 Article 4.6.2), the supervision basis the cost-plus-profit principle (GB/T 50319-2013 Article 6.3.3). Similar-rate conversion (tier 2) swaps only the differing elements, the original overheads and profit preserved. Where employer-supplied materials become contractor-purchased, add to the original all-in unit rate the material cost (with reasonable wastage) plus overheads and profit, at the rates of the item's rate build-up or the nearest analogous item (Article 3.6.6). Reverse rules: on laws and policy changes, the overheads and profit within the total price and unit rates are not adjusted (8.8.5); provisional-sum materials adjust only the pre-tax provisional material price, nothing else (8.4.6); fluctuation differentials carry VAT only, no overheads or profit (3.3.5).
- ←
Pricing principles for variation works in construction cost expert assessment: identical contract items take their rates, similar items take similar rates, and absent both, a new all-in unit rate from reasonable cost per the appraisal records plus the contract overheads and profit rates, or per the pricing basis (T/ZBD 100.4-2023 Article 4.6.2)
Unless the contract provides otherwise, the expert appraiser assesses variation works on three tiers: 1 where the varied work has an identical item in the contract, apply the all-in unit rate or percentage rate of that identical item; 2 where there is no identical item, an analogous item's all-in unit rate or percentage rate may be applied; 3 where there is neither an identical nor an analogous item, determine a new all-in unit rate from the reasonable cost of executing the work calculated per the appraisal records submitted by the contractor plus the contract overheads and profit rates, or from the pricing basis of the construction authority or the relevant industry at the project's location plus the contract overheads and profit rates. Item 3 marks a major adjustment responding to governments phasing out budget quota publication: the contractor must be able to evidence cost where no identical or similar all-in unit rate exists, and the appraiser assesses from those records together with the contract rates and the works as actually executed.
- ←
Determining the all-in unit rate of additional works (outside the contract-agreed scope of works) (GB/T 50500-2024 Section 8.10)
The all-in unit rate of additional works follows the dual path of 'contract unit rates first, negotiated rate build-up as fallback': (1) list and measure per the contract-agreed measurement and pricing rules, and price by combining contract unit rates and tender price levels; (2) where no applicable unit rate exists, the employer and contractor renegotiate the measurement and pricing rules. Conversion of contract unit rates must consider four factor groups: labour/material/machinery price differences, bulk-procurement effects, correction of under/over-priced items, and differences between competition-formed and negotiated rates; before implementation, submit the quotation for review and sign a supplementary agreement before proceeding; further variations to additional works are priced per Section 8.9, and Clauses 8.2.2/8.2.3 (BOQ errors/omissions) should not apply. Construction cost expert assessment (judicial appraisal) position: works outside the contract are not necessarily bound by the original contract; the contractor bears the burden of proof.
- ←
Measurement units for landscape plant installation (plant/m/m2/clump), plant specification terminology, and item-characteristic description essentials (GB/T 50858-2024)
Plant installation measurement units are fixed by category and planting method, not self-invented: trees/single-shrub/scattered bamboo/palms/climbers by plant (count), massed shrubs/flower ground-cover by m2, hedges by m (hedge length, not plant count), clumping bamboo/single-clump aquatics by clump (GB/T 50858-2024 Appendix A Table A.3.1, 4.2.5). Plant specification terms have unified definitions: DBH = trunk diameter at 1.3 m above ground (landscape caliber, not highway 1.2 m); crown diameter = mean of max and min vertical-projection diameters; ground diameter at 0.1 m; trunk diameter at 0.3 m; meter diameter at 1.0 m; plant height = ground to top. Item characteristics must be standard, concise, accurate, complete (4.1.2); survival rates above CJJ 82, shaping requirements, and grass-brick inlay ratios must be stated in characteristics.
- ←
Derivation of new (built-up) rates when a design change changes the construction process (construction method): qualifying the source + the three-tier path of GB/T 50500-2024 clause 8.9.1
"Change of construction method" is a price-impact factor of "item description change" expressly listed in GB/T 50500-2024 8.9.1: process changes caused by design changes or employer requirements are variations requiring derivation of new (built-up) rates; a contractor's autonomous process switch is construction method statement optimization, generally not adjusting the contract price, costs borne by the contractor itself. Pricing follows three tiers: identical conditions + identical item descriptions retain the contract unit rate; similar item descriptions/conditions convert via the original all-in unit rate analysis, replacing only differing elements; different item descriptions/conditions (complete method change) negotiate at "reasonable cost + profit" with a new all-in unit rate analysis. Confirm the pricing path in writing before implementation and keep evidence; accompanying quantity changes beyond 15% (exclusive) follow 8.9.2 — for increases, reasonably reduce; for decreases, reasonably increase.
- ←
Can final account review/audit adjust awarded all-in unit rates? — rate locking under re-measurable contracts, statutory exceptions, and the limits of audit authority
In principle, no. Under a re-measurable (unit-rate) contract, awarded all-in unit rates within the contractual risk range remain fixed at final account review; the review checks each rate item by item against the priced bill of quantities (BOQ); absent other contractual agreement, rates adjust only upon adjustment events such as variations, errors and omissions in the BOQ, quantity deviations exceeding 15%, changes in costs beyond the risk range, and substitution of provisional sums. Government fiscal review of project cost / audit is administrative supervision and does not affect contract validity — its conclusions serve as the basis for settlement only where the contract expressly provides that they do so.
- ←
Deducting unexecuted (unbuilt) items from the contract price: disallowance rules at final account (re-measurable vs lump-sum contract bases, linked deductions, and contractor compensation)
Unexecuted work must be disallowed from the contract-price BOQ: under re-measurable (unit-rate) contracts, measurement is against actuals and unexecuted items are deducted at the contract all-in unit rates (with rates reasonably marked up where the reduction exceeds 15%); under lump-sum contracts, the unexecuted portions are disallowed after checking settlement drawings, scope and taking-over (completion acceptance) reports against the contract price. Whole-item deletions require linked adjustment of preliminaries and statutory levies and fees; cancellation of nominated specialist subcontract works requires deduction of the corresponding main contractor's attendance and coordination provisions; dayworks not incurred are clawed back; for work cancelled for non-contractor reasons, the contractor's incurred costs and reasonable expected returns deserve compensation.
- ←
Design change overview: authority to propose, classification and grading, approval and implementation, three-tier pricing, settlement and disputes across six links (with variation concept cross-links and FIDIC mapping)
The design-change full chain: any of four parties may propose; only the original designer issues the document (Survey and Design Administration Regulations, art. 28); the chief supervising engineer must sign it off before construction; approve first, then construct; price on the three-tier ladder; settle on the documents. Procedural red lines: verbal instructions are no pricing voucher (unless construction per them is proven); the supervisor's emergency verbal instruction must be confirmed in writing within 24 hours (local supervision codes); emergency-rescue works proceed first with formalities completed within 10 working days. Pricing runs the ladder "identical — contract rate; analogous — converted; different — negotiated" (GB/T 50500-2024 cl. 8.9.1), with quantities beyond ±15% re-rated (down for increases, up for decreases) and the preliminaries scheme to be submitted before execution or the adjustment forfeited. Claims run the double 28-day limit, forfeited on default; the variation price takes the ninth head of the final account, disputes assessed across five tiers by instructions, drawings and confirmations.
- ←
Pricing path for variation items with no applicable or analogous all-in unit rate: agreeing a market-reasonable all-in rate, the cost-plus-profit fallback, and the expert-assessment position (GB/T 50500-2024 clauses 8.9 and 8.6.3; GB/T 50319-2013 clause 6.3.3; T/ZBD 100.4-2023 clause 4.6.2)
When a variation item has neither an identical nor an analogous all-in unit rate in the contract, the employer and the contractor shall agree a market-reasonable all-in rate in light of the execution of the works, market prices, the contract rate-pricing rules and the tendered rate level (GB/T 50500-2024 clause 8.9.1, bands 3 to 5); where agreement fails, the Engineer (chief supervising engineer) determines a reasonable rate or price on the cost-plus-profit principle (GB/T 50319-2013 clause 6.3.3), and once the matter enters construction cost expert assessment the new all-in rate is fixed as the reasonable cost of the executed works plus the overhead rate and profit margin agreed in the contract, the contractor bearing the burden of proof (T/ZBD 100.4-2023 clause 4.6.2). Where the change in quantity exceeds 15% (15% excluded), clause 8.9.2 adjusts the rate up or down in combination with the effect of bulk-procurement discounts. Pricing of labour, materials and plant may follow the order of clause 8.6.3: price information sources agreed in the contract; then the tax-exclusive published price information issued by the construction cost administration or the industry at the location of the works, plus the priced build-up details of analogous billed items in the BOQ; then the contractor's procurement prices confirmed by both parties.