Engineering Knowledge Cards.
Confidence HighUpdated 2026-11-08

Three-tier re-rating of all-in unit rates after changes in item description/work content: retain the contract unit rate, convert the contract unit rate, or negotiate a new rate (GB/T 50500-2024 Clause 8.9.1)

Changes in item description/construction conditions are handled in three tiers: identical -> retain the contract unit rate; similar -> convert and adjust the contract unit rate (replace only the price differential of the differing factor, keeping management fee and profit); different -> negotiate a rate on the reasonable-cost-plus-profit principle. Judgment factors include materials, construction methods, foundation/height/member specifications, season, transport mode, etc.; where accompanied by quantity changes beyond 15%, the unit rate is reasonably reduced for increases and reasonably raised for decreases; contractual agreement takes precedence.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.2.1条、第8.9.1条、第8.9.2条、第8.9.3条、第8.10.3条
  • T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.4.4条
  • GB/T 50319-2013 · Code for Construction Project Supervision 第6.3.3条

Topic Positioning

Answers "after the item description / work content / construction conditions of a billed (BOQ) item change, can the original all-in unit rate still be used and how should it be re-rated" — the three-tier judgment framework (retain / convert / negotiate) per GB/T 50500-2024 Clause 8.9.1, applicable to re-rating of unit rates arising from variations and errors and omissions in the BOQ.

Core Conclusions

Three-tier rules: (1) identical construction conditions + identical item description -> directly adopt the corresponding contract unit rate, no adjustment; (2) similar item description or similar construction conditions -> use the contract unit rate of a similar billed (BOQ) item after conversion and adjustment, most commonly for material changes: new all-in unit rate = original all-in unit rate - original material cost + new material cost (per the consumption in the original rate build-up x the new material price), keeping the levels of management fee, profit, and risk cost and replacing only the differing factor; (3) different item description or different construction conditions -> negotiate a market-reasonable all-in unit rate combining similar-item pricing rules and bid levels; where no identical/similar item unit rate exists, determine it on the reasonable-cost-plus-profit principle (DB37/T 5028-2022 Clause 9.3.2). Judge the degree of change by two factor groups: description-related (materials, construction methods, impact on other divisional/sub-divisional works, etc.) and condition-related (foundation, height, member specifications, construction season, material transport mode, machinery usage, etc.). Linked rules: where BOQ quantities increase or decrease by more than 15% simultaneously, the unit rate is reasonably reduced for increased quantities (procurement discounts) and reasonably raised for decreased quantities (Clause 8.9.2); for lump-sum contracts, whether the contract unit rate applies to valuation of variations decides adjustment or negotiation (Clause 8.9.3); under re-measurable (unit-rate) contracts, where contract drawings and the priced BOQ are inconsistent during performance, the BOQ governs (Clause 3.4.5); under fixed unit-rate contracts the all-in unit rate must not be adjusted except for agreed adjustable situations (T/ZBD 100.5-2023 Clause 3.1.6).

Applicable Boundaries

Applies to valuation of variations and BOQ errors/omissions under BOQ-priced unit-rate/lump-sum contracts; where the contract explicitly agrees on the valuation of variations (e.g., only material price differential conversion, no adjustment within the risk band), the contract governs. Whether a change is "similar" or "different" should first be confirmed in writing by both parties before deciding to retain, convert, or re-price. Not applicable to adjustment for cost fluctuation (Section 8.7), determination of provisional sums (Section 8.4), or other independent price-adjustment rules. The 2024 edition is more flexible than the 2013 edition — contractual agreement takes precedence over the national standard's default rules.

Further Reading

See GB/T 50500-2024: Clause 2.0.27 (errors and omissions in the BOQ), Clause 3.4.5 (drawings inconsistent with the BOQ — the BOQ governs), Clause 4.1.7 (five elements of a billed (BOQ) item), Clause 8.2.1 (re-measurement of errors and omissions and the 15% boundary), Clauses 8.9.1-8.9.3 (three-tier re-rating and the beyond-15% linkage), Clause 8.10.3 (differing factors for additional works retaining contract unit rates); companion standards T/ZBD 100.4-2023 Clause 4.4.4 (judicial-appraisal caliber), T/ZBD 100.5-2023 Clause 3.1.6 (final account review), DB37/T 5028-2022 Clause 9.3.2 (supervision valuation of variations), GB/T 51262-2017 Clause 5.6.1 (appraisal of variation disputes).

Keywords

Cited By