GB 50500-2013 Chapter 9 'Adjustment of the Contract Price' at a glance: the 15 adjustable events, their five-category grouping and clause order, the trigger conditions and direction of price adjustment for each event, submission time limits and confirmation (deemed approval) procedures, the order of application when several events coincide, and a clause mapping to GB/T 50500-2024
Clause 9.1.1 of GB 50500-2013 lists 15 adjustable events, and the official commentary groups them into five categories: changes in laws and regulations (9.2); variations (9.3 variation, 9.4 item description mismatch, 9.5 omitted BOQ items, 9.6 quantity deviation, 9.7 dayworks); changes in costs (9.8 changes in costs, 9.9 provisional prices); claims (9.10 force majeure, 9.11 earlier completion, 9.12 delay damages, 9.13 claims); and others (9.14 site instruction records plus other adjustment events agreed by both parties). Clause numbers are easily shifted: changes in costs is 9.8 (not 9.7, which is dayworks); force majeure 9.10; earlier completion 9.11; delay damages 9.12; claims 9.13; site instruction records 9.14. Direction of adjustment: under 9.6.2, where a quantity deviation exceeds 15%, the all-in unit rate of the increased portion beyond 15% is reduced, and where the quantity decreases by more than 15% the all-in unit rate of the remaining portion is increased (reverse correction); 9.3.1 sets a four-tier pricing ladder for variations (an applicable item takes the original rate; a similar item is referenced within a reasonable range; where neither applies, the contractor proposes a rate from published price information x its quoted floating rate for the employer's confirmation; where the published price information carries no price, a lawful market price from market survey is proposed for confirmation); under 9.8.2, where no band is agreed and a unit rate changes by more than 5%, the portion beyond 5% is adjusted. Where events coincide: if a variation also causes a quantity deviation above 15%, that item's rate is adjusted under 9.6.2 (clause 9.3.1 paragraph 1), preliminaries move in linkage under 9.6.3/9.3.2, and cost fluctuation is separately adjusted under Annex A for the price differential only, without double counting.
Applicable Codes
- GB 50500-2013 建设工程工程量清单计价规范 Ch. 9 合同价款调整(9.1.1、9.2.1、9.3.1~9.3.2、9.4.2、9.5.1、9.6.2~9.6.3、9.7.1、9.7.3、9.8.1~9.8.4、9.9.1、9.10.1、9.11.2、9.12.1~9.12.2、9.13.2~9.13.6、9.14.2、9.14.4~9.14.5、9.15)
- GB/T 50500-2024 建设工程工程量清单计价标准 Ch. 8(8.2.1、8.9.1、8.9.2、8.11.12)
- GB 50500-2013 第3.1.5条(安全文明施工费)
- GB 50500-2013 App. A(物价变化合同价款调整方法)
What this card covers
An index card for Chapter 9 'Adjustment of the Contract Price' of GB 50500-2013: the 15 adjustable events under the commentary's five-category grouping and clause order, with trigger conditions, adjustment direction, submission time limits and confirmation procedures, the order of application where several situations coincide, and a mapping to GB/T 50500-2024. Use it to locate clauses, check clause numbers, and route a given cost.
Core conclusions
1. The 15 adjustable events and the five-category grouping (wording of clause 9.1.1; the five-category division is in the commentary)
Clause 9.1.1 provides: where the following events (among others) occur, the parties shall adjust the contract price as agreed in the contract: 1 changes in laws and regulations; 2 variations; 3 item description mismatch; 4 omitted BOQ items; 5 quantity deviation; 6 dayworks; 7 changes in costs; 8 provisional prices; 9 force majeure; 10 earlier completion (acceleration compensation); 11 delay damages; 12 claims; 13 site instruction records; 14 provisional sums; 15 other adjustment events agreed between the employer and the contractor.
The commentary groups them into five categories:
- changes in laws and regulations: 9.2;
- variations: 9.3 variation, 9.4 item description mismatch, 9.5 omitted BOQ items, 9.6 quantity deviation, 9.7 dayworks;
- changes in costs: 9.8 changes in costs, 9.9 provisional prices;
- claims: 9.10 force majeure, 9.11 earlier completion, 9.12 delay damages, 9.13 claims;
- others: 9.14 site instruction records and other agreed adjustment events. The commentary adds: by content, a site instruction record may fall under variations, under claims, or involve no price adjustment at all.
2. Clause order (with corrections of frequent misalignment)
The full order: 9.1 general provisions - 9.2 changes in laws and regulations - 9.3 variation - 9.4 item description mismatch - 9.5 omitted BOQ items - 9.6 quantity deviation - 9.7 dayworks - 9.8 changes in costs - 9.9 provisional prices - 9.10 force majeure - 9.11 earlier completion - 9.12 delay damages - 9.13 claims - 9.14 site instruction records - 9.15 provisional sums.
Four high-frequency misalignment points: changes in costs = 9.8 (not 9.7; 9.7 is dayworks); force majeure = 9.10; delay damages = 9.12 (not 9.13); claims = 9.13 (not 9.14); site instruction records = 9.14 (not 9.10). A one-line shift between adjacent rows is the classic error; always check the section number on the first line of the clause text.
3. 'Trigger condition -> direction of adjustment' by situation
| Clause | Situation | Trigger condition (key points of the clause) | Direction of adjustment |
|---|---|---|---|
| 9.2 | Changes in laws and regulations | the base date is 28 days before the tender submission deadline for tendered works and 28 days before contract signing for non-tendered works; after the base date, changes in state laws, regulations, rules and policies increase or decrease the construction cost | two-way; adjusted under the provisions issued accordingly by the provincial or sectoral building authority or its authorised cost administration institution (9.2.1) |
| 9.3 | Variation | the variation changes the items or their quantities in the priced BOQ | two-way, four-tier pricing (9.3.1): (1) an applicable item exists - adopt that item's rate, but where the variation causes a quantity deviation above 15% for that item, the rate is adjusted under 9.6.2; (2) no applicable item but a similar one - reference the similar item's rate within a reasonable range; (3) neither applicable nor similar - the contractor proposes a rate based on the variation documents, the method of measurement, the pricing method, the published price information issued by the cost administration institution and its quoted floating rate, for the employer's confirmation; (4) neither applicable nor similar and the published price information carries no price - the contractor proposes a rate based on the method of measurement and the pricing method and on a lawful market price obtained by market survey, for the employer's confirmation |
| 9.4 | Item description mismatch | during performance, the item description of any item in the tender BOQ does not match the design drawings (including design changes), and the mismatch increases or decreases the cost of that item | two-way; the all-in unit rate is re-determined under the relevant clauses of 9.3 on the basis of the item description actually built and the contract price adjusted (9.4.2) |
| 9.5 | Omitted BOQ items | during performance an item is missing from the tender BOQ and new divisional and sub-divisional BOQ items appear | one-way increase; the contract price is adjusted once the rate is determined under 9.3.1 (9.5.1) |
| 9.6 | Quantity deviation | deviation exceeds 15% owing to the quantity deviation rules of this section and to variation under 9.3 and other causes | two-way reverse correction: where the quantity increases by more than 15%, the all-in unit rate of the increased portion shall be reduced; where it decreases by more than 15%, the all-in unit rate of the remaining portion shall be increased (9.6.2) |
| 9.6.3 | Preliminaries driven by quantity deviation | quantities change as in 9.6.2 and cause corresponding changes in related preliminaries items | for preliminaries priced by coefficient or as a single lump sum: preliminaries increase where quantity increases and decrease where quantity decreases |
| 9.7 | Dayworks | sundry work that the employer instructs the contractor to perform on a dayworks basis | the contractor shall comply (9.7.1); priced per the confirmed results of the certified dayworks record |
| 9.8 | Changes in costs | during performance, fluctuations in the prices of labour, materials, construction equipment and machine-shifts affect the contract price | two-way; adjusted as agreed in the contract by one of the Annex A methods (9.8.1). Where the contractor procures materials and equipment, the contract shall state the range or band of price changes of the principal materials and equipment; where nothing is agreed and a unit rate changes by more than 5%, the price of the portion beyond 5% is calculated and adjusted by the Annex A method (9.8.2) |
| 9.8.4 | Employer-supplied materials | the employer supplies materials and construction equipment | 9.8.1 and 9.8.2 do not apply; the employer adjusts according to the actual change and the amount enters the construction cost of the works |
| 9.9 | Provisional prices | materials and construction equipment given provisional prices in the tender BOQ are subject to compulsory tendering by law | the employer and the contractor select the supplier and fix the price by tendering, then replace the provisional price on that basis and adjust the contract price (9.9.1) |
| 9.10 | Force majeure | a force majeure event causes casualties, property damage and additional costs | shared under five heads with price and time adjusted (9.10.1): (1) damage to the contract works themselves, casualties and property losses of third parties caused by damage to the works, and damage to materials brought to site for the works and to equipment awaiting installation - employer; (2) casualties of each party's own personnel are borne by that party's own unit; (3) damage to the contractor's construction plant and its costs of suspension - contractor; (4) during suspension, wages of the management and security personnel the contractor must keep on site at the employer's request - employer; (5) costs of cleaning up and repairing the works - employer |
| 9.11 | Earlier completion (acceleration compensation) | the employer requires the contract works to be completed early | acceleration measures shall be agreed with the contractor's consent, the programme revised, and the employer bears the contractor's additional earlier-completion (acceleration compensation) costs (9.11.2) |
| 9.12 | Delay damages | the contractor fails to construct as agreed in the contract, so actual progress falls behind the programme | the contractor pays the employer: it shall accelerate to meet the contract time for completion; where delay occurs it shall compensate the loss and pay delay damages as agreed in the contract (9.12.1); delay damages shall be agreed in the contract with the amount payable per calendar day stated, entered in the final account documents and deducted from the settlement payment (9.12.2); payment of delay damages does not relieve the contractor of its other contractual duties and obligations |
| 9.13 | Claims | an event not attributable to the contractor causes the contractor loss | one-way increase (in the contractor's favour); raised under the 9.13.2 procedure and handled under 9.13.3 |
| 9.14 | Site instruction records | a site instruction record event occurs on the contract works | by record content it may be classified as variation or as claim, and part of such content involves no price adjustment; where the contractor performs work without the employer's certification, unless the employer's written consent is obtained, the resulting costs are borne by the contractor (9.14.4) |
| 9.15 | Provisional sums | use of the provisional sums included in the signed contract price | used only on the employer's instruction; although provisional sums sit inside the contract price they do not belong to the contractor and do not necessarily occur; only what actually occurs as agreed becomes due to the contractor and enters the final account; after deducting payments made under 9.1 to 9.14, any balance (if any) belongs to the employer |
4. Submission time limits and confirmation (deemed approval) procedures
- Changes in laws and regulations: base dates per table row 9.2; only changes occurring after the base date are adjusted (9.2.1).
- Variation affecting preliminaries: the contractor shall in advance submit its intended construction method for confirmation, detailing the changes against the original method's preliminaries items, and execute after both parties confirm (9.3.2); failure to submit in advance is treated as the variation not affecting preliminaries, or as waiver of the right of adjustment. Basis: mandatory HSE provisions under 3.1.5 for the items actually changed; rate-priced preliminaries take the rates determined under 9.3.1; lump-sum (or coefficient) preliminaries adjust for actual changes, but adjustment amount = actual adjustment amount x the contractor's quoted floating rate.
- Dayworks: within 24 hours after the work finishes, the contractor submits a certified dayworks record report in triplicate; the employer confirms within 2 days of receipt and returns one copy as the basis of pricing and payment; no confirmation or amendments within the time limit means the record is deemed approved by the employer (9.7.3).
- Claims (raised by the contractor): Notice of Claim within 28 days of knowing or having reason to know of the event (late notice extinguishes the right to claim) -> formal claim notice within 28 days of the Notice of Claim (with records and supporting documents) -> continuing-claim notices while the effect continues -> final claim notice within 28 days after the effect ends (9.13.2).
- Claims (handled by the employer): the employer examines the records and documents and replies within 28 days of receiving the claim notice or further documents; no reply within the period means the claim is deemed approved; on acceptance the amount is paid as an addition to the contract price in the current progress payment, otherwise the dispute resolution route applies (9.13.3).
- End point of the claims window: once the final account is settled, the contractor is deemed to have no further right to claim for pre-final-account events; only later claims may be raised in the final closure of accounts, the window ending when both parties close the accounts (9.13.6).
- Site instruction records: the contractor submits the site record report within 7 days of the instruction; the employer verifies, confirms or proposes amendments within 48 hours; failure within 48 hours is deemed approval (9.14.2). Within 7 days after the work is completed, the contractor computes the price from the record and submits it for confirmation, added to the contract price and paid with the progress payment of the same period (9.14.5).
5. Order of application where several situations coincide
- Variation + quantity deviation above 15%: clause 9.3.1 paragraph 1 - where an applicable item exists that item's rate is adopted, 'but where the variation causes the quantity of that BOQ item to change and the quantity deviation exceeds 15%, the rate of that item shall be adjusted under clause 9.6.2 of this standard'. The over-15% rule overrides direct adoption of the contract rate: route under 9.3, then correct the over-15% portion of the rate under 9.6.2.
- + linked preliminaries: coefficient or lump-sum preliminaries follow the quantity up and down under 9.6.3; where the variation substantially changes the construction method, confirm under 9.3.2 first, then handle the items under 3.1.5 (mandatory HSE provisions), 9.3.1 (rate-priced) and 'actual adjustment amount x quoted floating rate' (lump-sum/coefficient).
- + changes in costs: 9.8.1 and 9.8.2 follow the Annex A methods and act on the price differential (fluctuations beyond the agreed band or beyond 5%); 9.3/9.6 act on the all-in unit rate level (rate build-up and quantity correction) - different objects, each computed on its own basis, counted once only; employer-supplied materials sit outside 9.8.1/9.8.2, adjusted by the employer on the actual change (9.8.4).
- Provisional prices versus provisional sums: a provisional price is a price-to-be-fixed item - under 9.9.1 fixed by tendering and replacing the provisional price; a provisional sum is a fund reserve, not an independent adjustment event - used only on the employer's instruction, any balance returning to the employer (9.15), funding the payments arising under 9.1 to 9.14.
6. Mapping to GB/T 50500-2024 (the current edition)
- The 15% quantity boundary becomes two tiers, 'up to and including 15%' and 'beyond 15%': clause 8.9.1 - where a variation or BOQ errors and omissions change the items (added or removed), or quantities change by no more than 15% (15% inclusive), the all-in unit rate is determined under that clause: (1) same item description, same construction conditions - the corresponding contract rate; (2) similar description under the same conditions, or the same description under similar conditions - the converted and adjusted contract rate of a similar BOQ item; (3) different description under the same conditions, or the same description under different conditions - a negotiated market-reasonable all-in unit rate referencing similar items' pricing rules and tender level; (4) different description, different conditions - negotiated referencing the all-in unit rates of similar BOQ items of comparable works; (5) a reduction or cancellation that materially changes the construction conditions - negotiated from the circumstances, market prices, contract pricing rules and tender level.
- Beyond 15% (15% excluded): clause 8.9.2 - where BOQ items and quantities increase, the contract rates and new all-in unit rates may be reasonably reduced to reflect the procurement discounts on labour and materials; where they decrease, the rates are reasonably increased to reflect the loss of those discounts.
- Two-tier treatment of errors and omissions: clause 8.2.1 - under a unit-rate contract all divisional and sub-divisional BOQ items and quantities of the contract drawings are re-measured under 7.2.1; errors and omissions causing item changes or a quantity deviation within 15% (inclusive) go to clause 8.9.1, beyond 15% (exclusive) to clause 8.9.2; 'omitted items, item description mismatches and quantity deviations' all belong to BOQ errors and omissions.
- Force majeure sharing (clause 8.11.12): employer - damage to the permanent works and delivered materials plus repairs; third-party casualties and property losses within the site or caused by the works; during suspension, care, cleaning and repair costs and wages of management and security personnel kept on site and of waiting workers; extension of time and required acceleration costs. Contractor - its construction plant damage and suspension costs; damage to and cleaning/repair of its preliminaries items; third-party losses it causes. Each party bears its own personnel casualties and other uncovered property losses; insurance recovery and deductible-sharing rules are included.
- '9.x' provisions of the 2013 edition appear in the 2024 edition scattered through Chapter 8 (8.2 BOQ errors, 8.9 rate adjustment, 8.11 claims); cite the current edition's clause numbers.
Applicable boundaries
- The clause wording here is from Chapter 9 of GB 50500-2013, superseded by GB/T 50500-2024 (a recommended standard). Newly signed contracts and works performed after the 2024 edition should follow GB/T 50500-2024; the 2013 clauses apply only to works contracted under that edition or expressly citing it, and to checking the basis in existing final account disputes.
- The clauses of Chapter 9 presuppose 'as agreed in the contract' (9.1.1 reads 'among others'); where the contract stipulates otherwise on adjustable scope, bands, procedures or time limits, the contract governs; the limits listed here (28 days, 7 days, 48 hours, 24 hours, 2 days) are the standard's defaults, a stricter or looser contractual limit prevailing.
- The 15% line in 9.6.2 is 'exceeding 15%' - exactly 15% does not trigger it (the 2024 edition is the opposite in 8.9.1: 15% inclusive stays in the no-adjustment tier); the two editions draw the boundary differently and must not be mixed.
- The adjustment time point under 9.2 and the adverse-adjustment principle where the contractor is responsible for delay must be judged against the contractual time provisions and the commentary; this card gives only the base date rule.
- This card is an index of clause mapping and order of application, not a substitute for interpreting the project contract; amounts and rates must be computed from the project contract and the locally published rules.
Further reading
- GB 50500-2013: clause 9.1.1 and commentary (five-category grouping); 9.2.1; 9.3.1 and 9.3.2; 9.4.2; 9.5.1; 9.6.2 and 9.6.3; 9.7.1 and 9.7.3; 9.8.1, 9.8.2 and 9.8.4 with Annex A; 9.9.1; 9.10.1; 9.11.2; 9.12.1 and 9.12.2; 9.13.2, 9.13.3 and 9.13.6; 9.14.2, 9.14.4 and 9.14.5; 9.15; and clause 3.1.5 (mandatory HSE provisions).
- GB/T 50500-2024: clauses 8.2.1, 8.9.1, 8.9.2, 8.11.12; sections 7.1 to 7.4; Annex A and Annex G.
- Companion references: GB/T 50875-2013 (terminology standard) for 'all-in unit rate', 'provisional sums', 'dayworks', 'site instruction record'; local adjustment rules issued under 9.2.1.