Section order of Chapter 9 'adjustment of the contract price' in GB 50500-2013 mapped to the clause numbers of GB/T 50500-2024: dayworks 9.7 -> 8.6, provisional prices 9.9 -> 8.4, claims 9.13 -> 8.11, provisional sums 9.15 -> 8.3
GB 50500-2013 (withdrawn) Chapter 9 runs: 9.2 changes in laws and regulations, 9.3 variations, 9.4 mismatch of item descriptions, 9.5 BOQ omissions, 9.6 quantity deviations, 9.7 dayworks, 9.8 changes in costs, 9.9 provisional prices, 9.10 force majeure, 9.11 earlier completion (acceleration compensation), 9.12 delay damages, 9.13 claims, 9.14 site instruction records, 9.15 provisional sums. GB/T 50500-2024 consolidates these price-adjustment events into Chapter 8: BOQ errors 8.2, provisional sums 8.3, provisional prices 8.4, dayworks 8.6, changes in costs 8.7, variations 8.9, additional works 8.10, claims 8.11; the final account items are listed in Clause 10.3.2 (provisional sums item 3, provisional prices item 4, dayworks item 6, claims item 11). The common miscitations 'provisional prices 9.8, dayworks 9.9, claims 9.14' all fail against the actual section order of both editions.
Applicable Codes
- GB 50500-2013 建设工程工程量清单计价规范 第9.1.1条及条文说明(Ch. 9节序)、第9.7.4条、第9.13.3条、第9.15节(已废止)
- GB/T 50500-2024 建设工程工程量清单计价标准 第8.1.1条、第8.2~8.11节、第10.3.2条
Topic positioning
A clause-number mapping and error-correction tool for the 'adjustment of the contract price' events across the two BOQ pricing standards: the section order of GB 50500-2013 Chapter 9 against the sections of GB/T 50500-2024 Chapter 8, for spotting mis-cited old clause numbers and for taking evidence on separate footings for legacy-contract and current projects.
Core conclusions
I. Section order of Chapter 9 'adjustment of the contract price' in GB 50500-2013 (withdrawn; per the commentary to Clause 9.1.1 of that edition) Clause 9.1.1 of that edition lists 15 classes of events requiring adjustment of the contract price, and the commentary groups them into five families with their section numbers:
- legal and regulatory changes: 9.2 changes in laws and regulations;
- variations: 9.3 variations, 9.4 mismatch of item descriptions, 9.5 BOQ omissions, 9.6 quantity deviations, 9.7 dayworks;
- cost changes: 9.8 changes in costs, 9.9 provisional prices;
- claims: 9.10 force majeure, 9.11 earlier completion (acceleration compensation), 9.12 delay damages, 9.13 claims;
- others: 9.14 site instruction records, plus other adjustment matters agreed between employer and contractor;
- plus 9.15 provisional sums (Clauses 9.15.1 and 9.15.2: provisional sums may be used only on the instructions of the employer, and the balance after deducting amounts paid belongs to the employer).
II. Corresponding clause numbers in GB/T 50500-2024 (current) The 2024 edition consolidates the contract price adjustment events into Chapter 8 'adjustment of the contract price', with the section numbers:
| Event | 2013 edition section (withdrawn) | 2024 edition clause |
|---|---|---|
| BOQ errors / item description mismatch / omissions | 9.4, 9.5 | Section 8.2 |
| Provisional sums | 9.15 | Section 8.3 (8.3.1, 8.3.5) |
| Provisional prices (materials / specialist works) | 9.9 | Section 8.4 (8.4.1, 8.4.5, 8.4.6, 8.4.7) |
| Dayworks | 9.7 | Section 8.6 (8.6.2-8.6.5); measurement in Section 7.5 |
| Changes in costs | 9.8 | Section 8.7 (beyond 5% adjusted per Annex A where no band is agreed; see 8.7.2) |
| Variations | 9.3 | Section 8.9 |
| Additional works | none (no separate 2013 section) | Section 8.10 |
| Claims | 9.13 | Section 8.11 (8.11.1-8.11.21) |
| Site instruction records | 9.14 | item abolished; out-of-contract work routed to variations, additional works or dayworks |
| Final account items | scattered across Chapter 9 | Clause 10.3.2, 13 items (provisional sums item 3, provisional prices item 4, dayworks item 6, claims item 11) |
III. Common mis-citations and corrections
- Mis-citing 'provisional prices = 2013 edition 9.8': 9.8 is changes in costs; provisional prices are 9.9.
- Mis-citing 'dayworks = 2013 edition 9.9': 9.9 is provisional prices; dayworks are 9.7 (Clause 9.7.4 of that edition: priced at the certified quantity x the dayworks unit rates in the priced BOQ).
- Mis-citing 'claims = 2013 edition 9.14': 9.14 is site instruction records; claims are 9.13 (Clause 9.13.3 of that edition sets the claim handling procedure and the 28-day response period).
- Only 'provisional sums = 9.15' holds good in the 2013 edition; but under the 2024 edition none of these four events appears in Chapter 9 - they sit in Sections 8.3, 8.4, 8.6 and 8.11 - so in a 2024 context the numbers 9.8 / 9.9 / 9.14 / 9.15 correspond to nothing.
Boundaries of applicability
- For self-checking clause citations and for aligning the evidence basis of old and new projects: newly executed contracts and current settlements cite GB/T 50500-2024 Chapter 8 and Clause 10.3.2; only legacy projects signed under the 2013 edition, or settlements audited under the old edition, cite the Chapter 9 numbers, and they must cite the actual section numbers per the table above - misaligned numbers must not be carried forward.
- This mapping covers the section-level correspondence only; the content of individual clauses and their figures must still be taken from the text of each edition, and the substantive rules of the two editions are not one-to-one (the 2024 edition abolishes the statutory site-record procedure, changes the consequence of a late claim from 'the right to claim is lost' to 'may be treated as waived', and adds dayworks rules on settlement deductions and VAT difference adjustments).
- Sectoral standards (highway or railway pricing rules, for example) are systems of their own; this mapping does not reach them.
Further reading
GB 50500-2013, code for BOQ pricing of construction works: Clause 9.1.1 and its commentary (15 adjustment events and their grouping), Clause 9.7.4 (dayworks), Section 9.15 (provisional sums); GB/T 50500-2024, standard for BOQ pricing of construction works: Clause 8.1.1 (11 adjustment events), Sections 8.2, 8.3, 8.4, 8.6, 8.7, 8.9, 8.10 and 8.11, and Clause 10.3.2 (final account items).
Keywords
- 条文号对照
- GB 50500-2013
- GB/T 50500-2024
- 第9章 合同价款调整
- 第8章 合同价款调整
- 计日工9.7
- 暂估价9.9
- 索赔9.13
- 暂列金额9.15