Line items and order of the final account price (the 13 items of GB/T 50500-2024, Clause 10.3.2)
Final account documents list 13 items in order: contract BOQ total -> errors and omissions in the BOQ adjustment -> provisional sums adjustment -> adjustment of provisional prices after procurement (materials + nominated specialist subcontract works) -> main contractor's attendance and coordination provisions adjustment -> dayworks adjustment -> changes in costs adjustment -> laws, regulations and policy changes adjustment -> variations -> additional works -> claim amounts -> penalties -> other amounts; this both standardizes final account compilation and supports cost-indicator statistics and cost estimation for similar works.
Topic Positioning
Which items a final account document lists and in what order — GB/T 50500-2024 "China national pricing standard for BOQ (GB/T 50500)", Clause 10.3.2, gives the 13-item statutory order, the baseline for compiling the final account, checking the basis of the final account, and cost-indicator statistics.
Core Conclusions
The final account price lists 13 items in order: ① contract BOQ total; ② adjustment for errors and omissions in the BOQ; ③ provisional sums adjustment; ④ adjustment of provisional prices after procurement (prime cost (PC) sums for materials + provisional sum for nominated specialist subcontract works, the latter applying to main (general) contracting contracts); ⑤ main contractor's attendance and coordination provisions adjustment (main (general) contracting contracts); ⑥ dayworks adjustment; ⑦ changes in costs adjustment; ⑧ laws, regulations and policy changes adjustment; ⑨ variation increase/decrease; ⑩ additional works; ⑪ claim amounts; ⑫ penalties for non-performance per contract; ⑬ other amounts (if any). The final account document is compiled in this order; the clause also serves the compilation of cost indicators for similar works and cost-estimation applications.
Applicable Boundaries
Applies to compiling and checking final account documents for contracts performed normally to completion. Distinguish two other listings: interim settlement by construction stage payment applications per Clause 10.2.10 (cumulative settled amount, cumulative paid, current deductions, current payable); settlement on termination of contract per Section 10.4. In the final account, "quantities" lock via dual-signed measurement of the works results per Section 7.1; "prices" follow the contract and the order of the employer's approval of material prices; the employer's overdue non-checking deemed-acceptance fallback is Clause 10.3.8.
Further Reading
GB/T 50500-2024 "China national pricing standard for BOQ (GB/T 50500)", Clause 10.3.2 (item order), Clause 10.2.10 (interim settlement by construction stage payment application), Clause 10.3.8 (overdue deemed acceptance), Section 7.1 (measurement of the works); terms: GB/T 50875-2013, Clauses 3.4.9, 3.4.10 (construction payment settlement classification and final account definition).
Keywords
- final account
- 结算价款列项
- 结算文件编制
- 合同价款调整事项
- 合同清单总价
- GB/T 50500-2024
- 造价指标