Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Completion-settlement treatment of provisional sums: incurred amounts entered per actuals, unused amounts wholly deducted (GB/T 50500-2024, Section 8.3)

The provisional sum is controlled by the employer and used on the employer's instructions; it does not belong to the contractor. Settlement general principle: amounts actually incurred are entered per actuals (quantities per mutually confirmed drawings, priced at contract unit prices); unused amounts are wholly deducted and revert to the employer; what enters the settlement is the "provisional sum adjustment amount" (settlement line item 3), i.e., the difference between the actually confirmed price and the original provisional sum, the price adjustment including VAT; provisional sums for specified materials/nominated works (materials/specialized works) are handled separately under Section 8.4 — the two must not be conflated.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.13条(暂列金额术语)
  • GB/T 50500-2024 第8.3.1条(发包人掌握、未使用归发包人)
  • GB/T 50500-2024 第8.3.5条(未发生事件全额扣除、按实际完成计算)
  • GB/T 50500-2024 第10.3.2条(竣工结算列项第3项)
  • GB 50500-2013 建设工程工程量清单计价规范 第9.15节(已废止,已被2024版第8.3节替代)

Topic Positioning

This card covers the nature and final account treatment of provisional sums, per GB/T 50500-2024, Clauses 2.0.13, 7.2.3, 8.3, and 10.3.2 — for construction payment settlement of BOQ-priced works whose contract price includes a provisional sum.

Core Conclusions

The provisional sum is a reserve the employer tentatively includes in the contract price for works, services, and price adjustments not yet determined or detailed at tendering: controlled by the employer, used on the employer's instructions, and not owned by the contractor. Settlement general principle — incurred amounts entered per actuals, unused amounts wholly deducted: absent adjustment events, the full amount is deducted at settlement and reverts to the employer; amounts used for undetermined works are computed per the actual works completed at the employer's request, and works the employer did not request are deducted from the contract price. The settlement line item is the "provisional sum adjustment amount" (settlement line item 3) — the difference between the actually confirmed price and the original provisional sum, positive or negative. Pricing: quantities per mutually confirmed drawings at contract unit prices, changes in preliminaries adjusted per the variation rules (Section 8.9); the price adjustment includes VAT.

Applicable Boundaries

Applies to BOQ-priced works whose contract price includes a provisional sum; other contractual agreements govern. Provisional sums for specified materials/nominated works (materials/specialized works) follow Section 8.4 separately — do not conflate. Practical reminders: use presupposes the employer's written instruction, otherwise it may be found "not requested by the employer" and deducted; keep a separate ledger, one order one settlement; unused portions must be returned.

Further Reading

See GB/T 50500-2024, Clause 2.0.13 (term), Clause 7.2.3 (measurement), Clauses 8.3.1-8.3.5 (nature and adjustment), Clause 10.3.2 (settlement line items); compare Section 8.4 provisional sums for specified materials/nominated works and Section 8.9 unit-price adjustment for variations.

Keywords

  • provisional sums
  • provisional sum
  • 暂列金额余额
  • 暂列金额调整价款
  • 第8.3节
  • 发包人指令
  • 竣工结算扣除
  • 第2.0.13条

Cited By