Treatment of the four items of the bill of provisional sums and other charges under GB/T 50500-2024 in performance and at the final account: unused provisional sums revert to the employer, provisional prices replaced and adjusted, dayworks measured as incurred, main contractor's attendance and coordination provisions lump-sum or re-rated, plus the final account item sequence (sections 8.3-8.6, clauses 10.3.2 / 10.3.3)

Under GB/T 50500-2024: provisional sums (8.3.1, 8.3.5) are controlled by the employer and used per instruction; they accrue to the contractor only when actually incurred, and where no adjustment event occurs the whole amount is deducted at the final account with the balance reverting to the employer. Provisional prices (8.4) are replaced by the tender winning price or a price confirmed by the employer; for materials only the pre-tax material provisional price inside the all-in unit rate is adjusted and other costs stand, while nominated specialist works are replaced wholesale at tax-inclusive prices. Dayworks (8.6) are measured as incurred under section 7.5 and priced at the contract dayworks rates; the final account includes the amounts actually incurred and deducts the dayworks amounts of the original BOQ, with no separate preliminaries. Main contractor's attendance and coordination provisions (8.5): when priced per item they are at lump-sum risk and not adjusted at the final account; when priced by percentage rate they may adjust under clauses 8.5.1-8.5.5 for changes in the scope of materials or subcontract works, variations, or employer-caused time changes; contractor-caused delay is not adjusted and attracts delay damages. The final account lists items in the 13-item sequence of clause 10.3.2, and attendance provisions and preliminaries must be re-calculated per clause 10.3.3.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.3.1条、8.3.2条、8.3.5条(暂列金额)
  • GB/T 50500-2024 第8.4.1条、8.4.5条、8.4.6条、8.4.7条、8.4.8条(暂估价)
  • GB/T 50500-2024 第8.5.1条~8.5.6条(总承包服务费)
  • GB/T 50500-2024 第8.6.1条~8.6.5条、第7.5.2条(计日工)
  • GB/T 50500-2024 第10.3.2条、第10.3.3条(竣工结算列项与重算)
  • GB/T 50500-2024 App. E Table E.4.5、Table E.8.2
  • GB 50500-2013 建设工程工程量清单计价规范 第9.15节(已废止,暂列金额余额归属)

Topic Positioning

Which way each of the four items of the bill of provisional sums and other charges (provisional sums, provisional prices, dayworks, main contractor's attendance and coordination provisions) adjusts during performance and at the final account: unused provisional sums are deducted with the balance to the employer; provisional prices are replaced by confirmed or winning prices and the difference adjusted; dayworks are measured as incurred with the original BOQ amount deducted; attendance provisions are lump-sum when priced per item and re-calculable when priced by rate. Also the line-item sequence of the final account.

Core Conclusions

1. Provisional sums: employer-controlled, incurred as certified, unused balance to the employer

  • 8.3.1: provisional sums inside the total contract price are controlled by the employer and used under instructions issued by the employer. Though listed in the total contract price they do not belong to the contractor and may never arise; only when actually incurred under the contract do they become payment due to the contractor and enter the works settlement. Unused provisional sums belong to the employer at the final account.
  • 8.3.2 (for works not fully foreseeable or specifiable in detail): the parties calculate the quantities of the bill of work items from the construction drawings confirmed by both parties and the adjusted price at contract unit rates; resulting changes in preliminaries may be calculated and adjusted under section 8.9; 'the contract price shall be adjusted by the difference between the determined adjusted price and the provisional sum', and the total contract price adjusted for the provisional sum difference includes the adjustment of VAT. Unless the contract provides otherwise, measurement and valuation may follow the variation rules.
  • 8.3.5 (two settlement paths): where no provisional sum adjustment event has occurred during performance, the provisional sums inside the total contract price are deducted in full at settlement; where an event has occurred, declaration, verification and determination of the adjusted provisional sum price follow Chapter 8 and payment follows Chapters 9 and 10. Sums used for works or services not yet specified or not specifiable in detail are calculated on the actual work or services completed at the employer's request; what the employer has not requested is deducted from the total contract price at the final account.

2. Provisional prices: replaced by confirmed or winning prices, adjusting price elements only

  • 8.4.1 (statutorily tendered): the pre-tax material price and (or) the tax-inclusive specialist subcontract price determined by tendering replace the provisional prices and adjust the contract price. The material provisional price is a pre-tax unit rate (VAT excluded) and the specialist works provisional price is tax-inclusive: materials substitute the 'winning pre-tax procurement price' for the original provisional pre-tax price, and specialist subcontracts substitute the 'winning tax-inclusive tender price' for the original tax-inclusive provisional price of the specialist works.
  • 8.4.5 / 8.4.6 (materials not statutorily tendered): the contractor may enquire the market or offer its own price, and after employer confirmation the pre-tax price replaces the provisional price; or the parties enquire jointly, confirm and replace at a pre-tax price, computing the VAT change caused by the price adjustment. 'Price adjustment of a BOQ item carrying a material provisional price adjusts only the pre-tax material provisional price inside the all-in unit rate; other costs included in the all-in unit rate shall not be adjusted.' The adjusted contract unit rate then serves the valuation of BOQ errors, provisional sums and variations under sections 8.2, 8.3 and 8.9.
  • 8.4.7 (specialist works not statutorily tendered): a VAT-inclusive specialist works price may be determined under section 8.10 to replace the provisional price of the specialist works, or the parties may tender jointly and determine a VAT-inclusive specialist subcontract price as the replacement.
  • 8.4.8: where the contractor tenders for provisional-sum specialist works tendered by the employer as tenderer and wins, the attendance and coordination provisions for those specialist works are deducted per clause 8.5.3 - provisional-sum specialist works won and executed by the contractor no longer attract those provisions.

3. Dayworks: measured as incurred, priced at contract rates, original BOQ amounts deducted

  • 8.6.1 / 8.6.2: where work under the contract is not suitably priced under the contract and the national or sectoral BOQ pricing standards for the relevant works, dayworks pricing may be used; measurement follows section 7.5, and pricing follows the all-in unit rate of the dayworks items in the contract BOQ (quantity x contract dayworks rate).
  • 8.6.3 (path where no applicable rate exists): (1) first, the works price information published by the market price source agreed in the contract; where the contract is silent or unclear, the net-of-tax market price information for labour, materials and plant rental published by the cost administration department or the industry at the project location, and the detailed price build-up in the all-in unit rate analysis sheets of similar BOQ items in the contract BOQ; (2) where that information contains no relevant market price, the contractor's purchase rate confirmed by the parties, and the detailed price build-up of similar BOQ items.
  • 8.6.4: the dayworks all-in unit rate shall include the extra costs arising from the sporadic and small-scale character of daywork items and the preliminaries attributable to them; the preliminaries in the total contract price are not adjusted because dayworks occur (preliminaries are already inside the dayworks rate and are not charged again).
  • 8.6.5 (settlement): daywork items calculable under the contract all enter the settlement total, but the dayworks items of the contract BOQ included in the total contract price are deducted from the settlement total; VAT is adjusted by multiplying 'the total confirmed dayworks price actually incurred minus the total dayworks price inside the total contract price' by the applicable VAT rate.
  • 7.5.2, ten situations where dayworks measurement and pricing may be used: additional or substitute works not measurable under the construction drawings, variations or the contract measurement rules; short-duration, incidental, limited-scope or small-quantity items added at the employer's request; abnormal operation caused by extreme changes in working conditions; repair of damage to other works caused by emergency works; opening of concealed works at the employer's request where testing proves compliance with the contract; costs of repairing surrounding works affected after another contractor completes its work; costs of replacing materials forced by extension caused by the employer suspending (stopping) the works; cleaning and clearing outside the contract scope specially required by the employer; test runs outside the contract scope required by the employer; repair and restoration of minor damaged works not caused by the contractor (large-scale restoration is measured and priced as a variation).

4. Main contractor's attendance and coordination provisions: lump-sum when priced per item, re-calculable when priced by rate

  • 8.5.1: where employer-supplied (free-issue) materials change to contractor-supplied, the all-in unit rates of the affected work items adjust per clause 3.6.6 and the corresponding attendance and coordination provisions for those free-issue materials charged in the total contract price are deducted.
  • 8.5.2: where contractor-supplied materials change to employer-supplied (free-issue), the increased attendance and coordination provisions are calculated per clause 3.7.4 and the contract price adjusted; the fee or rate for the new item may be negotiated by reference to the attendance schedule item of the material category and delivery time closest within the total contract price.
  • 8.5.3: where provisional-sum specialist subcontracts or specialist works directly let by the employer are cancelled, or confirmed for completion by the contractor, or won by the contractor under clause 8.4.8, or performed after the contractor's contract works are complete and it has left site, the corresponding attendance and coordination provisions charged in the total contract price are deducted.
  • 8.5.4: attendance and coordination provisions priced per item are at lump-sum risk and are not adjusted at works settlement, apart from deductions or adjustments under clauses 8.4.8, 8.5.1-8.5.3 and 8.5.5; where priced by percentage rate and the contract does not agree the rate base (or agrees unclearly), adjustment follows the clauses above, and at settlement the fee may be computed on the contract prices of specialist subcontracts and directly let specialist works and on the supply contract prices of employer-supplied materials (Table E.4.5: enter the 'confirmed calculation base A2' at settlement; settlement amount C2 = A2 x B).
  • 8.5.5: where a variation occurs in an employer-approved specialist subcontract, or employer-caused events substantially change the time of the relevant specialist subcontracts or directly let specialist works, the affected attendance and coordination provisions may be recalculated and adjusted.
  • 8.5.6: where contractor-caused events substantially extend the time of the relevant specialist subcontracts or directly let specialist works, the contractor pays the employer the delay damages under clause 8.11.18; where the substantial extension stems from the main contractor's failure to perform its management, coordination and cooperation duties, the attendance and coordination provisions for those specialist works are not adjusted, and the contractor pays the delay damages agreed in the contract.

5. Line-item sequence and re-calculation at the final account

  • 10.3.2 sequence of final account items: 1 total price of the contract BOQ; 2 adjustments for BOQ errors; 3 provisional sum adjustments (for works and services not fully foreseeable or specifiable in detail per clause 2.0.13); 4 provisional price adjustments (1 material provisional price adjustments; 2 specialist works provisional price adjustments, applicable to main contracting contracts); 5 attendance and coordination provision adjustments (applicable to main contracting contracts); 6 dayworks adjustments; 7 adjustments for changes in costs; 8 adjustments for changes in laws, regulations and policies; 9 additions and omissions from variations; 10 additional works; 11 claims; 12 liquidated damages for non-performance under the contract; 13 other amounts (if any).
  • 10.3.3: at the final account the preliminaries and the attendance and coordination provisions are re-calculated and determined - the provisions are calculated per section 8.5 for all specialist subcontracts, directly let specialist works and employer-supplied materials; preliminaries and provisions listed in interim settlements by construction stage are not a basis of the final account.
  • Dayworks settlement details follow Table E.8.2 of Annex E, 'dayworks final (interim) settlement detail sheet', valued on the actual quantities confirmed by the parties (Table E.4.4, note 2).

Applicability Boundaries

  • Version note: section 9.15 of GB 50500-2013 read: 'Provisional sums in the priced contract may be used only as instructed by the employer. Though listed in the contract price they do not belong to the contractor, nor do they necessarily arise; only when actually incurred under the contract do they become amounts due to the contractor and enter the works settlement ... the provisional sum balance (if any) remains the employer's.' The direction matches the 2024 edition, but GB 50500-2013 is withdrawn: current citations go to clauses 8.3.1 and 8.3.5 of GB/T 50500-2024, and section 9.15 must no longer be cited.
  • The replacement bases of material provisional prices (pre-tax) and specialist works provisional prices (tax-inclusive) differ; the material adjustment rules must not be transplanted to specialist works. Material adjustment moves the material provisional price element only; overheads, profit and other costs are not adjusted (see section 8.4).
  • 'Lump sum' for attendance and coordination provisions targets per-item pricing only; where priced by rate with an agreed base, the fee is computed on that base and re-calculation does not apply.
  • Dayworks preliminaries are already inside the all-in unit rate, and the employer may not approve further preliminaries because dayworks occur; dayworks do not apply to works measurable normally under drawings, variations or the contract measurement rules, nor to large-scale restoration of damage (handled as a variation).
  • Specialist works and labour works subcontracted by the contractor on its own attract no attendance and coordination provisions; exclude them before any deduction.

Further Reading

  • GB/T 50500-2024 clauses 8.3.1, 8.3.2, 8.3.5 (use, adjustment and settlement deduction of provisional sums); clause 2.0.13 (definition of provisional sums).
  • Clauses 8.4.1, 8.4.5, 8.4.6, 8.4.7, 8.4.8 (replacement and price adjustment of provisional prices); section 8.10 (price determination of non-tendered specialist works).
  • Clauses 8.5.1-8.5.6 (adjustment and lump-sum rules of attendance and coordination provisions); clauses 3.6.6 and 3.7.4 (rate adjustment when free-issue and contractor-supplied materials interchange).
  • Clauses 8.6.1-8.6.5 and section 7.5 (dayworks pricing, measurement and settlement); clause 8.11.18 (delay damages).
  • Clauses 10.3.2 and 10.3.3 (final account itemisation, re-calculation of preliminaries and attendance provisions); Annex E Table E.4.5 (settlement column of the attendance pricing sheet, C2 = A2 x B), Table E.8.2 (dayworks final (interim) settlement detail sheet).
  • Bound settlement documents may follow the 13 items of clause 10.3.2 directly, easing the compilation of cost benchmarks for similar projects.

Keywords

  • 其他项目清单结算
  • 暂列金额余额归发包人
  • 暂估价取代调价
  • 计日工据实计量
  • 总承包服务费包干
  • 竣工结算列项
  • GB/T 50500-2024 第8章