GB/T 50500-2024 rules for pricing dayworks and deducting them in the final account: quantity measured as incurred x the contract dayworks all-in unit rate, deduction of the dayworks BOQ items from the total settlement price, and VAT adjusted on the difference
Dayworks are priced under GB/T 50500-2024 clause 8.6.2: measured in accordance with section 7.5, with the dayworks amount determined as the calculated quantity multiplied by the corresponding dayworks all-in unit rate in the contract BOQ. At settlement, under clause 8.6.5, all dayworks items that the contract requires to be counted are included in the total settlement price, but the dayworks items carried in the contract BOQ and included in the contract price must be deducted from that total (to prevent double counting); dayworks VAT is adjusted by multiplying the difference between the confirmed total of dayworks amounts actually incurred and the total of dayworks amounts carried in the contract price by the applicable VAT rate.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.6.2条、第8.6.5条
- GB/T 50500-2024 第7.5节(计日工计量)
- GB/T 50500-2024 第10.3.2条第6项
- GB/T 50500-2024 第2.0.16条(计日工术语)
Topic Scope
Section 8.6 of GB/T 50500-2024, the China national pricing standard for BOQ, governs the measurement and pricing of dayworks and the treatment of dayworks amounts in the total final account price under a logic of full inclusion, deduction of the originally billed items, and VAT on the difference.
Core Conclusions
- Pricing basis (clause 8.6.2): 'Works or tasks priced on a dayworks basis shall be measured in accordance with section 7.5 of this standard and priced by reference to the all-in unit rates of the dayworks items in the contract bill of quantities'; 'the relevant dayworks amounts shall be determined as the quantities calculated under the relevant provisions multiplied by the corresponding dayworks contract rates in the contract bill of quantities'. That is, dayworks rates are always the all-in unit rates already stated in the contract BOQ; no new rate build-up is made, only the quantities are confirmed as actually incurred (measured under section 7.5, typically confirmed daily through site instruction records covering trades and labour-hours, materials, and plant machine-shifts).
- Listing at settlement (clause 8.6.5): 'At settlement of the works, dayworks items that the contract requires to be counted shall all be included in the total settlement price, but dayworks items in the contract bill of quantities that are included in the contract price shall be deducted from the total settlement price.' The first half ensures that dayworks actually incurred are not omitted; the second half prevents double counting between dayworks items already carried in the contract price and the amounts actually incurred.
- VAT adjustment (clause 8.6.5): 'The VAT on dayworks items shall be adjusted on the amount obtained as the confirmed total of dayworks amounts actually incurred minus the total of dayworks amounts in the contract price, multiplied by the applicable VAT rate' - that is, tax is charged only on the net difference, with no double taxation of dayworks items already taxed within the contract price.
- Position in the settlement documents: under clause 10.3.2, the dayworks adjustment amount is item 6 of the final account price items, placed after the adjustment amount for main contractor's attendance and coordination provisions and before the price adjustment for changes in costs.
The settlement treatment can be summarised as: 'quantity measured as incurred x contract dayworks all-in unit rate -> fully included in the total settlement price -> dayworks items already carried in the contract price deducted -> VAT charged on the difference'.
Applicable Boundaries
- Applies only where dayworks items with pre-set all-in unit rates are provided in the contract BOQ; where the contract sets no dayworks rates and a separate pricing method must be agreed, this treatment does not apply and the contract or a supplementary agreement governs.
- Dayworks are for work within the scope agreed in the contract (typically minor tasks not suited to pricing under the measurement rules); work that can already be measured and billed as divisional/sub-divisional work items must not be switched to dayworks pricing, which would amount to double counting or evasion of the contract rates.
- Dayworks quantities must be supported by certified on-site measurement records (trade, labour-hours, materials, plant machine-shifts); measurement without certification cannot enter the settlement.
- The standard is a recommendatory national standard, binding only where incorporated by the contract; where the contract provides otherwise for dayworks settlement, the agreed terms prevail.
Further Reading
- GB/T 50500-2024 clauses 8.6.2 and 8.6.5 (dayworks pricing and deduction at settlement); clause 2.0.16 (definition of dayworks).
- GB/T 50500-2024 section 7.5 (dayworks measurement, clauses 7.5.2 to 7.5.6).
- GB/T 50500-2024 clause 10.3.2, item 6 (final account price items - dayworks adjustment amount).
- Related: clause 8.1.1, the eleven categories of contract price adjustment (dayworks being one of them); site instruction records and the certification elements of dayworks (signing chain of personnel, timing, quantity evidence, price basis).