Engineering Knowledge Cards.

dayworks

14 knowledge cards · sorted by most recently updated

Concept Guide

Concept

Dayworks is a reimbursement mechanism in Chinese bill-of-quantities pricing (GB 50500-2013; GB/T 50500-2024), forming one of the "other project costs". The employer's daywork schedule lists provisional items in three groups — labour (measured in work-days), materials (by quantity) and construction plant (by machine-shift) — and bidders enter a rate for each item when tendering. Those rates are normally all-in unit rates, covering labour, materials, plant, overheads and profit.

Settlement follows an actual-quantity-times-quoted-rate logic: quantities are confirmed by certified dayworks records (site instruction and signed measurement) and then valued at the tendered daywork rates, while items left unpriced are generally not paid. Dayworks therefore act both as a provisional allowance for unforeseen risk and as a lawful valuation route for miscellaneous and temporary additional work, with the rate level driven by the bidder's pricing strategy and enterprise cost data rather than by post-hoc negotiation.

FIDIC Mapping

Corresponding terms: 计日工 = dayworks; 计日工表 = Daywork Schedule; 计日工签证 = certified dayworks records.

Under the FIDIC Red Book, Sub-Clause 1.1.26 defines "Daywork Schedule" as the document included in the Contract showing the amounts and manner of payment to the Contractor for labour, materials and equipment used for daywork. Sub-Clause 13.5 [Daywork] requires the Contractor to deliver each day accurate statements in duplicate, plus one electronic copy, showing the resources used in executing the previous day's work as recorded under Sub-Clause 6.10 [Contractor's Records]. Statements that are correct and agreed are signed by the Engineer and returned; where a statement is not correct and agreed, the Engineer proceeds under Sub-Clause 3.7 to agree or determine. If no Daywork Schedule is included, Sub-Clause 13.5 does not apply.

Both systems value daywork as actual resources consumed multiplied by pre-agreed rates. The institutional difference lies in the pricing infrastructure and the decision-making party: in China rates are derived from the quota system and entered by bidders, with quantities confirmed by site records; in FIDIC the rates are those the bidder inserts in the Daywork Schedule attached to the Bill of Quantities, and the measurement basis is the Contractor's daily resource statements countersigned by the Engineer. Usage warning: dayworks denotes a contractual valuation mechanism, not a work order or a timesheet, and it is distinct from paying labour by the day.

Chinese TermEnglish TermFIDIC TermRelationNotes
计日工dayworksDaywork (Sub-Clause 13.5); Daywork Schedule (Sub-Clause 1.1.26)identical两侧均为零星工作按实际消耗资源计价的机制,差异在计价基础设施:中国计日工单价从定额取定并由投标人在计日工表中报价,结算按现场签证确认的数量计价;FIDIC 单价来自工程量清单所附 Daywork Schedule 的投标报价,以承包商每日报送、工程师签认的资源记录为计量凭据,有争议时按 3.7 商定或确定。
计日工签证certified dayworks recordsContractor's daily daywork statements (Sub-Clause 13.5, with records under Sub-Clause 6.10)adjacent中国侧以现场签证确认实际数量,再乘以已报计日工单价计价;FIDIC 侧以承包商每日提交的报表为凭据,报表正确并达成一致才由工程师签署返还,不能一致时转入 3.7 商定或确定程序,程序性与签认主体不同。
综合单价all-in unit rateamounts and manner of payment stated in the Daywork Schedule (Sub-Clause 1.1.26)adjacent中国计日工单价通常为含人材机、管理费与利润的综合单价,由投标人按定额及自身水平填报;FIDIC 的 Daywork Schedule 载明劳务、材料与设备的支付金额与方式,其构成依合同附表约定,不套用中国的定额取费体系。

Updated 2026-09-13