dayworks
Concept Guide
Concept
Dayworks is a reimbursement mechanism in Chinese bill-of-quantities pricing (GB 50500-2013; GB/T 50500-2024), forming one of the "other project costs". The employer's daywork schedule lists provisional items in three groups — labour (measured in work-days), materials (by quantity) and construction plant (by machine-shift) — and bidders enter a rate for each item when tendering. Those rates are normally all-in unit rates, covering labour, materials, plant, overheads and profit.
Settlement follows an actual-quantity-times-quoted-rate logic: quantities are confirmed by certified dayworks records (site instruction and signed measurement) and then valued at the tendered daywork rates, while items left unpriced are generally not paid. Dayworks therefore act both as a provisional allowance for unforeseen risk and as a lawful valuation route for miscellaneous and temporary additional work, with the rate level driven by the bidder's pricing strategy and enterprise cost data rather than by post-hoc negotiation.
FIDIC Mapping
Corresponding terms: 计日工 = dayworks; 计日工表 = Daywork Schedule; 计日工签证 = certified dayworks records.
Under the FIDIC Red Book, Sub-Clause 1.1.26 defines "Daywork Schedule" as the document included in the Contract showing the amounts and manner of payment to the Contractor for labour, materials and equipment used for daywork. Sub-Clause 13.5 [Daywork] requires the Contractor to deliver each day accurate statements in duplicate, plus one electronic copy, showing the resources used in executing the previous day's work as recorded under Sub-Clause 6.10 [Contractor's Records]. Statements that are correct and agreed are signed by the Engineer and returned; where a statement is not correct and agreed, the Engineer proceeds under Sub-Clause 3.7 to agree or determine. If no Daywork Schedule is included, Sub-Clause 13.5 does not apply.
Both systems value daywork as actual resources consumed multiplied by pre-agreed rates. The institutional difference lies in the pricing infrastructure and the decision-making party: in China rates are derived from the quota system and entered by bidders, with quantities confirmed by site records; in FIDIC the rates are those the bidder inserts in the Daywork Schedule attached to the Bill of Quantities, and the measurement basis is the Contractor's daily resource statements countersigned by the Engineer. Usage warning: dayworks denotes a contractual valuation mechanism, not a work order or a timesheet, and it is distinct from paying labour by the day.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 计日工 | dayworks | Daywork (Sub-Clause 13.5); Daywork Schedule (Sub-Clause 1.1.26) | identical | 两侧均为零星工作按实际消耗资源计价的机制,差异在计价基础设施:中国计日工单价从定额取定并由投标人在计日工表中报价,结算按现场签证确认的数量计价;FIDIC 单价来自工程量清单所附 Daywork Schedule 的投标报价,以承包商每日报送、工程师签认的资源记录为计量凭据,有争议时按 3.7 商定或确定。 |
| 计日工签证 | certified dayworks records | Contractor's daily daywork statements (Sub-Clause 13.5, with records under Sub-Clause 6.10) | adjacent | 中国侧以现场签证确认实际数量,再乘以已报计日工单价计价;FIDIC 侧以承包商每日提交的报表为凭据,报表正确并达成一致才由工程师签署返还,不能一致时转入 3.7 商定或确定程序,程序性与签认主体不同。 |
| 综合单价 | all-in unit rate | amounts and manner of payment stated in the Daywork Schedule (Sub-Clause 1.1.26) | adjacent | 中国计日工单价通常为含人材机、管理费与利润的综合单价,由投标人按定额及自身水平填报;FIDIC 的 Daywork Schedule 载明劳务、材料与设备的支付金额与方式,其构成依合同附表约定,不套用中国的定额取费体系。 |
Updated 2026-09-13
- 01
GB/T 50500-2024 rules for pricing dayworks and deducting them in the final account: quantity measured as incurred x the contract dayworks all-in unit rate, deduction of the dayworks BOQ items from the total settlement price, and VAT adjusted on the difference
Dayworks are priced under GB/T 50500-2024 clause 8.6.2: measured in acco…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.6.2条、第8.6.5条GB/T 50500-2024 第7.5节(计日工计量)GB/T 50500-2024 第10.3.2条第6项2026-11-01 - 02
Four-axis distinction among variations, additional works, dayworks and claims under GB/T 50500-2024 (triggering events / procedure / time limits / pricing basis) and the fallback positioning of claims
GB/T 50500-2024 clause 8.1.1 lists contract price adjustment matters in…
GB/T 50500-2024 建设工程工程量清单计价标准 Ch. 2 术语 2.0.16、2.0.28、2.0.30GB/T 50500-2024 Ch. 7 合同工程计量 7.4.1、7.5.1、7.5.2、7.5.5、7.6.1GB/T 50500-2024 Ch. 8 合同价款调整 8.1.1、8.6.2、8.9.1、8.9.2、8.9.6、8.9.8、8.10.1、8.10.2、8.10.3、8.11.1、8.11.3、8.11.5、8.11.7、8.11.9、8.11.102026-11-01 - 03
Boundary distinctions among omitted BOQ items (BOQ errors), provisional prices, provisional sums, dayworks and site instruction records in contract price adjustment: required but not listed vs listed but unpriced vs confirmation evidence for unforeseen matters
Under GB/T 50500-2024: omission falls under 'BOQ errors' (clause 2.0.27…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.27、7.2.1、8.2、8.3.1、8.3.2、8.3.5、8.4.1、8.4.5、8.4.7、8.6.1、8.6.5、8.9、10.3.2、12.2.1条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.9、5.9.1、5.9.2条GB/T 50875-2013 · Standard glossary of project costs 第3.4.8条2026-10-25 - 04
Pricing channels for works outside the contract scope and unforeseen works: recognising and pricing additional works, when dayworks apply, and the rules for using provisional sums
Where the contractor, at the employer's request, completes additional wo…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.10.1条GB/T 50500-2024 第7.5.2条GB/T 50500-2024 第8.3.2条2026-09-26 - 05
Four essential elements of a valid site instruction / variation record: signature chain of personnel, time points, quantity substantiation and price basis
A valid site instruction / variation record = four elements complete: (1…
GB/T 50500-2024 第12.2.1条GB/T 50500-2024 第7.5.5条GB/T 50500-2024 第7.5.6条2026-09-25 - 06
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contr…
GB/T 50500-2024 建设工程工程量清单计价标准(第8.1.1/8.1.2条、第8.2~8.11节、第7.5节、App. A、App. G)FIDIC Red/Yellow Book 2017(第13.3、13.4、13.6、13.7、20.2.1 条〔对照〕)GB/T 50875-2013 工程造价术语标准2026-09-25 - 07
Determining labour cost in the all-in unit rate: the two-step "norm resource consumption × labour unit price" method and its standard basis
Labour cost in the all-in unit rate is determined in two steps as "norm…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9、8.6.3条GB/T 51095-2015 建设工程造价咨询规范 第5.3.9、7.4.2条TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.1节2026-09-25 - 08
GB/T 50500-2024: definitions of the three pricing methods (unit rate / lump sum / rate-based) and their applicability to each BOQ category
GB/T 50500-2024 provides: work-section BOQ items and day-work items shou…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.10~2.0.12、3.1.5、3.2.1、3.2.7条2026-09-25 - 09
GB/T 50500-2024 abolishes site instructions (xianchang qianzheng): out-of-contract work now goes through variations / new works / dayworks, and statutory time limits become contractual
GB/T 50500-2024 deletes the 2013 Section 9.14 "site instructions" with i…
GB/T 50500-2024 建设工程工程量清单计价标准(第2.0.16/2.0.28/2.0.30条、第7.5节、第8.1.1条、第8.6节、第8.9节、第8.10节)GB/T 50875-2013 工程造价术语标准(第3.4.8条 现场签证)GB 50500-2013 建设工程工程量清单计价规范(第9.14节,已废止,对照)2026-09-25 - 10
Recording quantities for site instructions and certified records: a three-stage closed-loop procedure, recording elements, and daywork daily reporting requirements
Quantity recording for site instructions and certified records follows t…
GB/T 50500-2024 建设工程工程量清单计价标准T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准DB37/T 5028-2022 建设工程监理工作规程2026-09-25 - 11
Dayworks must be covered by a certification report: the full workflow of dayworks certification under GB/T 50500-2024 clause 7.5 (daily submission -> summary certification report -> deemed approval upon default -> signed confirmation and pricing) and the procedural differences from the 2013 edition
Yes, it must be done - for dayworks, the certified dayworks report is th…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.16条、第7.5.1~7.5.6条、第8.6.2条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.7.3、9.7.4条(已被替代,供老合同对照)2026-09-25 - 12
Full workflow of daywork (casual labor): sign-off, measurement, pricing, and cost control
Daywork (casual labor) management hinges on "instruction first, then wor…
GB/T 50500-2024 建设工程工程量清单计价标准DB14/T 1319-2021 公路工程标准工程量清单及计量规范T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准2026-09-25 - 13
Site instructions and certified records overview: applicable matters and prohibited items, the five-node handling procedure, graded signing authority, the 2024 standard basis and settlement application
Certification runs a five-node closed loop: assess reasonableness before…
GB/T 50500-2024 建设工程工程量清单计价标准(第7.5、8.6、8.9、8.10、12.2.1条)GB/T 51262-2017 建设工程造价鉴定规范(第5.9节)T/CAEC 006-2024 建筑工程监理文件资料管理标准(第7.2.8、7.2.9条)2026-09-25 - 14
Identifying fabricated and duplicate labour attendance records: a four-layer method — field checks → cross-verification → duplicate screening → statistical screening
Core principle: "a single record is untrustworthy; only cross-verificati…
GB/T 50500-2024 第7.5.5条DB11/T 382-2017 第6.4.3条DB11/T 1448-2017 第5.3.2条2026-09-25