Dayworks must be covered by a certification report: the full workflow of dayworks certification under GB/T 50500-2024 clause 7.5 (daily submission -> summary certification report -> deemed approval upon default -> signed confirmation and pricing) and the procedural differences from the 2013 edition
Yes, it must be done - for dayworks, the certified dayworks report is the sole vehicle of measurement and pricing: GB/T 50500-2024 clause 7.5 requires that the intention to use dayworks be proposed and approved in advance (failure to propose is deemed waiver; failure of the employer to reply is deemed consent, 7.5.1); during execution, the five categories of returns and vouchers be submitted for every day worked (7.5.3); after continuing work ends, a dayworks certification report containing the summary of the daily records be submitted within the agreed time (7.5.4); the employer verify and check within the time limits, failing which deemed approval (7.5.5); after both parties sign and confirm the results, pricing follows the all-in dayworks rates in the contract BOQ (7.5.6, 8.6.2); the certified quantities exclude the contractor's own on-site management personnel and the construction plant already on site. The 2013 edition once required submission of the on-site certification report in triplicate within 24 hours after the end of the work and confirmation by the employer within 2 days (clauses 9.7.3, 9.7.4).
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.16条、第7.5.1~7.5.6条、第8.6.2条
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.7.3、9.7.4条(已被替代,供老合同对照)
Topic Positioning
Answers "must dayworks be certified by site records, and how": under clause 7.5 of GB/T 50500-2024 "Pricing Standard for Bill of Quantities of Construction Works", the full workflow of the dayworks certification report (advance proposal and approval -> daily submission -> summary certification report -> employer verification and checking -> joint signed confirmation -> pricing), with the differences from the old GB 50500-2013 procedure - applicable to the certification of dayworks during construction, settlement review and contract-compliance self-checks.
Core Conclusions
Yes - under the current standard, the only recognised vehicle for measuring and pricing dayworks is the "dayworks certification report": the quantities are confirmed by certification, and the rates follow the all-in dayworks rates in the contract BOQ. The basis and procedure:
Definition (clause 2.0.16): dayworks - "a method by which the contractor carries out sundry items or work instructed by the employer which are not suitably measured and priced under the measurement and pricing rules agreed in the contract, but are instead priced at the agreed rates on the basis of the actual consumption of labour workdays, material quantities and plant machine-shifts confirmed by the employer"; that is, "sundry works or work carried out by the contractor at the employer's instruction which are not suitably measured and priced under the standards for measurement of quantities and the pricing rules of this standard, but are measured and priced using the dayworks rates agreed in the contract".
Advance proposal and approval (clause 7.5.1): where the contractor considers that an item or work is not suitably measured under clauses 7.2-7.4 of this standard and should instead be measured under the dayworks provisions of clause 8.6, it shall propose so to the employer within the agreed time, and the employer shall reply within the agreed time. If the contractor fails to propose in time, it is deemed to have waived the need to measure by dayworks; if the employer fails to reply in time, it is deemed to have consented to measurement by dayworks.
Applicable situations (clause 7.5.2): unless otherwise agreed in the contract, the following items and sundry work may be measured and priced as dayworks: (1) additional or substitute works that cannot be measured from the construction drawings, the variations or the agreed measurement rules; (2) short-duration, sundry, limited-scope, small-quantity items added at the employer's request; (3) abnormal operations caused by extreme changes in working conditions; (4) repair of damage to other works caused by carrying out emergency works; (5) opening up concealed works at the employer's request where the works concerned prove by testing to conform to the contract; (6) the cost of restoring surrounding works affected after other contractors finish their work; (7) the cost of materials that must be replaced because the employer suspends (stops) the works and the works are thereby delayed; (8) cleaning and clearing off outside the contract scope specially required by the employer; (9) test runs outside the contract scope required by the employer; (10) repair and restoration of minor works damaged for reasons not attributable to the contractor (restoration after large-scale damage shall be measured and priced as a variation).
Daily submission (clause 7.5.3): for any work priced as dayworks, on every day of its execution the contractor shall submit to the employer for verification the following returns and vouchers covering that day's dayworks content: (1) the name, content and quantity of the work; (2) the names, trades, grades and hours consumed of all personnel deployed on the work; (3) the names, categories, specifications, brands and quantities of the materials deployed; (4) the models, quantities and machine-shifts consumed of the construction plant deployed; (5) other information and vouchers required by the employer.
Summary certification (clause 7.5.4): where dayworks work is not completed within a single day and continues, the contractor shall, after the work ends, submit the dayworks certification report to the employer within the agreed time, containing a summary of each day's dayworks records.
Employer verification, checking and deemed approval (clause 7.5.5): the employer shall notify the contractor in writing of the verification results within the agreed time after receiving the returns, and shall check the dayworks certification report within the agreed time after receiving it. If the employer fails to provide the verification or checking results within the agreed time, the contents of the contractor's returns or dayworks certification report shall be deemed approved by the employer.
Signed confirmation and pricing (clauses 7.5.6, 8.6.2): the employer and the contractor shall sign the jointly confirmed dayworks results, which form the basis for computing the dayworks price. Work priced as dayworks shall be measured under the provisions of clause 7.5 and priced at the all-in rates of the dayworks items in the contract BOQ - i.e. the quantities computed under the relevant provisions multiplied by the corresponding dayworks contract rates in the contract BOQ determine the dayworks price.
Scope red lines (repeated in 7.5.3-7.5.6): the numbers of personnel, materials and construction plant in the dayworks certification report shall be the measured quantities of the work concerned and exclude the contractor's own on-site management personnel and the construction plant already on site, which are not measurable.
2013 edition comparison (for old contracts): GB 50500-2013 (superseded by GB/T 50500-2024) clause 9.7.3 - where any dayworks item continued, the contractor shall, within 24 hours after the work ended, submit to the employer an on-site certification report containing the summary of the dayworks records, in triplicate. The employer shall confirm within 2 days of receiving the report and return one copy to the contractor as the basis for pricing and payment of the dayworks; where the employer neither confirms nor raises comments within the time limit, the on-site certification report submitted by the contractor shall be deemed approved. Clause 9.7.4 - after the dayworks item ends, the contractor shall verify the quantities of that category from the confirmed on-site certification report and compute the payable price from the verified quantities and the dayworks rates in the priced BOQ; where the priced BOQ contains no such dayworks rate, the parties agree the dayworks rate under clause 9.3 of that code.
Applicable Boundaries
- Applies to the measurement and pricing of dayworks in construction works procured and executed on a bill-of-quantities basis.
- GB/T 50500-2024 is a recommended standard; the contract prevails: the 2024 edition changes the submission and confirmation periods from the 2013 edition's "24 hours / 2 days" to "the time agreed in the contract" - check the contract for the deadlines; where the contract states no periods, the "deemed approval upon default" mechanism cannot even trigger - the period clause is a key risk point at the contract drafting stage.
- The 24 hours, triplicate and 2-day confirmation all belong to the 2013 edition (now superseded) and must not be applied directly to 2024-edition contracts; old contracts expressly adopting the 2013 rules follow the contract.
- The non-measurable scope (the contractor's own on-site management personnel and the construction plant pre-existing on site are not counted in the certified quantities) is a high-frequency disallowance point at settlement.
- Restoration after large-scale damage shall be measured and priced as a variation, not through the dayworks channel.
Further Reading
- GB/T 50500-2024 "Pricing Standard for Bill of Quantities of Construction Works" clause 2.0.16 (dayworks term), clauses 7.5.1-7.5.6 (measurement of the contract works - dayworks certification and measurement), clause 8.6.2 (contract price adjustment - dayworks pricing).
- GB 50500-2013 "Code for Valuation with Bill of Quantities of Construction Works" clauses 9.7.3, 9.7.4 (superseded; for old-contract comparison).
Keywords
- dayworks
- 计日工签证报告
- 计日工计量
- 计日工计价
- GB/T 50500-2024
- 建设工程工程量清单计价标准
- 现场签证报告
- dayworks