Identifying fabricated and duplicate labour attendance records: a four-layer method — field checks → cross-verification → duplicate screening → statistical screening
Core principle: "a single record is untrustworthy; only cross-verification is valid": first run field-level checks to scan fake records, then cross-verify along four lines — quantities, construction/supervision logs, real-name attendance and payroll, and safety-education/briefing signature sheets; use a person × date pivot to find duplicates across crews/periods/dayworks/contracts on the same day; finally use statistical indicators to circumscribe anomalies. Certified dayworks records count only actual work content, excluding the contractor's on-site management personnel and machinery already on site.
Applicable Codes
- GB/T 50500-2024 第7.5.5条
- DB11/T 382-2017 第6.4.3条
- DB11/T 1448-2017 第5.3.2条
- DB32/T 4321-2022 第7.2条
- DB64/T 1684-2020 第4.2.4条
- ZJKX-ZHJZ001-2021 第5.3.4条
- TB 10402-2019 第10.1.1条
- GB/T 51262-2017 第5.9.1条
Topic Positioning
A general investigation method for identifying fabricated and duplicate labour attendance records on site, applicable to labour-cost authenticity verification in process cost review, final account review, and construction cost expert assessment (judicial appraisal).
Core Conclusions
Core principle: a single record is untrustworthy; cross-verification is required. Four investigation layers: ① Field-level checks: reported time conflicting with weather/holidays/work stoppage-resumption, attendance before entry or after exit, over 24 hours in a single day; missing real-name information; special operations reported without certification (supervisors spot-check certified work, DB11/T 382-2017, Clause 6.4.3); missing signatures or retrospective/proxy signing; reported trades inconsistent with the day's work content. ② Cross-footing verification: total worker-days versus completed quantities (against quota norms (prescribed resource consumption standards) labour content or enterprise-measured productivity); comparison with construction/supervision logs — construction logs must not be back-filled (DB11/T 1448-2017, Clause 5.3.2); attendance without the crew's work in that day's log is typical fabrication; comparison with real-name attendance and payroll records (attendance combined with site access management, DB32/T 4321-2022, Clause 7.2; DB64/T 1684-2020, Clause 4.2.4; ZJKX-ZHJZ001-2021, Clause 5.3.4); comparison with safety-education/technical-briefing signature sheets — notably fewer signatures than reported workers is an anomaly. ③ Duplicate reporting: a person × date pivot to find same-day duplicates across crews/BOQ items; comparison with the monthly measurement certification and sign-off ledger for cross-period duplicates; checking dayworks against labour already included in divisional items — certified dayworks records count only actual work content, excluding the contractor's on-site management personnel and machinery already on site (GB/T 50500-2024, Clause 7.5.5); management personnel reporting dayworks is a violation; checking cross-contract duplicates and inflated work-hour conversions. ④ Statistical screening: project-wide per-capita productivity, horizontal comparison of same-trade unit prices, sudden jumps in single-day worker-day totals, and abnormal dayworks proportions.
Applicable Boundaries
Applies to labour-cost authenticity checks during construction and at settlement; the method is general; productivity benchmarking must follow this project's contract, quota norms, or enterprise-measured levels. Appraisal pricing rules for certified-fee disputes are in GB/T 51262-2017, Clause 5.9.1. This card does not replace quantity take-off (measurement) or BOQ-based pricing rules themselves.
Further Reading
GB/T 50500-2024 "China national pricing standard for BOQ" Clause 7.5.5 (certified dayworks records basis); DB11/T 382-2017 "Rules for construction supervision of building works" Clause 6.4.3 (safety training and certification checks); DB11/T 1448-2017 "Rules for construction document management of urban rail transit works" Clause 5.3.2 (daily construction log entries, no back-filling); DB32/T 4321-2022 "Technical specification for construction safety management information systems of highway works" Clause 7.2 (real-name attendance); DB64/T 1684-2020 "Technical standard for smart construction sites" Clause 4.2.4 (attendance linked to payroll); ZJKX-ZHJZ001-2021 "CSCEC smart construction site standard" Clause 5.3.4 (attendance combined with site access management); TB 10402-2019 "Code for supervision of railway construction works" Clause 10.1.1 (supervisor log contents).