Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Four essential elements of a valid site instruction / variation record: signature chain of personnel, time points, quantity substantiation and price basis

A valid site instruction / variation record = four elements complete: (1) Personnel: signed by the contractor's handling officer and project manager with seal; reviewed by the discipline supervising engineer; signed by the Engineer (chief supervising engineer), who computes the fee; and submitted to the employer for approval (duration-related site instructions / variation records additionally require the seal of the follow-up audit unit); (2) Time: date of occurrence/completion, submission within the agreed time limit, and the employer's failure to verify within the stipulated period being deemed acceptance; (3) Quantity: location, dimensions and quantities plus calculation formulas, sketches/photos and original vouchers signed by all parties, measured as actually incurred; (4) Price: calculation process and result, employer's approval of material prices, and the signed dayworks confirmation result. Missing calculation formulas or photos, or late submission, are the gaps most frequently attacked in settlement disputes.

Applicable Codes

  • GB/T 50500-2024 第12.2.1条
  • GB/T 50500-2024 第7.5.5条
  • GB/T 50500-2024 第7.5.6条
  • T/SDJZXH 004.1-2022 第10.6.1、10.6.3条
  • DB37/T 5164-2020 第7.5.5条
  • GB/T 50875-2013 第3.4.8条

Topic Positioning

Answers 'what a valid site instruction / variation record should contain' - the complete checklist and normative basis for the four elements of personnel, time, quantity and price, for use in preparing and reviewing site instructions / variation records and in self-inspection of settlement disputes.

Core Conclusions

A valid site instruction / variation record = four elements complete:

  1. Personnel: signed by the contractor's handling officer and project manager with the project department seal; the discipline supervising engineer reviews the site instruction / variation record description, sketches and quantities; the Engineer (chief supervising engineer) signs the opinion and computes the fee; finally it is submitted to the employer for approval. Duration-related site instructions / variation records additionally require signature and seal of the responsible persons of the employer, contractor, supervisor and follow-up audit unit. Baseline of validity: a written document signed by the on-site management personnel of both parties within their contractually agreed duties is a valid pricing voucher for the works (GB/T 50500-2024, Clause 12.2.1); a missing employer signature is a procedural defect curable by retrospective certification, but where the contract makes it a condition of validity and no remedial evidence exists, its validity is restricted.
  2. Time: distinguish the 'date the fact occurred/was completed' from the 'date of submission' - the contractor must submit to the supervisor within the time limit agreed in the contract; beyond it the supervisor may refuse the site instruction / variation record; the employer's verification has an agreed time limit, and if the employer fails to notify in writing within it, the submitted content is deemed accepted (Clause 7.5.5; the same rule applies to certified dayworks records).
  3. Quantity: state clearly the location, dimensions, quantities and materials; quantities must be supported by logically clear calculation formulas, together with the site instruction / variation record basis, sketch descriptions and site photos; at the time of occurrence the supervisor measures on site jointly with the employer and contractor to form original vouchers signed by all parties, confirmed as actually incurred. The dayworks scope counts only construction labour, materials and plant actually deployed, excluding the contractor's own on-site management staff and site plant already present (Clause 7.5.6).
  4. Price: attach the calculation process and result, with survey data if necessary; material prices are submitted to the employer for verification and approval before procurement (employer's approval of material prices), and prices confirmed by both parties prevail over published price information (government guidance prices) and market inquiries; dayworks prices are based on the dayworks confirmation result signed by both parties (Clause 7.5.6).

Applicable Boundaries

Applies to preparation, review and settlement disputes of site instructions / variation records between employer and contractor. Where the contract has clearer provisions on site instruction / variation record procedure, submission time limits or validity requirements, the contract prevails. Not applicable to settlement of variations without a site instruction / variation record (see the card on the five-tier expert determination rules); for in-depth remedies of one-sided signature defects see the card on validity of signatures on site instructions / variation records.

Further Reading

See GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clause 12.2.1 (valid pricing vouchers), Clause 7.5.5 (site instruction / variation record time limits and deemed acceptance upon the employer's failure to verify within the prescribed period), Clause 7.5.6 (dayworks site instruction / variation record scope); T/SDJZXH 004.1-2022, Clauses 10.6.1 and 10.6.3 (confirmation as actually incurred; the Engineer computes the fee and reports to the employer for approval); T/SDJZXH 002-2022 and DB37/T 5028-2022 (signature requirements for contractor and supervisor on site instructions / variation records); DB37/T 5164-2020, Clause 7.5.5 (four-party signature for duration-related site instructions / variation records); GB/T 50875-2013, Clause 3.4.8 (definition of site instruction / variation record).

Keywords

Cited By