Determining the commencement date in disputes: the date stated in the commencement notice (commencement order) versus the date of actual entry onto site with the employer's consent, and how that determination cascades into the start of the construction period, extensions of time, delay damages, and suspension and idle-resource losses
In principle the commencement date stated in the commencement notice (commencement order) governs; if the start conditions were not yet ready when the notice was issued, the time at which the start conditions became ready is the commencement date; if the start time was postponed for reasons attributable to the contractor, the time stated in the commencement notice still governs; if the contractor has actually entered the site and commenced the works with the employer's consent, the time of actual entry and commencement governs; if no commencement notice was issued and no evidence proves the actual commencement date, the date is determined by comprehensively weighing the times stated in the commencement report, the contract, the construction permit, the completion acceptance report or the completion acceptance filing record, together with the facts of whether the start conditions were ready (Fa Shi [2020] No. 25, Article 8). In short: the formal document (the order) prevails, subject to two factual corrections - start conditions not ready, and actual entry with consent.
Applicable Codes
- 法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第八条、第九条、第十条
- 法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第二十三条
- 中华人民共和国民法典 第八百零三条、第八百零四条、第五百八十五条
- 法释〔2023〕13号 最高人民法院关于适用《中华人民共和国民法典》合同编通则若干问题的解释 第六十四条、第六十五条
- GB/T 50319-2013 建设工程监理规范 第5.1.8条
- GB/T 51262-2017 建设工程造价鉴定规范 第5.7.1条
- GF-2017-0201 建设工程施工合同(示范文本)第7.3.2、7.5.1、7.5.2、7.8.1、7.8.5项
- 中华人民共和国建筑法(2019修正)第九条
- 中华人民共和国民事诉讼法(2023修正)第六十七条
- 中华人民共和国仲裁法(2025修订)第五十五条至第五十八条
Scope
The commencement date is the starting point of the construction period and the common reference for delay damages for late completion, extensions of time, suspension and idle-resource claims, and construction cost expert assessment. This card resolves a frequent dispute: where the date stated in the commencement order (commencement notice) differs from the contractor's actual entry onto site, which day counts in law as the commencement date, and how that determination cascades into extension requirements, delay damages and suspension losses.
Core conclusions
1. The statutory order of determination (Fa Shi [2020] No. 25, Article 8, full text)
'Where the parties dispute the commencement date of a construction project, the people's court shall determine it according to the following situations: (1) The commencement date is the date stated in the commencement notice issued by the employer or the supervisor; where the start conditions were not yet ready after the commencement notice was issued, the time at which the start conditions became ready is the commencement date; where the start time was postponed for reasons attributable to the contractor, the time stated in the commencement notice is the commencement date. (2) Where the contractor has already entered the site and commenced the works in practice with the employer's consent, the time of actual entry and commencement is the commencement date. (3) Where the employer or the supervisor issued no commencement notice and there is no relevant evidence proving the actual commencement date, the people's court shall comprehensively consider the times stated in the commencement report, the contract, the construction permit, the completion acceptance report or the completion acceptance filing record, and determine the commencement date in combination with the facts of whether the start conditions were ready.'
Reduced to four dispute patterns:
| Dispute pattern | Determination |
|---|---|
| Order first, actual entry later, and the start conditions not yet ready on the order date | The date the start conditions became ready is the commencement date |
| Actual entry earlier than the order, with the employer's consent | The date of actual entry and commencement is the commencement date |
| Actual entry earlier than the order, but without the employer's consent (unauthorised entry) | The date stated in the order remains the commencement date |
| Actual entry later than the order date, for reasons attributable to the contractor | The order date remains the commencement date (lateness does not defer it) |
2. Preconditions for issuing the commencement order (GB/T 50319-2013, 5.1.8)
The chief supervising engineer shall organise the professional supervising engineers to review the commencement application form and supporting documents submitted by the contractor; when the following conditions are all met, the chief supervising engineer signs the review opinion and, after approval by the construction unit, issues the commencement order: 1 design disclosure and drawing review completed; 2 the project execution plan already signed by the chief supervising engineer; 3 the contractor's on-site quality and work-safety management systems established, management and construction personnel in place, construction plant ready for use, and the main construction materials secured; 4 site access roads, water, power and communications meeting the start requirements. The clause also provides: 'The chief supervising engineer shall issue the commencement order to the contractor 7 days before the commencement date. The construction period runs from the commencement date stated in the commencement order issued by the chief supervising engineer.'
These four conditions also form the technical reference for judging whether 'the start conditions were ready' - if the order was issued but the conditions were not actually in place, the contractor may claim the date the conditions became ready as the commencement date.
3. The corresponding contractual mechanism (GF-2017-0201, 7.3.2 and 7.5.1)
'The supervisor shall issue the commencement notice to the contractor 7 days before the planned commencement date; the construction period runs from the commencement date stated in the commencement notice.' 'Unless the particular conditions of contract provide otherwise, where for reasons attributable to the employer the supervisor fails to issue the commencement notice within 90 days from the planned commencement date, the contractor is entitled to demand a price adjustment or to terminate the contract. The employer shall bear the costs thereby increased and (or) the period of delay thereby caused, and shall pay the contractor a reasonable profit.'
Clause 7.5.1 lists the situations in which the employer bears the period and costs and pays a reasonable profit, those directly related to commencement being: failure to provide drawings as agreed in the contract, or drawings not conforming to the agreement; failure to provide the site, construction conditions, basic data, permits or approvals as agreed; errors or omissions in the survey benchmarks, base lines and level points provided and the written data; failure to agree to issue the commencement notice within 7 days from the planned commencement date; failure to pay the advance payment, progress payments or final account payments on the agreed dates; failure of the supervisor to issue instructions, approvals and other documents as agreed. The same clause also provides: 'where the works fail to commence on the planned commencement date for reasons attributable to the employer, the employer shall extend the completion date to the actual commencement date, ensuring that the actual construction period is no shorter than the total calendar days agreed in the contract.'
4. The two commencement regimes compared axis by axis
| Axis | Notice/order regime (formal start) | Actual entry regime (factual start) |
|---|---|---|
| Date determination | The date stated in the notice of the employer or the supervisor is the commencement date; if the conditions were not ready after issue, the readiness date; if postponed for contractor reasons, still the stated date | The day of 'actual entry and commencement with the employer's consent'; the threshold is consent, not presence - unilateral entry, erecting temporary facilities or sitting on site generally do not qualify; physical traces of construction (inspection lots, concealed-work acceptance, pouring records etc.) are needed to support it |
| Extension requirements | Employer failed to provide drawings, site, permits, basic data etc. - extension; failed to agree to the notice within 7 days of the planned start - extension plus costs plus profit; for its own reasons the contractor must apply within the agreed period and obtain consent, else no extension; force majeure - extension | The reference point moves forward to the actual entry date, and extension events are reported case by case within the contractual periods from that date; phased site handover and sectional starts are determined section by section by 'readiness of the start conditions', not covered by one order; standstill after entry goes through the 'suspension of the works / claim' procedure, not the 'start conditions not ready' procedure |
| Judicial relief for extensions (Fa Shi [2020] No. 25, Article 10) | 'Where the parties agree that an extension ... must be confirmed by the employer or the supervisor by sign-off, and the contractor, though lacking confirmation, can prove it applied within the period agreed in the contract and the grounds meet the contract, the people's court shall support the extension claim. Where the parties agree that failure to apply within the agreed period means no extension, the agreement governs, except where the employer agrees after the period or the contractor raises a reasonable defence.' | The same - under factual start, the threshold and burden of proof for extension grounds are unchanged, but the earlier start date moves the whole time axis of the 'agreed periods' forward, increasing the risk of late applications |
| Delay damages rules | The period runs from the order date (or its corrected date); where the employer failed to issue the notice on time, or issued it while the conditions were unready, causing delay, this is the employer's breach and does not constitute contractor delay | The earlier start date means the contractor carries more calendar days to the same completion date, raising its exposure to delay damages; an employer claiming 'entry equals commencement' must prove that the entry was consented to and was construction within the contract period. Excessive liquidated damages may be reduced on request - where the agreed damages exceed the loss caused by 30 percent, the people's court may generally find them excessive (Fa Shi [2023] No. 13, Article 65); the defaulting party claiming excess bears the burden of proof (Article 64 of the same interpretation) |
| Suspension loss calculation | Civil Code Article 803: 'Where the employer fails to provide the raw materials, equipment, site, funds or technical data at the agreed time and to the agreed requirements, the contractor may postpone the construction date and claim compensation for losses from suspension, idle resources and the like.' Article 804: 'Where the works are stopped or slowed down midway for reasons attributable to the employer, the employer shall take measures to remedy or reduce the loss, and compensate the contractor for the losses so caused and the actual costs thereof, including suspension, idle resources, re-handling, relocation of machinery and equipment, and accumulation of materials and components.' | Standstill after entry is handled as suspension of the works: GF-2017-0201, 7.8.5 requires that 'before the works resume, the supervisor, together with the employer and the contractor, determines the losses caused by the suspension and the conditions for resumption of the works'; where the works are suspended for the employer's reasons, the employer bears the costs thereby increased and (or) the period of delay thereby caused, and pays the contractor a reasonable profit (7.8.1) |
| Evidence points | The original commencement notice / order and proof of service, the commencement application form and the chief supervising engineer's review opinion, the construction unit's approval documents, supervision logs, drawing delivery and site handover records | The entry notice and written documents or correspondence showing the employer's or supervisor's consent to entry, construction logs, inspection-lot and concealed-work acceptance records, concrete pouring and material arrival records, photographic records. Allocation of the burden of proof: 'a party has the responsibility to provide evidence for its own claims' (Civil Procedure Law (2023 revision), Article 67) |
5. Treatment at the construction cost expert assessment stage (GB/T 51262-2017, 5.7.1)
'Where the parties dispute the commencement time of the assessed project, the assessor shall refer the decision to the commissioning party; if an opinion is required, it is given as follows for the commissioning party's judgment: 1 Where the contract states a commencement time but the employer has approved the contractor's commencement report or issued a commencement notice, the time of the approved report or issued notice shall be adopted; 2 where the contract does not state a commencement time, the employer-approved commencement time shall be adopted; absent that, the commencement time may be determined from construction logs, acceptance records and other relevant evidence; 3 where the contract states a time and the contractor cannot start on time for its own reasons: if the employer accepts the contractor's postponement application, the time is extended accordingly; if the employer refuses or no application was made within the agreed time, no extension; 4 where commencement at the contractual time is impossible for reasons not attributable to the contractor, the time is extended accordingly; 5 where commencement on time is impossible due to force majeure, the time is extended accordingly; 6 where the evidence shows nothing of the employer or contractor advancing or postponing the commencement, the contractual commencement time is adopted.'
The assessment approach thus matches the judicial one: contractual commencement time < the employer-approved commencement report / commencement notice < objective evidence (construction logs, acceptance records) as fallback.
6. Neighbouring date and precondition rules
- Completion date (Fa Shi [2020] No. 25, Article 9): '(1) where the construction project has passed completion acceptance, the date of passing completion acceptance is the completion date; (2) where the contractor has submitted the completion acceptance report and the employer delays the acceptance, the date on which the contractor submitted the acceptance report is the completion date; (3) where the construction project has not undergone completion acceptance and the employer uses the works prematurely without taking-over, the date of transfer of possession of the works is the completion date.' The commencement determination and the completion determination together form the total calendar days of the construction period, and both must use the same basis (calendar days, not working days).
- Construction permit and the start deadline (Construction Law (2019 revision), Article 9): 'The construction unit shall commence within three months from the date of obtaining the construction permit. Where commencement on schedule is impossible for some reason, it shall apply to the issuing authority for an extension; extensions are limited to two, each of no more than three months. Where it neither commences nor applies for an extension, or exceeds the extension time limit, the construction permit lapses automatically.' The time stated in the construction permit may serve as auxiliary evidence when no commencement notice exists, but the permit date itself does not equal the commencement date.
7. The time boundary between the new and old rules
Fa Shi [2026] No. 12 (SPC Interpretation (II) on the Application of Law in Construction Contract Dispute Cases), Article 23: 'This Interpretation takes effect from 30 June 2026. For first-instance construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect, this Interpretation applies. Where judicial interpretations previously issued by the Supreme People's Court are inconsistent with this Interpretation, this Interpretation prevails.' A dispute over the commencement date therefore requires the 'case acceptance point in time' to be fixed first: first-instance cases newly accepted after 30 June 2026 apply Interpretation (II); cases accepted earlier still apply the original rules such as Fa Shi [2020] No. 25; where the two are inconsistent, Interpretation (II) prevails.
Boundaries
- Applies to commencement date and construction period start disputes in construction contract disputes (including settlement disputes, construction cost expert assessment and arbitration); not applicable to sale, work-and-material or other non-construction contracts.
- 'Actual entry' is established only with the consent of the employer (or its authorised supervisor); unconsented unilateral entry, sitting on site, erecting temporary facilities or mere start preparations generally do not constitute factual commencement and cannot move the period start point forward.
- GB/T 50319-2013, 5.1.8 is a supervision-procedure code (a recommended national standard); its four conditions serve only as the technical reference for judging whether 'the start conditions were ready', and can neither replace the judicial interpretation's factual determination nor, by themselves, defeat the validity of a commencement order.
- Judicial relief for extensions rests on the twin requirements of 'an application made within the contractual period + extension grounds meeting the contract'; where the contract provides that failure to apply within the period means no extension, the agreement governs, subject only to the employer's later consent or the contractor's reasonable defence.
- The 30 percent damages marker is a discretionary reference line for 'generally finding damages excessive', not an absolute cap and not an automatic reduction; the party seeking reduction bears the burden of proof, and a bad-faith defaulter's request for reduction is generally refused.
- Fa Shi [2026] No. 12 applies only to 'first-instance cases newly accepted after it takes effect' and does not reach back to cases accepted before; check the case acceptance point before citing.
- In construction cost expert assessment, the expert assessor has no final decision power over disputed commencement times and may only offer opinions for the commissioning party's judgment.
Further reading
- Fa Shi [2020] No. 25 (SPC Interpretation I on construction contract disputes): Art 8 commencement date, Art 9 completion date, Art 10 extension applications and sign-off.
- Fa Shi [2026] No. 12 (Interpretation II), Art 23 (effect date and new-old transition).
- GB/T 50319-2013 Code for Construction Project Supervision, 5.1.8 (commencement application review, four order conditions, issue 7 days ahead, period from the order date).
- GB/T 51262-2017 Code for Construction Cost Expert Assessment, 5.7.1 (six rules for disputed commencement times).
- GF-2017-0201 Model Construction Contract: 7.3.2 (notice; 90 days without notice), 7.5.1 (employer-caused delay), 7.5.2 (contractor-caused delay and delay damages), 7.8.1 / 7.8.5 (suspension; loss determination before resumption).
- Civil Code: Art 803, Art 804 (extension; suspension and idle-resource compensation on employer breach), Art 585 (agreed damages and judicial adjustment).
- Fa Shi [2023] No. 13 (Contract Part interpretation): Art 64 (burden of proof on damages adjustment), Art 65 (damages exceeding loss by 30 percent generally excessive).
- Construction Law (2019 revision), Art 9 (permit; start within three months; extensions limited to two).
- Civil Procedure Law (2023 revision), Art 67 (burden of proof; court collection and verification of evidence); Arbitration Law (2025 revision), Art 55-58 (tribunal evidence collection, expert assessment of special issues, hearing cross-examination, evidence preservation).
Keywords
- 开工日期认定
- 开工令
- 开工通知
- 实际进场施工
- 法释〔2020〕25号第八条
- 工期起算
- 工期顺延
- 停窝工损失