Organising evidence for suspension cost claims: itemised proof lists for labour, plant and overheads, and the three conditions of an established claim (T/YJXB 0001-2023 Chapter 6; GB/T 50326-2017 Article 7.5.8)
A suspension cost claim must satisfy three conditions at once: claiming per the contract (failing or unclear terms, per laws and regulations), collecting claim materials comprehensively, and giving notice of claim intention and the report within the agreed or statutory periods - the three indispensable conditions (GB/T 50326-2017 Article 7.5.8). Proof is itemised by cost: production workers' wages need minutes, construction logs, labour / service contracts, attendance sheets, payroll, payment records and site clock-ins, plus proof of the necessity and objectivity of the wages having to be paid; plant standby needs entry / exit acceptance sheets, hire contracts, plant lists, hire settlements and reconciliation statements; suspension overheads need documents proving total overheads and contract duration - tender documents, budgets, drawings, contract - and one must provide sufficient evidence of the overhead amount for each day (T/YJXB 0001-2023 Articles 6.0.5, 6.0.3, 6.0.8). Where site certifications exist they govern (Article 3.0.3).
Applicable Codes
- T/YJXB 0001-2023《建设工程停工承包人费用计算标准》第2.0.6、3.0.3、3.0.9、4.0.8、5.0.3、5.0.8、6.0.3、6.0.5、6.0.8条
- GB/T 50326-2017 · Code for Construction Project Management 第7.5.8条
- GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.8节、第5.8.3条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.3条、第8.11.9条
- 《中华人民共和国民法典》第五百八十四条、第五百九十一条
- GF-2020-0216《建设项目工程总承包合同(示范文本)》通用条款第19条
- 陕西省2025版建设工程费用规则第8.3条(周转性材料停窝工费)
- 山东省施工机械台班费用编制规则第6.0.1条(施工机械停滞费构成)
- 湖南省2025版消耗量标准附录(机械停滞台班按台班折旧费计算)
Scope of the question
Organising materials for suspension and idle-resource cost claims: the three conditions of an established claim, the proof lists per cost item (labour, plant, overheads), and the two constraints - certification first and the duty to mitigate - on the evidence scope.
Core conclusions
- Conditions of an established claim (GB/T 50326-2017 Code for Construction Project Management, Article 7.5.8): the project management body shall administer contract claims as required; claims shall: 1 be made per the contract - absent or unclear terms, per laws and regulations; 2 collect and organise claim materials comprehensively and completely; 3 give the notice of intention and the claim report per the agreed or statutory procedure and periods; 4 the report stating grounds, amounts and time. The commentary: basis, evidence and procedure are intrinsically linked - three indispensable conditions of an established claim; evidence includes party statements, documents, physical evidence, audio-visual and electronic data, witness statements, expert opinions and inspection records, and only evidence verified on inquiry grounds findings; giving the claim documents within the contractual or statutory period, with review or sign-off completed, is the key assurance of confirmation.
- Production workers' wages (T/YJXB 0001-2023 Article 6.0.5): minutes, construction logs, labour and service contracts, written labour agreements, attendance sheets, payroll, payment records, site clock-ins, the execution plan, electronic data and the like; where wages must be paid during suspension, evidence must prove the necessity and objectivity of payment (lump-sum or full-package labour usually shows no wage outlay - burden on the claimant).
- Plant standby (Article 6.0.3): entry / exit acceptance sheets, hire contracts, plant lists, the execution plan, notarised documents, hire settlements, reconciliations, electronic data; hired plant must prove hire losses continued during suspension; owned plant must prove its configuration on site.
- Suspension overheads (Article 6.0.8): documents proving total overheads and contract duration - tender documents, budgets, drawings, the contract, the execution plan; computing suspension overheads requires sufficient evidence of the daily overhead amount, plus materials showing the actual incidence of overhead spend.
- Constraint 1 - certification first (Article 3.0.3): where the suspension costs carry site certifications, the certifications govern; absent them, the standard applies. Basis: the GB 50500-2013 position that the parties may fix by certification the quantities and rates of labour, plant and materials during suspension - where certification fixes the costs, the standard is not needed.
- Constraint 2 - duty to mitigate (Article 3.0.9): after suspension the contractor shall act to reduce or prevent enlargement of loss; under the Civil Code the non-breaching party must avoid enlarging loss and cannot claim the enlarged part; a contractor failing to mitigate bears the enlarged loss himself. This bounds the claimable retained staff, idled plant and suspension period.
- Acceptance frame for the evidence: basis (contract clauses / law), evidence (per-item materials, verified on inquiry) and procedure (notice and report within the agreed or statutory periods) all present - missing any one, the claim hardly stands; evidence forms include statements, documents, physical items, audio-visual and electronic data, witnesses, expert opinions and inspection records.
Applicability limits
- The lists are evidentiary directions; the contract's procedure and documentation requirements govern; certifications prevail over itemised computation per the standard.
- Evidence must be verified on inquiry: backdated or later-reconstructed attendance sheets and logs are the common break points - form them contemporaneously with all-party sign-off.
- Wage proof presupposes wages having to be paid (necessity plus objectivity); overhead proof has the daily-amount threshold - a contract total alone will not carry.
- Procedure and periods follow the contract first (failing agreement, the 28-day nodes: notice then report); lateness may forfeit.
- This card settles what evidence to prepare; computation and pricing of each item are in the dedicated cards.
Further reading
T/YJXB 0001-2023: Articles 3.0.3 (certification first), 3.0.9 (mitigation), 6.0.3, 6.0.5, 6.0.8 (computation bases); GB/T 50326-2017 Article 7.5.8; procedure and periods: GB/T 50500-2024 Section 8.11; GB/T 51262-2017 Article 5.8.3 (the employer-caused suspension cost list as the claim anchor).