Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Suspension caused by the employer: claim basis and accrual limits for on-site management staff wages (suspension management fee)

Where construction is suspended for employer causes, on-site management staff wages are claimable: GB/T 51262-2017 Clause 5.8.3 expressly includes "wages of on-site production workers and management staff" in the cost schedule; GB/T 50500-2024 Clauses 8.11.9/8.11.10 list idle-labor costs as a claimable loss and additionally allow profit to be claimed. Accrual follows T/YJXB 0001-2023 Clause 4.0.8 "reasonable suspension management fee" — not higher than in the normal construction period, not zeroed out, based on actual occurrence. It is subject to three limits: the duty to mitigate (necessity of retained staff), cost vouchers, and the 28-day claim procedure; contrary contract agreements prevail.

Applicable Codes

  • GB/T 51262-2017 建设工程造价鉴定规范
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/YJXB 0001-2023 建设工程停工承包人费用计算标准
  • 民法典

Topic Positioning

Whether the contractor's on-site management staff wages (suspension management fee) are claimable when construction is suspended for employer causes, how to accrue them, and what limits apply — a directly reusable set of standard interpretations and compliance reasoning.

Core Conclusions

  1. Claimable, with national-standard basis: GB/T 51262-2017 Code for Cost Expert Determination of Construction Works, Clause 5.8.3, provides that suspension costs caused by the employer are borne by the employer, and its cost schedule expressly lists "wages of on-site production workers and management staff"; GB/T 50500-2024 Standard for Valuation of Construction Works with Bills of Quantities, Clause 8.11.9, lists "idle-labor costs of mobilized personnel unable to proceed with construction" as a claimable loss, and Clause 8.11.10 additionally allows profit to be claimed for employer-responsibility causes (including suspension and failure to resume on time).
  2. Accrual basis: per T/YJXB 0001-2023 Standard for Calculation of Contractor's Suspension Costs, Clause 4.0.8, a "reasonable suspension management fee" shall be accrued over the suspension — for short suspensions management staff are generally not dismissed; wages, office expenses, etc. occur per actual day; the amount shall be no higher than the management fee of the normal construction period, nor zeroed out outright.
  3. Three limits: ① duty to mitigate (Civil Code + T/YJXB Clause 3.0.9) — expanded losses from failure to take loss-prevention measures cannot be claimed, and the necessity of retention determines the compensable headcount; ② accrual per actual occurrence, evidenced by payroll vouchers, attendance records, social insurance, etc.; ③ procedurally, per the contract, issue the claim notice within 28 days after the event and submit the claim report within a further 28 days — late submission is deemed waiver.

Applicable Boundaries

Applies to suspension claims caused by the employer (or borne by the employer per contract); suspension costs caused by the contractor are self-borne; force majeure is handled separately per GB/T 50500-2024 Clauses 8.11.12–8.11.14. Not applicable to single-point price queries or case-specific computation; actual amounts must be determined against suspension duration, the retained-staff roster, and the special conditions of the contract.

Further Reading

GB/T 51262-2017 Clause 5.8.3; GB/T 50500-2024 Clauses 8.11.9, 8.11.10 (and force majeure clauses 8.11.12–8.11.14); T/YJXB 0001-2023 Clauses 2.0.9, 3.0.9, 4.0.8; mitigation rules of the Civil Code; claim procedure in the general conditions of GF-2017-0201.

Keywords

Cited By