Checklist of elements of proof for an employer claiming liquidated damages for delay (late completion) and the measurement of the days of delay: the liquidated damages clause; the commencement date and the contract period; determination of the actual completion date under three scenarios; deduction of approved extensions; attribution of the delay and apportionment of concurrent delay; and the rule of sharing concurrent delays in proportion to liability

Claimable, but the amount is not fixed directly by 'how many days late it actually was': days of delay = actual completion date - (commencement date + contract period + extension approved by the employer), multiplied by the contractually agreed daily rate (subject to any cap). Civil Code Article 585(1) is the basis of the claim, and the employer bears the burden of proof under Civil Procedure Law Article 67(1); where the contractor proves statutory or agreed grounds for extension, or that it applied for an extension within the agreed period, the days are reduced (Fa Shi [2020] No. 25 Articles 9 and 10). The employer need not first prove actual loss - the burden of proving that 'the liquidated damages are excessively higher than the loss' lies on the defaulting party - but to withstand a judicial reduction the employer should still have loss evidence ready.

Applicable Codes

  • 《中华人民共和国民法典》(主席令第45号)第五百八十五条、第五百八十四条、第八百零三条、第八百零四条
  • 《中华人民共和国民事诉讼法》(2023修正)第六十七条
  • 法释〔2015〕5号《最高人民法院关于适用〈中华人民共和国民事诉讼法〉的解释》(2022修正)第九十条
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第六条、第九条、第十条
  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十七条、第二十三条
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.33、8.11.4、8.11.7、8.11.8、8.11.18、8.11.19条
  • GF-2017-0201《建设工程施工合同(示范文本)》第7.3.2、7.5.1、7.5.2、7.6、7.7、7.8.1项
  • T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.9.7条
  • https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2017/art_17339_234222.html
  • https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_8a77c93f6be648d7ad1f30bccc26dce3.html

Topic Positioning

When the employer claims liquidated damages for delay (late completion) from the contractor under the contract, what facts must be proved to the people's court, the normative basis and evidentiary materials for each element, how the days of delay are measured, and how concurrent delay is apportioned. For settlement disputes, preparation of proof in arbitration and litigation, and the preparation and verification of cost and delay assessment opinions.

Core Conclusions

1. Basis of the claim and allocation of the burden of proof

Civil Code Article 585: 'The parties may agree that, where one party breaches the contract, it shall pay the other party a certain amount of liquidated damages according to the circumstances of the breach, or agree on a method of calculating the damages arising from the breach. Where the agreed liquidated damages are lower than the loss caused, the people's court or arbitration institution may increase them upon the request of a party; where the agreed liquidated damages are excessively higher than the loss caused, the people's court or arbitration institution may reduce them appropriately upon the request of a party. Where the parties agree on liquidated damages for delayed performance, the defaulting party, having paid the liquidated damages, shall also perform its obligation.'

Civil Procedure Law Article 67: 'A party shall provide evidence in support of its own claims. Evidence that a party or its agent ad litem cannot collect by itself for objective reasons, or that the people's court deems necessary for trying the case, shall be investigated and collected by the people's court. The people's court shall examine and verify evidence comprehensively and objectively according to statutory procedure.'

SPC Interpretation on the Application of the Civil Procedure Law Article 90: 'A party shall provide evidence to prove the facts on which its own claims are based or its rebuttal of the other party's claims, except as otherwise provided by law. Where, before judgment is made, a party fails to adduce evidence or its evidence is insufficient to prove its factual claims, the party bearing the burden of proof shall bear the adverse consequences.'

That is: the fact, attribution and duration of the delay are proved by the employer; that 'the liquidated damages are excessively higher than the loss' is proved by the party seeking the reduction (see the related card on the judicial adjustment of liquidated damages).

2. Measurement of the days of delay

GB/T 50500-2024 Clause 2.0.33 defines 'delay damages' as: 'the losses the contractor must pay the employer under the contract where, by failing to proceed as planned under the contract works, the actual duration exceeds the contract period or the contract periods of works completed in phases (including extensions approved by the employer); for works agreed to be completed and handed over in phases, delay damages are the compensation calculated under the contract according to the delay time of the relevant part.'

Hence the formula: days of delay = actual completion date - (commencement date + contract period + extension approved by the employer); for works completed and handed over in phases, calculate separately for each phase according to its actual delay and the calculation method agreed in the contract - the phases must not be merged into one total.

3. Checklist of elements of proof (items 1-6 are constitutive; items 7-8 are computational and procedural)

# Element Basis Points of proof (materials) Consequence of failure
1 Valid contract with a clear liquidated damages clause (daily rate, calculation base, cap) Civil Code Article 585(1); GB/T 50500-2024 Clause 8.11.19; GF-2017-0201 Item 7.5.2 Original contract agreement and particular conditions (check the daily rate; whether the base is the contract price at signing or the settlement price; the cumulative cap), letter of acceptance, supplementary agreements No agreement or an unclear one -> only a claim for actual loss; the court or the assessor must not presume a daily rate
2 Contract period and commencement date fixed (baseline completion date) GF-2017-0201 Item 7.3.2: 'the contract period runs from the commencement date stated in the commencement notice'; Item 7.5.2 Commencement notice/report, construction permit, supervising engineer's commencement order, tendered period, period stated in the contract agreement Commencement date unclear -> the days of delay cannot start to run; the actual mobilisation date may be adopted
3 Actual completion date Fa Shi [2020] No. 25 Article 9 (three determination rules, below) Taking-over report/acceptance records (date of passing); proof of receipt of the contractor's taking-over report (where the employer delays acceptance); handover documents, records of use or occupation (premature use) Employer delays acceptance or uses the works prematurely -> the completion date moves earlier; the days of delay shorten or vanish
4 Days of delay (net of approved extensions) GB/T 50500-2024 Clauses 2.0.33, 8.11.7, 8.11.8; Fa Shi [2020] No. 25 Article 10 Register of extension records and approvals (listing each approved and refused item with reasons), approved construction programme (network plan), supervising engineer's extension approvals Failure to prove the approval position -> the contractor's rebuttal suffices to deduct under 'no record but timely application + grounds conforming to the contract'
5 Delay attributable to the contractor (excluding employer causes and relief events) GB/T 50500-2024 Clause 8.11.18(1)(4); converse: GF-2017-0201 Item 7.5.1; Civil Code Articles 803 and 804 Weekly/monthly programme vs actual completion comparisons, supervising engineer's notices and corrective responses, records of labour and plant input, proof that the employer supplied drawings, materials and payments as agreed, weather records Attribution unclear -> apportioned by liability over concurrent delay, or the claim refused in full
6 Apportionment of concurrent delay (overlapping windows) T/ZBD 100.4-2023 Clause 4.9.7(4) Timeline of delay events (start/end dates + responsible party), overlapping-window table, expert or cost assessment opinion Overlapping windows may not be counted into the contractor's delay alone
7 Calculation base and cap not exceeded GB/T 50500-2024 Clause 8.11.19; contract particular conditions; Clause 2.0.33 (phased completion) Confirmation of the settlement price or contract price at signing; for phased completion, calculate at each milestone The part above the cap is not supported; an unclear base is construed against the claiming party
8 No procedural bar or waiver GB/T 50500-2024 Clause 8.11.4 (dual 28-day nodes) Receipts of the Notice of Claim and the claim report, the liquidated damages reservation clause in the settlement documents, correspondence, final closure certificate A settlement agreement containing 'all sums settled, no further claims' or failure to claim in time may be deemed a waiver of the related claim

4. Original texts of key clauses

Fa Shi [2020] No. 25 Article 9: 'Where the parties dispute the actual completion date of the construction works, the people's court shall determine it as follows: (1) where the works have passed taking-over, the date of passing taking-over is the completion date; (2) where the contractor has submitted a taking-over report and the employer delays acceptance, the date the contractor submitted the report is the completion date; (3) where the works have not passed taking-over and the employer uses the works prematurely, the date of transfer of possession is the completion date.'

Fa Shi [2020] No. 25 Article 10: 'Where the parties agree that an extension of the period must be confirmed by the employer or the supervising engineer through a record or similar means, and the contractor, though without confirmation of the extension, can prove that it applied to the employer or the supervising engineer for an extension within the period agreed in the contract and that the grounds for the extension conform to the contract, the contractor's claim to an extension shall be supported by the people's court. Where the parties agree that failure to apply for an extension within the agreed period is deemed no extension of the period, the agreement governs - unless the employer consents to the extension after the agreed period or the contractor raises a reasonable defence.'

GB/T 50500-2024 Clause 8.11.7: 'When calculating delay (or extension) of the period and the resulting claim costs under this section, the work corresponding to the claimed period must lie on the critical path, or be work whose critical path is altered by the claim event; any extension of the contract period approved by the employer under the contract must be the time by which the contract period is extended. The employer must independently evaluate each claim event for all claims by the employer for delay (or extension) costs of the contractor; the claim must not include the costs of delay (or extension) caused to later works by earlier delay (or extension).'

GB/T 50500-2024 Clause 8.11.8: '1 If the delaying event lies on the critical path, the delay time is the period claimed; 2 if the delaying event lies off the critical path, and the work becomes critical because the delay exceeds the total float, the period claimed is the delay time less the total float; 3 if, after the delay, the event still lies off the critical path, no extension-of-time claim arises.'

GB/T 50500-2024 Clause 8.11.18(1)(4): 'losses caused to the employer by delay to the contract works due to the contractor's fault' - the employer may claim under this item according to the time of delay and/or the economic loss.

GB/T 50500-2024 Clause 8.11.19: for losses caused to the employer by the contractor's fault, the employer may choose one or more of '1 extending the quality defect warranty period; 2 requiring the contractor to pay the additional costs incurred; 3 requiring the contractor to pay delay damages; 4 requiring the contractor to pay liquidated damages as agreed in the contract'.

GB/T 50500-2024 Clause 8.11.4 (employer claim procedure): after a claim event, submit a written Notice of Claim for the works within the period agreed in the contract (28 days if not agreed); after the Notice of Claim, submit a written claim report within the agreed period (28 days if not agreed), stating the causes, the clauses relied on, the amount claimed, with records, supporting materials and a detailed cost calculation; for events of continuing effect, continue to give notice at intervals of no more than 28 days or at reasonable intervals, and submit the final report within 28 days after the event ends. 'Where the injured party fails to make a claim within the agreed time after the claim event arises, it is deemed, save as otherwise agreed in the contract or provided by laws and regulations, to have waived the related claim.'

GF-2017-0201 Item 7.5.2: 'Where delay is caused by the contractor, the calculation method and the cap of liquidated damages for late completion may be agreed in the particular conditions. Payment of liquidated damages for late completion does not release the contractor from its obligation to complete the works and to make good defects.'

T/ZBD 100.4-2023 Clause 4.9.7(4): 'Where the duration assessment report states, or the commissioning party determines, that the delay results from concurrent delay or multi-cause events, the expert shall, on the basis of the duration assessment report or the delay time agreed by both parties, and according to the shares of liability determined by the commissioning party, calculate the costs borne by each party in the corresponding proportions.'

5. Reverse checks against contractor defences

The employer must screen in advance the extension grounds the contractor may invoke: the seven categories of employer causes listed in GF-2017-0201 Item 7.5.1 (failure to supply drawings as agreed; failure to provide commencement conditions such as the site, site conditions, baseline data, permits and approvals; errors or omissions in survey baseline point data; failure to agree and issue the commencement notice within 7 days of the planned commencement date; failure to pay the advance payment, progress payments or the final account as agreed; failure of the supervising engineer to issue instructions or approvals as agreed; other circumstances agreed in the particular conditions); Civil Code Article 803: 'Where the employer fails to provide raw materials, equipment, the site, funds or technical data at the agreed time and to the agreed requirements, the contractor may extend the construction period and claim compensation for the losses of suspension and idle labour and plant'; Article 804: 'Where the works are suspended or slowed mid-way due to the employer's fault, the employer shall take measures to remedy or reduce the loss and compensate the contractor for the losses and actual costs thereby incurred, including suspension, idle labour and plant, double handling, relocation of plant and machinery, and the accumulation of materials and components.' Note also GF-2017-0201 Item 7.6 (adverse physical conditions), Item 7.7 (abnormally adverse climatic conditions - the contractor's increased costs from reasonable measures and/or the delayed period are borne by the employer) and Item 7.8.1 (suspension by the employer for its own reasons - the employer bears the costs and the delayed period and pays reasonable profit).

Scope of Application

  • This card assumes a valid contract with a clear liquidated damages (or delay damages) clause for late completion. Where the contract is void, the liquidated damages clause cannot in principle ground the claim; damages must be proved under Fa Shi [2020] No. 25 Article 6: 'Where a construction contract is void and one party claims damages from the other, that party bears the burden of proving the other's fault, the amount of loss, and the causation between fault and loss. Where the amount of loss cannot be determined and a party requests that it be determined by reference to the quality standard, construction period, payment time of the project price and other terms agreed in the contract, the people's court may rule taking into account the degree of fault of both parties, the causation between fault and loss and other factors.'
  • Liquidated damages are a monetary liability; payment does not release the contractor from the obligation to complete the works and make good defects (GF-2017-0201 Item 7.5.2).
  • Under GB/T 50500-2024 Clause 8.11.19 the employer may 'choose one or more' of delay damages and liquidated damages; but each option must correspond to different heads of loss, and the same delay window must not be compensated twice.
  • Delay does not automatically mean lateness: delay to work off the critical path that does not exhaust the total float yields no extension and no delay attributable for counting (Clause 8.11.8); conversely, claim costs must be assessed per event, and the knock-on effect of earlier delay on later works must not be counted again (Clause 8.11.7).
  • The contractor's own suspension and idle-labour-and-plant losses are claimable, but under Fa Shi [2026] No. 12 Article 17(2) 'where the contractor claims priority of payment out of the construction works for losses such as suspension and idle labour and plant caused by the employer, the people's court shall not support the claim' - such claims exist but rank without priority, and they do not affect the employer's claim to liquidated damages.
  • Old/new rule boundary: Fa Shi [2026] No. 12 Article 23: 'These Interpretations take effect from 30 June 2026. For construction contract dispute cases at first instance newly accepted by the people's courts after these Interpretations take effect, these Interpretations apply. Where judicial interpretations previously issued by the Supreme People's Court are inconsistent with these Interpretations, these Interpretations prevail.' First-instance cases accepted before 30 June 2026 still follow Fa Shi [2020] No. 25 and the existing interpretations; check the acceptance date before citing, and do not mix versions.
  • Allocation of the burden of proof does not change the facts: even with every element in place, if the contractor proves that it 'applied for an extension within the agreed period and the grounds conformed to the contract', the days are reduced accordingly (No. 25 Article 10).

Further Reading

  • Civil Code of the PRC (Presidential Order No. 45) Articles 585, 803, 804 and 584
  • Civil Procedure Law of the PRC (2023 amendment) Article 67; SPC Interpretation on the Application of the Civil Procedure Law (Fa Shi [2015] No. 5, 2022 amendment) Article 90
  • Fa Shi [2020] No. 25 'Interpretation (I) of the Supreme People's Court on Issues Concerning the Application of Law in Cases of Construction Contract Disputes' Articles 6, 9 and 10
  • Fa Shi [2026] No. 12 'Interpretation (II) of the Supreme People's Court on Issues Concerning the Application of Law in Cases of Construction Contract Disputes' Articles 17 and 23 (old/new rule boundary)
  • GB/T 50500-2024 'Pricing Standard for Bills of Quantities of Construction Works' Clause 2.0.33 (delay damages), Clause 8.11.4 (employer claim procedure), Clauses 8.11.7 and 8.11.8 (critical path and claimed period), Clause 8.11.18 (claimable scenarios from contractor fault), Clause 8.11.19 (remedies)
  • GF-2017-0201 'Model Construction Contract' Item 7.3.2 (commencement notice and start of the period), Item 7.5.1 (seven categories of employer-caused delay), Item 7.5.2 (liquidated damages for late completion and the cap), Item 7.6 (adverse physical conditions), Item 7.7 (abnormally adverse climatic conditions), Item 7.8.1 (suspension by the employer)
  • T/ZBD 100.4-2023 'Guidelines for Construction Cost Expert Assessment Practice' Clause 4.9.7 (assessment of delay losses and apportionment of concurrent delay by liability share)
  • Official verification pages (Ministry of Housing and Urban-Rural Development): https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2017/art_17339_234222.html ; https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_8a77c93f6be648d7ad1f30bccc26dce3.html

Keywords

  • 工期延误违约金
  • 逾期竣工违约金
  • 误期赔偿费
  • 举证要件
  • 实际竣工日期认定
  • 工期顺延
  • 共同延误
  • critical path
  • 民法典585条