Suspension of the works in four categories (employer-caused / contractor-caused / force majeure / government-ordered suspension): comparison of cost treatment - entitlement rules for personnel wages, time-related overheads during suspension, idle plant costs and suspension profit, extension of time and evidentiary requirements (clause-level comparison)

Suspension is classified by responsible party into three categories, with administrative suspension listed separately. (1) Employer-caused (GB/T 51262-2017 clause 5.8.3 item 2; GB/T 50500-2024 clauses 8.11.9/8.11.10): workers' wages, reasonable time-related overheads during suspension, idle plant costs, and the costs of protection, safekeeping and resumption preparations are all recoverable, profit may additionally be claimed, and time is extended. (2) Contractor-caused (clause 5.8.3 item 3; clause 5.7.4 item 2): all costs are self-borne with no extension of time, and T/YJXB 0001-2023 clause 1.0.3 expressly excludes such pricing. (3) Force majeure (GB/T 50500-2024 clause 8.11.12): losses are allocated by statute - only 'the wages of necessary management and security personnel required by the employer to remain on site and the wages of idle workers', together with the costs of care, clearance and repair and the acceleration costs, fall on the employer, while damage to construction plant and the suspension losses fall on the contractor; time is extended. (4) Government-ordered suspension (clause 8.11.13): time is extended and each party bears its own losses, with Section 8.8 policy-based price adjustment and clause 8.11.12 items 4 and 5 retained as exceptions. Each cost item is calculated under T/YJXB 0001-2023 Chapter 5 on the principle of 'actual-expenditure method first, rule-and-standard method as fallback', with evidence prepared under clauses 6.0.3/6.0.5/6.0.8/6.0.9.

Applicable Codes

  • GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.7.4条、第5.8.3条
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.3条、第8.11.9条、第8.11.10条、第8.11.12~8.11.15条
  • T/YJXB 0001-2023《建设工程停工承包人费用计算标准》第1.0.3、2.0.6、3.0.9、4.0.3、4.0.5、4.0.8、4.0.12、5.0.3、5.0.8、5.0.9、5.0.12、6.0.3、6.0.5、6.0.8、6.0.9条
  • GF-2020-0216《建设项目工程总承包合同(示范文本)》通用合同条件第17条

Topic positioning

How suspension of the works is classified by responsible party, and, for each of the four scenarios, whether site production workers' wages, time-related overheads during suspension, idle plant costs and suspension profit are recoverable, how they are calculated, whether time is extended, and what evidence is required. Basis: GB/T 51262-2017 (standard for construction cost expert assessment), GB/T 50500-2024 (national BOQ pricing standard) and T/YJXB 0001-2023 (standard for calculating the contractor's costs of suspension of construction works).

Core conclusions

1. Classification coordinates: three categories by responsible party, with administrative suspension listed separately

  • Expert assessment approach: GB/T 51262-2017 clause 5.8.3 original text - 'Where the parties dispute a claim for the costs of suspension of the works, the expert assessor shall assess as follows: 1 where the contract stipulates who bears the above costs, the assessment shall follow the contract; 2 where the suspension is caused by the employer, the costs shall be borne by the employer, including the costs of protecting the completed works, the safekeeping costs of materials and equipment delivered to site, construction plant hire charges, the wages of site production workers and management staff, and the costs of the contractor's preparations for resumption; 3 where the suspension is caused by the contractor, the costs shall be borne by the contractor.'
  • Pricing approach: GB/T 50500-2024 clause 8.11.9 takes as its premise 'an event occurring for reasons not attributable to the contractor', listing losses of labour, materials and construction plant caused by suspension, waiting, loss of efficiency and extension of duration.
  • Suspension required by a government competent authority is listed separately in GB/T 50500-2024 as 'an exceptional event of a force majeure nature' (clause 8.11.13); its sharing rules are not wholly identical to true force majeure, and in practice it should be handled as a fourth category.
  • Programme line: GB/T 51262-2017 clause 5.7.4 - '1 where the works are suspended for a reason attributable to the employer, the time shall be extended accordingly; 2 where the works are suspended for a reason attributable to the contractor, no extension of time shall be granted; 3 where, before completion of the works, the parties dispute the quality of the works and suspend pending expert assessment, and the quality of the works is assessed as acceptable and the contractor is not at fault, the assessment period counts as extended time.'

2. Four scenarios x cost items treatment comparison

Scenario Site production workers' wages / management staff wages (time-related overheads during suspension) Idle plant costs Other costs and profit Time
(1) Employer-caused (late drawings, site not handed over, suspension of the works, failure to resume on time after suspension, etc.) All recoverable. T/YJXB clause 4.0.5: 'if the wages of production workers must be paid during the suspension, the resulting increase in cost shall be calculated; if objectively they need not be paid and in fact were not paid, they shall not be counted'; clause 2.0.6 explains that these wages are compensatory in nature and are not counted where no such payment was made. Overheads per clause 4.0.8 'reasonable time-related overheads during suspension' - no higher than during normal construction, nor reducible to zero Recoverable. Clause 5.0.3: hired plant is calculated on the hire charges actually incurred during the suspension; owned plant has its standby costs calculated per the plant rate norms per machine-shift Protection of the completed works, safekeeping of materials and equipment delivered to site, and resumption preparation costs (clause 5.8.3 item 2); labour/material/plant losses including idle costs of labour and plant, losses on materials already delivered to site and standby costs (clause 8.11.9 item 1 and sub-items (1) to (4)); profit may additionally be claimed (clause 8.11.10, covering 'delay caused by the employer, suspension of the works, and failure to resume on time after suspension'); where the suspension is long (generally over 30 days), demobilisation costs (clauses 4.0.12 and 5.0.12) Extended (clause 5.7.4 item 1)
(2) Contractor-caused Not recoverable; borne entirely by the contractor Not recoverable; self-borne None; T/YJXB clause 1.0.3 - 'this standard does not apply to pricing activities arising from mid-course suspension caused by the contractor'; losses from a contractor-caused suspension may not be claimed against the employer No extension (clause 5.7.4 item 2)
(3) Force majeure Limited: only GB/T 50500-2024 clause 8.11.12 item 4 - 'during the suspension, the costs of care, clearance and repair of the works as required by the employer, the wages of the necessary management and security personnel the employer requires to remain on site, and the wages of idle workers the employer requires to remain on site shall be borne by the employer'; not counted where personnel were not required to remain or had been dismissed Not recoverable: clause 8.11.12 item 2 - 'damage to the contractor's construction plant and the suspension losses, and damage to preliminaries items and the costs of their clearance and repair ... shall be borne by the contractor' Damage to the permanent works and to materials already delivered to site and the repair costs, and injury to third-party personnel and property within the site -> employer (item 1); injury to the parties' own personnel and other property -> each party (item 3); acceleration costs -> employer (item 5); no suspension profit. Changes in costs or in laws and policies during the delayed period are handled under clauses 8.7, 8.8 and 8.11.9 (clause 8.11.14); force majeure striking within a delay period is borne by the party responsible for the delay (clause 8.11.15) Extended; where the employer requires acceleration, the acceleration costs are borne by the employer (clause 8.11.12 item 5)
(4) Government administrative / policy suspension (riot and commotion other than occurrences at the site, government-required suspension or interruption of the works / staggered construction / area-wide construction control, safety- and environment-driven stoppages, public-health and epidemic-control stoppages) By the reserved reading: wages of idle workers required to remain on site and wages of necessary management and security personnel are borne by the employer (clause 8.11.12 item 4); not counted where there is no requirement to remain Borne by the contractor (following the clause 8.11.12 item 2 approach) Clause 8.11.13 - 'the affected time shall be extended accordingly, and the employer and the contractor shall each bear their respective losses'; Section 8.8 policy-based price adjustment and clause 8.11.12 items 4 and 5 are retained as exceptions; no suspension profit Extended

3. Calculation methods (T/YJXB 0001-2023 Chapter 5: actual-expenditure method first, rule-and-standard method as fallback)

  • Idle plant costs (clause 5.0.3): actual-expenditure method - calculated on the plant hire charges actually paid during the suspension; rule-and-standard method - calculated under or by reference to the plant rate norms per machine-shift of the same period.
  • Time-related overheads during suspension (clause 5.0.8): a reasonable percentage of daily average overheads multiplied by the number of suspension days; daily average overheads = total contract overheads / contract duration. Overheads comprise 15 second-level accounts, calculated by the actual-expenditure method or, where that is impossible, at a suitable percentage.
  • Suspension profit (clause 5.0.9): a reasonable percentage of daily average profit multiplied by the number of suspension days; daily average profit = total contract profit (or total profit calculated at the profit rate for building enterprises in the statistical yearbook published by the statistical department at the location of the works) / contract duration. Suspension profit is not a current actual expenditure; it is a loss of expectation interest.
  • Demobilisation costs on suspension (clause 5.0.12): calculated on the actual expenditure of demobilisation, or by reference to the pricing rules and policy documents of the same period under a demobilisation plan.
  • Duty to mitigate (clause 3.0.9): 'after the works are suspended, the contractor shall take measures to reduce or prevent the enlargement of the loss ... where the contractor fails to take measures so that the loss is enlarged, it shall bear responsibility for the enlarged loss and may not claim the enlarged loss from the other party.'

4. Evidence requirements (T/YJXB 0001-2023 Chapter 6)

  • Site production workers' wages (clause 6.0.5): meeting minutes, construction logs, employment contracts, labour-service contracts, written labour agreements, attendance sheets, payroll sheets, wage payment records, on-site clock-in records, the project execution plan, electronic materials; the necessity and objectivity of paying the wages during the suspension must be proved.
  • Idle plant costs (clause 6.0.3): entry and exit acceptance slips, hire contracts, the plant inventory, the project execution plan, notarial certificates, hire-charge settlement statements, reconciliation statements, electronic materials; for owned plant, its configuration on the site must be proved.
  • Time-related overheads during suspension (clause 6.0.8): tendering documents, budget documents, construction drawings, the construction contract and the project execution plan showing total overheads and contract duration, to prove the daily amount of overheads and the actual expenditure.
  • Suspension profit (clause 6.0.9): tendering documents, budget documents, construction drawings, the construction contract and the project execution plan showing total profit and contract duration, and the profit rate for building enterprises in the statistical yearbook published by the statistical department at the location of the works.

5. Claims procedure (GB/T 50500-2024 clause 8.11.3) Within the period agreed in the contract (28 days if none) after the event, submit a written Notice of Claim; within the agreed period (28 days if none) after the notice is issued, submit the claim report (cause, relied-upon clauses, claimed costs or days of extension, records and supporting materials, and the detailed cost calculation sheet); for continuing effects, submit successive reports by stage and, after they end, the final report within the agreed period (28 days if none); claims involving both costs and time are submitted together. Where the aggrieved party fails to submit in time, 'unless otherwise agreed in the contract or otherwise provided by laws and regulations, it may be deemed to have waived the relevant claim'; where the other party fails to reply in time, it may be deemed to have approved.

Boundaries of application

  • Where the contract stipulates who bears the costs, the assessment always follows the contract first (GB/T 51262-2017 clause 5.8.3 item 1). For example, clause 17.4 item (4) of the general conditions of the model project general contracting contract GF-2020-0216 provides that where force majeure delays the works, 'the contractor's cost losses from the resulting suspension shall be reasonably shared between the employer and the contractor, and the necessary on-site workers' wages that must be paid during the suspension shall be borne by the employer' - not wholly consistent with GB/T 50500-2024 clause 8.11.12; agreed terms prevail.
  • The opening of clause 8.11.13, 'except as otherwise agreed in the contract and except as provided in Section 8.8 of this standard and items 4 and 5 of clause 8.11.12', is an excepting construction; the mainstream reading is that Section 8.8 (policy-based price adjustment) and items 4 and 5 of clause 8.11.12 remain applicable as retained exceptions. Practice is divided between 'retained' and 'excluded' readings; where an administrative suspension involves wage compensation, the special conditions of contract and the local expert-assessment and adjudication approach must be consulted - mechanical application is inappropriate.
  • Contractor-caused suspension is outside the scope of T/YJXB 0001-2023; under force majeure there is no general basis for claiming 'time-related overheads during suspension' or 'suspension profit'.
  • Each 'reasonable percentage' must be determined on the individual case, the contract and certified records, not mechanically; costs that objectively need not be incurred, or were not actually incurred, are not counted.
  • This card is a horizontal comparison of the four scenarios; the in-depth calculation of individual cost items, the machine-shift basis and verification of the chain of evidence are covered by dedicated cards.

Further reading

  • GB/T 51262-2017 (standard for construction cost expert assessment): clause 5.7.4 (assessment of suspension and extension of time) and clause 5.8.3 (assessment of suspension claims).
  • GB/T 50500-2024 (national BOQ pricing standard): clause 8.11.3 (claims procedure and the 28-day limits), clause 8.11.9 (claims for losses from causes not attributable to the contractor), clause 8.11.10 (profit claimable for employer-responsibility causes), clause 8.11.12 (sharing of force majeure losses), clause 8.11.13 (administrative / policy exceptional events), clause 8.11.14 (cost and policy changes within an extended period), clause 8.11.15 (allocation where force majeure strikes during a delay).
  • T/YJXB 0001-2023 (standard for calculating the contractor's costs of suspension): clause 1.0.3 (excluded scope), clause 2.0.6 (term: site production workers' wages), clause 3.0.9 (duty to mitigate), clauses 4.0.3/4.0.5/4.0.8/4.0.12 (cost items), clauses 5.0.3/5.0.8/5.0.9/5.0.12 (calculation methods), clauses 6.0.3/6.0.5/6.0.8/6.0.9 (calculation bases and evidentiary materials).
  • Model project general contracting contract GF-2020-0216, general conditions clause 17 (definition of force majeure, duty to mitigate, consequences, termination for force majeure).