Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Settlement during suspension: completed qualified work settled as normal + suspension costs shared by cause (employer/contractor/force majeure)

Suspension settlement splits into two ledgers: qualified completed work is measured per actual completion up to the suspension date and settled as normal (disputed portions — undisputed paid first, labor costs never withheld); suspension costs follow the cause — employer-caused: the employer bears all reasonable costs (protection, custody, machinery standstill, wages of workers and managers, resumption preparation, profit, demobilization, etc., GB/T 51262-2017 §5.8.3 + T/YJXB 0001-2023); contractor-caused: self-borne; force majeure/government control shared per GB/T 50500-2024 §8.11.12/13 (permanent works and delivered materials on the employer, machinery and measure losses on the contractor, retained-site wages and care/cleaning/repair on the employer, with extension of time). Contract agreement governs; termination after suspension settles per §10.4.4.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51262-2017 建设工程造价鉴定规范
  • T/YJXB 0001-2023 建设工程停工承包人费用计算标准
  • 保障农民工工资支付条例(国务院令第724号)

Topic Positioning

The complete framework for settling project payments during suspension: work completed before the suspension node settles as normal; new costs during suspension are borne according to the cause. Applies to work suspension scenarios during construction contract performance.

Core Conclusions

Two ledgers: (1) Completed work price — measured and confirmed per actual completion up to the suspension date, settled normally at contract BOQ calibers; disputed portions — undisputed paid first (GB/T 50500-2024 §9.4.11), labor costs never withheld for disputes (Regulations on Ensuring Wage Payment to Migrant Workers, Article 35). (2) Suspension costs by cause: employer-caused — borne by the employer (GB/T 51262-2017 §5.8.3), including completed-works protection, material/equipment custody, machinery rental/standstill, idle worker wages, suspension management fees (not above normal, not zero), resumption preparation, reasonable profit, demobilization beyond 30 days, statutory-fee increases from extension, and labor/machinery price rises (T/YJXB 0001-2023); contractor-caused — self-borne; force majeure/government control (§8.11.12/8.11.13) — permanent works and on-site material losses on the employer, construction machinery and measure losses on the contractor, casualties by each party, care/cleaning/repair costs on employer request and wages of retained management/security/idle workers on the employer, with extension of time and acceleration costs on the employer.

Applicable Boundaries

Targets suspension during contract performance. Where resumption never occurs, settle per contract termination: employer-breach termination pays the completed price, returns the retention money, plus penalties and damages (§10.4.4), with unrecovered prepayments fully clawed back (§9.2.6). Contract agreement governs; suspension claims observe the 28-day procedure with evidence fixed in writing (suspension orders, node measurements, daily cost records).

Further Reading

GB/T 50500-2024 "Standard for valuation of construction works by bill of quantities", Sections 7.1, 8.11, 9.4, 10.4; GB/T 51262-2017 "Code for construction cost expert assessment (judicial appraisal)", Clause 5.8.3; T/YJXB 0001-2023 "Standard for computing contractor costs in work suspension", Clauses 2.0.1, 4.0.1-4.0.22; Regulations on Ensuring Wage Payment to Migrant Workers, Articles 24, 29, 35.

Keywords

Cited By