Settlement during suspension: completed qualified work settled as normal + suspension costs shared by cause (employer/contractor/force majeure)
Suspension settlement splits into two ledgers: qualified completed work is measured per actual completion up to the suspension date and settled as normal (disputed portions — undisputed paid first, labor costs never withheld); suspension costs follow the cause — employer-caused: the employer bears all reasonable costs (protection, custody, machinery standstill, wages of workers and managers, resumption preparation, profit, demobilization, etc., GB/T 51262-2017 §5.8.3 + T/YJXB 0001-2023); contractor-caused: self-borne; force majeure/government control shared per GB/T 50500-2024 §8.11.12/13 (permanent works and delivered materials on the employer, machinery and measure losses on the contractor, retained-site wages and care/cleaning/repair on the employer, with extension of time). Contract agreement governs; termination after suspension settles per §10.4.4.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 51262-2017 建设工程造价鉴定规范
- T/YJXB 0001-2023 建设工程停工承包人费用计算标准
- 保障农民工工资支付条例(国务院令第724号)
Topic Positioning
The complete framework for settling project payments during suspension: work completed before the suspension node settles as normal; new costs during suspension are borne according to the cause. Applies to work suspension scenarios during construction contract performance.
Core Conclusions
Two ledgers: (1) Completed work price — measured and confirmed per actual completion up to the suspension date, settled normally at contract BOQ calibers; disputed portions — undisputed paid first (GB/T 50500-2024 §9.4.11), labor costs never withheld for disputes (Regulations on Ensuring Wage Payment to Migrant Workers, Article 35). (2) Suspension costs by cause: employer-caused — borne by the employer (GB/T 51262-2017 §5.8.3), including completed-works protection, material/equipment custody, machinery rental/standstill, idle worker wages, suspension management fees (not above normal, not zero), resumption preparation, reasonable profit, demobilization beyond 30 days, statutory-fee increases from extension, and labor/machinery price rises (T/YJXB 0001-2023); contractor-caused — self-borne; force majeure/government control (§8.11.12/8.11.13) — permanent works and on-site material losses on the employer, construction machinery and measure losses on the contractor, casualties by each party, care/cleaning/repair costs on employer request and wages of retained management/security/idle workers on the employer, with extension of time and acceleration costs on the employer.
Applicable Boundaries
Targets suspension during contract performance. Where resumption never occurs, settle per contract termination: employer-breach termination pays the completed price, returns the retention money, plus penalties and damages (§10.4.4), with unrecovered prepayments fully clawed back (§9.2.6). Contract agreement governs; suspension claims observe the 28-day procedure with evidence fixed in writing (suspension orders, node measurements, daily cost records).
Further Reading
GB/T 50500-2024 "Standard for valuation of construction works by bill of quantities", Sections 7.1, 8.11, 9.4, 10.4; GB/T 51262-2017 "Code for construction cost expert assessment (judicial appraisal)", Clause 5.8.3; T/YJXB 0001-2023 "Standard for computing contractor costs in work suspension", Clauses 2.0.1, 4.0.1-4.0.22; Regulations on Ensuring Wage Payment to Migrant Workers, Articles 24, 29, 35.
Keywords
- 停工结算
- costs of suspension
- suspension of the works
- 不可抗力停工
- 停工损失分担
- protection of completed works
- time-related overheads during suspension
- 停工撤场费
- T/YJXB 0001-2023
- GB/T 51262-2017
Related Cards
- →
Evolution of the 28-day time limit for construction claims: GB 50500-2013 'forfeiture of the right to claim' vs GB/T 50500-2024 'may be deemed waived', and the 28-day fallback where the contract is silent
GB 50500-2013 (abolished), Clause 9.13.2: the contractor shall submit a Notice of Claim within 28 days after knowing, or ought to have known, of the claim event; 'if the contractor fails to issue the Notice of Claim within the time limit, it forfeits the right to claim' (hard forfeiture). GB/T 50500-2024 (current, recommendatory), Clause 8.11.3, changes this to submission of the Notice of Claim 'within the period agreed in the contract (28 days if not agreed)', and where overdue, it 'may be handled as agreed in the contract' (soft treatment - the strength of forfeiture is delegated to the contract), plus a catch-all clause: 'where the aggrieved party fails to lodge a claim within the agreed time after the claim event arises, it may be deemed to have waived the relevant construction claim, unless otherwise agreed in the contract or provided by laws and regulations.' Where the contract sets no period, the 28-day limit still applies as fallback (Notice of Claim then report, dual nodes), and the overdue consequence falls under 'may be deemed waived', leaving room for exemption through contrary contract agreement, other provisions of laws and regulations, and the discretionary word 'may'.
- →
Preserving on-site evidence after construction disputes arise: priority checklist and strong preservation instruments (incl. Civil Procedure Law notarized evidence effect and pre-suit evidence preservation basis)
After a dispute arises, preserve evidence in the order "secure what will perish first, then collect what won't run away": on day one, prioritize the physical state, concealed works, measurement data, material stockpiles, and suspension scenes (photos/video + joint sign-off (countersignature)); within 1-3 days, systematically collect document originals, electronic data, witness statements, and test reports. Three strong preservation instruments: notarized preservation (Civil Procedure Law Article 69—facts proven by notarization shall be the basis of court findings unless contradicted by sufficient evidence), court evidence preservation (Article 81—available in suit when evidence may be lost, or pre-suit in urgent cases at the court where evidence is located, respondent's domicile, or competent court), and site inspection for construction cost expert assessment (judicial appraisal) (GB/T 51262-2017 Article 4.6—organized by the entrusting party, inspection records signed by those present; refusal to sign without written objection does not bar adoption).
- →
Settlement rules for the construction contract price after contract termination (four scenario rules + three material states + lump-sum contract pricing + quality threshold)
Termination ends only the unperformed part; the performed part must be settled, and conformity of the completed works is the precondition for payment (if repaired to conformity the repair cost is borne; if still nonconforming after repair, no contract price is payable). Termination by agreement is settled per the agreement; termination for force majeure pays seven categories of costs with no liquidated damages or claims; on termination for contractor breach the employer may suspend payment and verify losses, and quality warranty liability is not exempted; on termination for employer breach liquidated damages are additionally payable and the retention money refunded. On-site materials are allocated across three states. For termination of a lump-sum contract with no agreement: contractor breach — contract lump sum minus the price of the unperformed works; employer breach — the completed-work price is computed per contemporaneous pricing bases (GB/T 51262-2017 §5.10.7).
- →
Suspension caused by the employer: claim basis and accrual limits for on-site management staff wages (suspension management fee)
Where construction is suspended for employer causes, on-site management staff wages are claimable: GB/T 51262-2017 Clause 5.8.3 expressly includes "wages of on-site production workers and management staff" in the cost schedule; GB/T 50500-2024 Clauses 8.11.9/8.11.10 list idle-labor costs as a claimable loss and additionally allow profit to be claimed. Accrual follows T/YJXB 0001-2023 Clause 4.0.8 "reasonable suspension management fee" — not higher than in the normal construction period, not zeroed out, based on actual occurrence. It is subject to three limits: the duty to mitigate (necessity of retained staff), cost vouchers, and the 28-day claim procedure; contrary contract agreements prevail.
- →
Delay claims for design changes: critical-path determination, the time/cost double ledger, and the 28-day procedure
Delay caused by events not attributable to the contractor, such as design changes, is claimable, but duration compensation is bounded by the critical path: delays to critical-path activities extend in full; delays to non-critical activities are compensated only for the excess "delay time - total float" once beyond the total float and converted to critical; if still non-critical, no duration is compensated but cost losses remain claimable. Costs include idle labor, machinery standby, efficiency loss, shutdown/restart measures, and rework/demolition; profit may be added for employer-responsibility causes; substantive duration extension links to increased mid-term running costs of preliminary items. Procedurally: a written claim notice within 28 days of the event, then the claim report within the following 28 days — lateness is deemed waiver; on the supervision side, interim/final extension review is required.
Cited By
- ←
Suspension of the works in four categories (employer-caused / contractor-caused / force majeure / government-ordered suspension): comparison of cost treatment - entitlement rules for personnel wages, time-related overheads during suspension, idle plant costs and suspension profit, extension of time and evidentiary requirements (clause-level comparison)
Suspension is classified by responsible party into three categories, with administrative suspension listed separately. (1) Employer-caused (GB/T 51262-2017 clause 5.8.3 item 2; GB/T 50500-2024 clauses 8.11.9/8.11.10): workers' wages, reasonable time-related overheads during suspension, idle plant costs, and the costs of protection, safekeeping and resumption preparations are all recoverable, profit may additionally be claimed, and time is extended. (2) Contractor-caused (clause 5.8.3 item 3; clause 5.7.4 item 2): all costs are self-borne with no extension of time, and T/YJXB 0001-2023 clause 1.0.3 expressly excludes such pricing. (3) Force majeure (GB/T 50500-2024 clause 8.11.12): losses are allocated by statute - only 'the wages of necessary management and security personnel required by the employer to remain on site and the wages of idle workers', together with the costs of care, clearance and repair and the acceleration costs, fall on the employer, while damage to construction plant and the suspension losses fall on the contractor; time is extended. (4) Government-ordered suspension (clause 8.11.13): time is extended and each party bears its own losses, with Section 8.8 policy-based price adjustment and clause 8.11.12 items 4 and 5 retained as exceptions. Each cost item is calculated under T/YJXB 0001-2023 Chapter 5 on the principle of 'actual-expenditure method first, rule-and-standard method as fallback', with evidence prepared under clauses 6.0.3/6.0.5/6.0.8/6.0.9.
- ←
Liability and pricing basis for plant standby (idle machine-shift) costs: a comparison of four scenarios, employer-caused, contractor-caused, force majeure and abnormally adverse weather, with the code and contract clause authority and the rate-reduction rules for standby machine-shifts
Who bears the plant standby cost is decided by who caused the standstill, not by whether the plant stands on site: for an employer-caused standstill the employer bears the cost and profit may additionally be claimed (GB/T 50500-2024 Articles 8.11.9 and 8.11.10; GF-2017-0201 clause 7.8.1); for a contractor-caused standstill the contractor bears it alone (GB/T 51262-2017 Article 5.8.3 paragraph 3; T/YJXB 0001-2023 Article 1.0.3); under force majeure, 'damage to the contractor's construction plant and its costs of suspension' are borne by the contractor while the time for completion is extended (Article 8.11.12 paragraphs 2 and 5); abnormally adverse weather follows the contract, the extra cost of reasonable measures being borne by the employer (GF-2017-0201 clause 7.7). In pricing, the standby machine-shift rate = depreciation + labour cost (idle machine operators) + other charges, excluding overhaul, maintenance and fuel and power, with no uniform percentage discount.
- ←
Where the employer serves a notice of termination, the contractor promptly vacates, and the court later finds the termination invalid: whether the contractor's evacuation constitutes breach (stopping work and vacating the site characterised separately; three conditions of exemption), scenario comparison, loss sharing, and the effective dates of the legal bases
In principle the evacuation is not a breach by the contractor, but 'vacating the site' must be split into two acts: where the termination is invalid the contract still subsists, so if the employer merely served a termination notice it had no right to serve, without suspension or demobilisation instructions, the contractor that stops work on its own and removes its mobilised plant and materials may be found in breach for unauthorised suspension; by contrast, vacating on the strength of the employer's written termination notice and express instructions to stop work, demobilise and hand back the site is the creditor's refusal to accept performance plus a mitigation measure, is not attributable to the contractor, and the evacuation costs and suspension losses are claimable from the employer under Articles 803 and 804 of the Civil Code. Three conditions of exemption: a written notice or instruction as basis; evacuation proportionate to the instruction; prompt resumption once the employer withdraws the notice or requires resumption. Termination by notice does not take effect of itself: without a right to terminate, 'no effect of termination arises' (Fa Shi [2023] No. 13, Article 53), and the same holds even if the other party fails to sue within the objection period (Conference Minutes, Fa [2019] No. 254, Article 46).
- ←
Whether wages of site management personnel and time-related overheads during suspension can be included in an idle-cost claim: determining recoverable and non-recoverable scenarios, the calculation basis and the procedural limits
Yes, but only when handled as two separate cost heads passing three gates. (1) Wages of site management personnel are claimable: GB/T 51262-2017 Clause 5.8.3(2) lists 'wages of site production workers and management personnel' directly among the costs the employer bears when suspension of the works arises from the employer's cause. (2) Suspension overheads are calculable: T/YJXB 0001-2023 Clause 4.0.8 provides that 'reasonable suspension overheads shall be accrued over the suspension period ... they shall be no higher than the overheads amount during normal construction, nor reduced straight to zero', and Clause 5.0.8 computes them as daily average overheads x a reasonable percentage x suspension days (daily average overheads = total contract overheads / contract duration); the clause states only the method and no fixed percentage, and the head must not be double-billed with idle costs. (3) Suspension caused by the contractor is borne by the contractor (Clause 5.8.3(3)); under force majeure only 'wages of the necessary management and security personnel the employer requires to remain on site' are borne by the employer (GB/T 50500-2024 Clause 8.11.12(4)); where government authorities order a stoppage each party bears its own losses (Clause 8.11.13); wages of personnel already dismissed and not actually paid are not counted (Clause 4.0.5); the claim is bound by the duty to mitigate under Civil Code Article 591 and the 28-day claim period; and suspension and idle losses carry no priority right of payment out of the works (Fa Shi [2026] No. 12, Article 17(2)).
- ←
Allocating liability when employer-cause and contractor-cause events delay completion concurrently or in succession: attribution by time segment, extension of time only for the net delay on the critical path, overlapping periods shared in proportion to responsibility, and delay damages charged only on the residual delay left after extension
Neither a 50/50 split nor full liability on either party: the governing approach is 'attribution by segment + sharing in proportion to causative weight + no double counting'. Where responsibility can be separated by time segment, each segment is attributed to its own cause; only genuinely simultaneous, inseparable overlap periods are shared between the parties in proportion to their respective responsibility (T/ZBD 100.4-2023 cl. 4.9.7 para 4). The extendable time equals the net delay caused on the critical path by employer-cause events (and relief events): where the delaying event affects a critical activity, the delay time itself is the extension claimed; where a non-critical activity overruns its total float and becomes critical, the extension is 'delay time minus total float'; where it remains non-critical, no extension claim arises (GB/T 50500-2024 cl. 8.11.8). Delay damages / liquidated damages are charged only for the days by which the actual completion date is later than the extended completion date, because the very base of delay damages is 'the contract time for completion (including extensions approved by the employer)' (GB/T 50500-2024 cl. 2.0.33).
- ←
The requirements, statutory basis, points of proof and post-termination winding-up rules for the employer to terminate the construction contract where the contractor suspends the works for a long period without authorisation (non-performance of principal obligations)
Termination is available, but the mere length of the suspension does not itself create a right to terminate: the contractor's unauthorised suspension is a breach in the form of non-performance of principal obligations, and the employer must bring itself within Article 563(3) of the Civil Code (failure to perform within a reasonable period after demand) or item (4) of that article (the purpose of the contract cannot be achieved), or a contractually agreed termination ground (GF-2017-0201 cl. 16.2.3; GF-2020-0216 cl. 16.1.1 sub-item (8): 'suspension attributable to the contractor exceeding 56 days and affecting the whole of the works, or suspension attributable to the contractor exceeding 182 days'); Article 806(1) of the Civil Code lists only transfer of the works in breach and unlawful subcontracting as the employer's statutory termination grounds and does not include suspension, so a termination notice resting on 'long duration' alone, without demand or without the agreed threshold being met, has no terminating effect. Termination must be made by written notice reaching the other party (Article 565) and exercised within one year from knowing the ground (Article 564); after termination the employer must still settle the price of completed work that is up to standard, and the contractor's quality assurance liability and liability for breach are not discharged.
- ←
Determining extension of time for works suspended by adverse weather: the three-gate test of force majeure or abnormally adverse climatic conditions (event nature -> critical-path causation -> claim procedure), measurement of the critical path and total float, and positive-versus-negative scenario comparison
An extension of time can be granted, but not on the basis that 'the weather was bad': three gates must be passed concurrently - (1) the event qualifies as force majeure (Civil Code Article 180, 'objective circumstances that are unforeseeable, unavoidable and insurmountable', and Article 590 on exemption, notice and proof; GF-2017-0201 Sub-Clause 17.1) or as the 'abnormally adverse climatic conditions' agreed in the contract (GF-2017-0201 Sub-Clause 7.7, not yet amounting to force majeure); (2) the stoppage actually delays work on the critical path (the full delay time is extended) or delays non-critical work beyond its total float (extension = delay time - total float), while work remaining non-critical gives no claim to an extension (GB/T 50500-2024, Clause 8.11.8); and (3) a Notice of Claim is served within the period agreed in the contract or, absent agreement, within 28 days, failing which the right to an extension of time is lost (GF-2017-0201 Sub-Clause 19.1). Ordinary seasonal wind and rain and foreseeable weather are contractor risk and attract no extension; force majeure occurring while the contractor is already in delay does not exempt it from liability for breach.
- ←
Start and end dates for calculating standby rent and standby costs of standing construction plant (hired or owned): to which date they run absent a demobilisation site record, the presumption of the due demobilisation date, and the boundary set by the duty to mitigate
Absence of a demobilisation site record does not defeat the standby-cost claim; it only changes the mode of proof (T/YJXB 0001-2023, Art. 3.0.3: a site record governs where one exists; otherwise the standard applies). Standby rent claimable against the employer runs to the earlier of the 'actual demobilisation date' and the 'due demobilisation date': the due date = suspension date + about 30 days + a reasonable removal period (Art. 4.0.12 takes 'a fairly long suspension, generally more than 30 days' as the yardstick for when demobilisation should occur); where the employer instructs in writing that plant remain on site or demobilisation is objectively impossible, the boundary is the date the instruction ends or the actual demobilisation date; any overstay beyond that is enlarged loss under Article 591 of the Civil Code, borne by the contractor itself. Towards the lessor, rent runs under the hire contract until the plant is actually returned.
- ←
Bases of claim and evidentiary elements for suspension caused by late delivery of employer-supplied (free-issue) materials: the claim bases in Civil Code Arts. 803/804, costs and profit under GB/T 50500-2024 cl. 3.6.1/3.6.5, judicial relief where extension of time is uncertified, an elements table with itemised evidence, the 28-day claim procedure, and exclusion from the priority right
Yes, a claim lies, and it goes beyond an extension of time: under Civil Code Art. 803 the contractor may extend the works date and claim damages for suspension, idle time and like losses; Art. 804 lists the recoverable scope as 'losses and actual costs from suspension, idle labour and plant, double handling, relocation of plant and machinery, and accumulation of materials and components'; GB/T 50500-2024 cl. 3.6.5 goes further: where delivery dates are delayed for reasons attributable to the employer, the affected duration shall be reasonably extended and 'the contractor's losses compensated, including profit' (cl. 8.11.10 likewise allows profit to be claimed for events within the employer's responsibility). The claim must prove three links of causation (late employer-supplied delivery -> suspension of critical-path activities -> losses actually incurred). The elements are: (1) the employer-supply scope and delivery deadlines are defined; (2) the employer actually delivered late; (3) the delay falls on the critical path and caused suspension; (4) the start and end of the suspension are fixed; (5) the losses are real and quantifiable (actual-expenditure method first, rule-based standard method as fallback); (6) the contractor mitigated; (7) the claim was lodged under the 28-day two-stage procedure. Even without a certified extension of time, the contractor may still claim the extension if it applied within the contract period and the ground qualifies under the contract (Fa Shi [2020] No. 25 Art. 10). Suspension and idle-time losses are payable on action but enjoy no priority right of payment out of the works price (Fa Shi [2026] No. 12 Art. 17(2)).
- ←
Whether losses from suspension of the works and idle time can be brought within the priority right of repayment of the construction project price (Fa Shi [2026] No. 12 Article 17(2): not supported; the debt claim may be pursued but enjoys no priority ranking)
No. Article 17(2) of Fa Shi [2026] No. 12 reads: 'Where a contractor claims the priority right of repayment of the construction project price for losses such as suspension of the works or idle time caused by reasons attributable to the employer, the people's court shall not support the claim.' In character such losses are economic loss caused by the employer's breach (claim money), of the same category as the interest, liquidated damages and damages excluded by Article 40(2) of Fa Shi [2020] No. 25: the debt itself is established, can be sued for and paid, but enjoys no ranking ahead of mortgages and other claims; the character is not changed by the loss being certified in a site instruction record or included in the settlement total, and under Article 17(1) of the same interpretation the court must state in the operative part of the judgment 'the amount of the construction price enjoying the priority right of repayment and the corresponding works'.
- ←
Deciding situations where a claim succeeds but only an extension of time is granted without cost compensation: allocation of suspension losses between force majeure and government-mandated stoppages, abnormally adverse climatic conditions, the three requirements for cost claims, negative tests for idle costs, allocation of responsibility for concurrent delay, and the link to delay damages
Under GB/T 50500-2024, 'the claim succeeds but only time is extended, without cost compensation' is not a single event type: (1) force majeure (clause 8.11.12) and stoppages required by government authorities, stoppages required by state or local authorities for safety or environmental protection, stoppages under health and epidemic control requirements, and commotions and riots (clause 8.11.13) operate as 'extension of time plus each party bearing its own losses', but the opening words of clause 8.11.13 expressly exclude policy-based price adjustment under section 8.8 and paragraphs 4 and 5 of clause 8.11.12 (wages of management and security personnel required to remain on site by the employer, wages of idle personnel, and care, clearance and repair costs; acceleration costs required by the employer) - these three heads remain claimable; (2) abnormally adverse climatic conditions (GF-2017-0201 item 7.7) extend time and carry 'the increased costs of reasonable measures taken', but suspension idle losses are outside the item's listed scope; (3) a cost claim must simultaneously satisfy three requirements: a cause not attributable to the contractor (a risk recognised by the contract), actual loss actually incurred, and causation; (4) idle costs fail where no idling actually occurred, or where the delay did not affect the critical path or the total float; (5) concurrent delay is allocated under clause 8.11.15: 'the party responsible for causing the delay bears it; where both parties are responsible, in proportion to their shares of responsibility'; (6) an approved extension of time raises the baseline for calculating delay damages; only unapproved delay triggers delay damages under clause 2.0.33.
- ←
Recognition criteria for force majeure events, item-by-item sharing of losses, costs and time, supporting insurance, and the conditions for terminating the contract for force majeure (GF-2017-0201 clauses 17.1/17.3/17.4 compared with GB/T 50500-2024 clauses 8.11.12 to 8.11.15)
Force majeure is recognised by the three criteria of being unforeseeable at contract signing, unavoidable and insurmountable during performance (GF-2017-0201 clause 17.1). The sharing basis: the employer bears damage to the permanent works and to materials/construction equipment delivered to site, third-party casualties and property losses caused by damage to the works, wages that must be paid to workers during suspension, care/cleaning/repair costs and the wages of necessary personnel kept on site at the employer's request, and acceleration costs requested by the employer; the contractor bears damage to its own construction plant and preliminaries facilities, and each party bears its own casualties and other property; the contractor's other suspension costs are reasonably shared by both parties and the time for completion is extended accordingly; losses enlarged by failure to mitigate are borne by the party that failed to mitigate, and force majeure encountered during delayed performance does not relieve liability for breach (clause 17.3.2; GB/T 50500-2024 clause 8.11.12). Where force majeure prevents performance of the contract continuously for more than 84 days or cumulatively for more than 140 days, either party may terminate; after termination the seven heads of payment under clause 17.4 are paid within 28 days of being agreed or determined.
- ←
FIDIC Red Book 2017 EOT (8.5/20.2) vs GB/T 50500-2024 Section 8.11 delay-claim regime: the 28-day cadence, cost-and-time in one case, three-way liability, and the critical-path causation threshold
FIDIC 2017 Red Book EOT (Sub-Clause 8.5; procedure per 20.2) and GB/T 50500-2024 Section 8.11 share one skeleton: (1) both three-stage - "notice ASAP/within 28 days -> periodic supplements for continuing events -> final report within the period" - with FIDIC 20.2.1's 28-day hard bar ("shall not be entitled to any additional payment") against GB 8.11.3's contractual-period-first, 28-day-default, "handled per contract" and general waiver clause; (2) cost and time claimed in one case (FIDIC 20.2 titled "Payment and/or EOT"; GB 8.11.3(3) "shall be asserted together"); (3) three-way liability: employer causes -> time + cost (listed cases plus profit); government/force-majeure-type events -> time extended, losses borne separately; contractor causes -> no extension plus delay damages; (4) causation: FIDIC 8.5's "in the extent that completion is delayed" lands as the critical-path rule (GB 8.11.8: critical-path delay = claimable; non-critical delay exceeding total float turns critical, the difference claimable; still non-critical = no claim), 8.11.7 requiring event-by-event assessment excluding knock-on delays. Main procedural differences: FIDIC notices go to the Engineer who determines; GB runs directly between employer and contractor; FIDIC's 28 days are fixed, GB's 28 days only a default.
- ←
Panorama of suspension cost items for non-contractor-caused stoppages (T/YJXB 0001-2023: protection / standstill / wages / management / profit / demobilization / price rises / statutory fees)
For non-contractor-caused stoppages, the contractor may claim suspension costs (= cost increases + reasonable profit): completed-works protection (only if measures taken), construction machinery standstill, on-site production worker wages (only if actually paid), reasonable suspension management fees (not above normal, not zero), reasonable suspension profit, suspension demobilization (generally > 30 days), labor/machinery price rises where the extension crosses them, and increased statutory fees. Attribution follows the contract first; employer-caused stoppages are borne by the employer (GB/T 51262-2017 §5.8.3).