Determining extension of time for works suspended by adverse weather: the three-gate test of force majeure or abnormally adverse climatic conditions (event nature -> critical-path causation -> claim procedure), measurement of the critical path and total float, and positive-versus-negative scenario comparison

An extension of time can be granted, but not on the basis that 'the weather was bad': three gates must be passed concurrently - (1) the event qualifies as force majeure (Civil Code Article 180, 'objective circumstances that are unforeseeable, unavoidable and insurmountable', and Article 590 on exemption, notice and proof; GF-2017-0201 Sub-Clause 17.1) or as the 'abnormally adverse climatic conditions' agreed in the contract (GF-2017-0201 Sub-Clause 7.7, not yet amounting to force majeure); (2) the stoppage actually delays work on the critical path (the full delay time is extended) or delays non-critical work beyond its total float (extension = delay time - total float), while work remaining non-critical gives no claim to an extension (GB/T 50500-2024, Clause 8.11.8); and (3) a Notice of Claim is served within the period agreed in the contract or, absent agreement, within 28 days, failing which the right to an extension of time is lost (GF-2017-0201 Sub-Clause 19.1). Ordinary seasonal wind and rain and foreseeable weather are contractor risk and attract no extension; force majeure occurring while the contractor is already in delay does not exempt it from liability for breach.

Applicable Codes

  • 《中华人民共和国民法典》(主席令第45号)第一百八十条
  • 《中华人民共和国民法典》(主席令第45号)第五百九十条
  • GF-2017-0201《建设工程施工合同(示范文本)》第7.6项、第7.7项(异常恶劣的气候条件)
  • GF-2017-0201《建设工程施工合同(示范文本)》第17.1~17.4项(不可抗力的确认、通知、后果承担、解除合同)
  • GF-2017-0201《建设工程施工合同(示范文本)》第19.1、19.2项(索赔程序与处理)
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.8条(工期索赔与关键线路)
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.12条(不可抗力损失分担)
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.13条(政府主管部门要求停工等例外事件)
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十条

Topic Positioning

This card answers: after works are suspended by heavy rain, snowstorms, typhoons or extreme high or low temperatures, can the contractor claim an extension of time, by what standard is it assessed, and through what procedure. The conclusions are organised around the 'three gates' (event nature -> critical-path causation -> claim procedure), with a positive-versus-negative scenario comparison and the connected provisions on allocation of losses, based on the Civil Code, the general conditions of the model construction contract GF-2017-0201, and the China national pricing standard for BOQ, GB/T 50500-2024.

Core Conclusions

Conclusion first: an extension can be obtained, but the basis is not 'bad weather' itself; it is 'loss of time caused by a reason not attributable to the contractor'. If any of the three gates fails, no extension.

Gate 1: nature of the event (three categories, different consequences)

1) Constitutes force majeure -> extension of time; losses allocated by statute plus agreement

Civil Code Article 180: 'Where a civil obligation cannot be performed due to force majeure, no civil liability arises. Where the law provides otherwise, those provisions apply. Force majeure means objective circumstances that are unforeseeable, unavoidable and insurmountable.'

Civil Code Article 590: 'Where a party cannot perform the contract due to force majeure, it is exempted from liability in whole or in part according to the effect of the force majeure, except as otherwise provided by law. A party unable to perform due to force majeure shall promptly notify the other party so as to mitigate the loss that may be caused to it, and shall provide proof within a reasonable time. Where force majeure occurs after the party is in delay, the party is not exempted from liability for breach.'

GF-2017-0201 Sub-Clause 17.1 [Confirmation of Force Majeure]: 'Force majeure means natural disasters and social emergencies that the contract parties could not foresee when concluding the contract and cannot avoid or overcome during its performance, such as earthquakes, tsunamis, epidemics, riots, martial law, insurrection and war, and other circumstances agreed in the particular conditions.' The sub-clause also requires that 'after force majeure occurs, the employer and the contractor shall collect evidence proving the occurrence of the force majeure and the losses it caused, and shall promptly and carefully compile the losses'; where the parties disagree on whether an event is force majeure or on the losses, the supervising engineer deals with it under Sub-Clause 4.4 [Agreement or Determination], and disputes follow Clause 20 [Resolution of Disputes].

2) Constitutes 'abnormally adverse climatic conditions' (not yet force majeure) -> extension of time; reasonable precaution costs borne by the employer

GF-2017-0201 Sub-Clause 7.7 [Abnormally Adverse Climatic Conditions]: 'Abnormally adverse climatic conditions are climatic conditions encountered during construction that an experienced contractor could not foresee when concluding the contract, that materially affect performance of the contract, but that do not yet amount to a force majeure event. The contract parties may specify in the particular conditions the concrete circumstances of abnormally adverse climatic conditions.'

Consequences, as enacted: 'The contractor shall take reasonable measures to overcome the abnormally adverse climatic conditions and continue construction, and shall promptly notify the employer and the supervising engineer. With the employer's consent, the supervising engineer shall promptly issue instructions; where an instruction constitutes a variation, it is dealt with under Clause 10 [Variations]. The costs incurred by the contractor in taking reasonable measures and/or the time delayed are borne by the employer.'

3) Ordinary seasonal climate -> no extension; the contractor retains the risk

Climatic events cannot be rerouted through the 'unforeseeable physical conditions' path: GF-2017-0201 Sub-Clause 7.6 [Unforeseeable Physical Conditions] defines these as 'unforeseeable natural physical conditions, non-natural physical obstructions and pollutants encountered by an experienced contractor at the site, including subsurface and hydrological conditions and other circumstances agreed in the particular conditions, but excluding climatic conditions'. That is, ordinary wind and rain and normal high or low temperatures are risks an experienced contractor should have foreseen at contracting and has already absorbed into the contract duration and price, failing the 'unforeseeable' requirement of Civil Code Article 180.

A further, independent path: stoppages required by government authorities. GB/T 50500-2024, Clause 8.11.13: save as otherwise agreed in the contract and as provided by Section 8.8 and items 4 and 5 of Clause 8.11.12, where a delay in the duration is caused by the following exceptional events of a force majeure nature, 'the affected duration shall be extended accordingly, and the employer and the contractor shall each bear their corresponding losses' - (1) events such as turmoil and insurrection (excluding those occurring at the site); (2) the effects of stoppages, suspension (deferment) of construction, intermittent construction, or regional construction control necessitated by requirements of state or local government authorities; (3) the effects of stoppages ordered by state or local government authorities for safety or environmental protection; (4) the effects of stoppages ordered for health and epidemic control. In other words, for stoppages such as emergency control of heavily polluted weather, safety or environmental stoppages and epidemic control, the duration is extended even if the force majeure threshold is not met (losses are borne by each party, but the costs under items 4 and 5 of Clause 8.11.12, preserved by the first sentence of that clause, remain claimable).

Gate 2: causation and the critical path (GB/T 50500-2024, Clause 8.11.8)

'When a delay event occurs, the parties may determine, on the basis of the approved construction progress programme, whether the event occurs on the critical path and whether it causes a delay to work on the critical path; the extension of the duration claimed shall comply with the following: 1 where the delayed work is work on the critical path, the delayed time is the extension claimed; 2 where the delayed work is not on the critical path but, due to the delay exceeding total float, becomes work on the critical path, the difference between the delay time and the total float is the extension claimed; 3 where the work remains off the critical path after the delay, no claim for extension of the duration arises.'

Commentary on the provision: 'Work on the critical path is decisive for the progress of the whole project and determines the overall duration of the project. Extension of work not on the critical path shall not be counted as a claim for extension of the duration. Where the delayed work is not on the critical path but, having been postponed, becomes work on the critical path, the time extended after it becomes work on the critical path is the extension claimable.'

Gate 3: procedure (notice and claim time limits)

Claim procedure (GF-2017-0201 Sub-Clause 19.1 [Contractor's Claims]): (1) 'The contractor shall, within 28 days of knowing or reasonably being expected to know of the claim event, submit a Notice of Claim to the supervising engineer stating the cause of the claim event; if the contractor fails to give notice within those 28 days, it loses the right to demand additional payment and/or an extension of time'; (2) within 28 days of issuing the Notice of Claim, submit a formal claim report with the necessary records and supporting materials; (3) where the event has a continuing effect, continue to submit further notices at reasonable intervals, stating the cumulative additional payment and/or days of extension; (4) within 28 days after the effect of the claim event ends, submit the final claim report. Determination procedure (Sub-Clause 19.2): the supervising engineer completes its review and reports to the employer within 14 days of receiving the claim report; the employer shall, within 28 days of the supervising engineer receiving the claim report or further supporting materials, issue a determination signed by the employer, 'and if the employer fails to reply within the time limit, the contractor's claim is deemed approved'.

The special notice duty for force majeure (Sub-Clause 17.2): 'Where a party encounters a force majeure event that hinders its performance of contractual obligations, it shall immediately notify the other party and the supervising engineer, explaining in writing the details of the force majeure and of the hindrance, and provide the necessary proof. If the force majeure continues, the party shall promptly submit interim reports to the other party and the supervising engineer on the force majeure and the hindrance to performance, and shall submit the final report and related materials within 28 days after the end of the force majeure event.'

Judicial relief (Fa Shi [2020] No. 25, Article 10): 'Where the parties agree that an extension of time must be confirmed by the employer or the supervising engineer by signed certification or the like, and the contractor, though it has not obtained confirmation of the extension, can prove that it applied within the period agreed in the contract to the employer or the supervising engineer for the extension and that the grounds for the extension accord with the contract, the people's court shall uphold the contractor's claim to the extension. Where the parties agree that the contractor's failure to apply within the agreed period is treated as no extension of time, that agreement governs, unless the employer agrees to the extension after the agreed period or the contractor raises a reasonable defence.'

Positive versus negative scenario comparison

# Scenario Outcome for the duration Main basis
1 Weather meets the force majeure threshold (unforeseeable at contracting, unavoidable and insurmountable in performance, e.g. extreme disastrous weather causing substantial blockage) Duration shall be extended Civil Code Articles 180 and 590; GF-2017-0201 Sub-Clauses 17.1 and 17.3.2
2 Constitutes 'abnormally adverse climatic conditions' short of force majeure Extend; reasonable precaution costs borne by the employer GF-2017-0201 Sub-Clause 7.7
3 Stoppage ordered by a government authority (regional construction control, safety or environmental stoppage, health and epidemic control) Affected duration extended accordingly; losses borne by each party (costs under items 4 and 5 of Clause 8.11.12 remain claimable) GB/T 50500-2024 Clause 8.11.13
4 The delay falls on critical-path work The full delay time counts as the claimed extension GB/T 50500-2024 Clause 8.11.8, item 1
5 Non-critical work delayed beyond total float and becoming critical Extension = delay time - total float Same clause, item 2
6 The work remains non-critical after the delay, float not exceeded No claim for extension (actual cost losses may be claimed separately) Same clause, item 3
7 The particular conditions specify more concrete triggers (rainfall, temperature, wind speed, weather-warning thresholds and the like) Extend as agreed (agreement prevails) GF-2017-0201 Sub-Clause 7.7 ('the parties may specify the concrete circumstances in the particular conditions')
8 Ordinary seasonal rain, normal strong wind, commonly met high or low temperatures No extension; the contractor retains the risk Civil Code Article 180 ('unforeseeable' not met); GF-2017-0201 Sub-Clause 7.6 (climatic conditions expressly excluded)
9 Contractor's own causes (shortage of labour or plant, unsuitable method, failure to take reasonable measures to continue construction) No extension; liable for late-completion damages GF-2017-0201 Sub-Clauses 7.5.2 and 16.2.2
10 Force majeure encountered while the contractor is in delay No exemption from liability for breach Civil Code Article 590(2); GF-2017-0201 Sub-Clause 17.3.2, final paragraph
11 Claim raised out of time (no Notice of Claim within the agreed period or 28 days) Right to demand extension lost (unless a reasonable defence exists or the employer consents afterwards) GF-2017-0201 Sub-Clause 19.1; Fa Shi [2020] No. 25, Article 10

Losses and termination beyond the extension (connected matters, not part of the duration itself)

  • Allocation of force majeure losses (GB/T 50500-2024, Clause 8.11.12): (1) damage to the permanent works and to materials delivered to the site, and repair costs, together with third-party personal injury and property loss within the site and damage to the works caused by the force majeure, are borne by the employer; (2) damage to the contractor's construction plant, suspension costs and damage to preliminary items, and the costs of clearance and repair, together with third-party personal injury and property loss occurring for reasons attributable to the contractor, are borne by the contractor; (3) each party bears its own personnel injuries and property losses other than those above; (4) where the works are suspended by the force majeure, the costs of caring for, clearing and repairing the works as required by the employer during the stoppage, the wages of the management and security personnel required to remain at the site at the employer's request, and the wages of personnel required to remain at the site on standby at the employer's request, are borne by the employer; (5) where the force majeure delays the contractor in performing its contractual obligations, the duration shall be extended, and where the employer requires acceleration, the acceleration costs thereby increased are borne by the employer.
  • GF-2017-0201 Sub-Clause 17.3.2 is to the same effect and adds: 'where the force majeure affects the contractor's performance of its contractual obligations and has caused or will cause a delay in the duration, the duration shall be extended; the contractor's cost losses from the stoppage caused thereby are shared reasonably between the employer and the contractor, and the wages of workers that must be paid during the stoppage are borne by the employer'; 'a party that has failed to take effective measures, with the result that the loss expanded, bears liability for the expanded loss' (corresponding to the mitigation and notice duties of Civil Code Article 590).
  • The insurance path: GF-2017-0201 Sub-Clause 18.1, 'unless otherwise agreed in the particular conditions, the employer shall insure the works under construction all risks insurance or erection all risks insurance'; GB/T 50500-2024, Clause 8.11.12, latter part, allows claiming on the insurer, with deductibles and the amounts exceeding the indemnity borne by the employer and the contractor respectively.
  • Right of termination: GF-2017-0201 Sub-Clause 17.4, 'where performance of the contract is prevented by force majeure continuously for more than 84 days or cumulatively for more than 140 days, both the employer and the contractor have the right to terminate the contract'; after termination, the payments follow the items listed in that sub-clause (the price of the work done, the price of materials and equipment delivered, return costs, evacuation and dismissal costs and the like), agreed or determined, and are paid within 28 days of the determination.

Boundaries of Application

  • GF-2017-0201 is a model text; its general conditions bind the parties only once the contract incorporates them; where the particular conditions or the specific contract stipulate otherwise on climatic thresholds or warning levels, those stipulations govern (Sub-Clause 7.7 expressly authorises agreeing concrete circumstances).
  • Force majeure and 'abnormally adverse climatic conditions' are mutually exclusive tiers: once the force majeure threshold is met, Clause 17 applies; only below it does Sub-Clause 7.7 apply; both differ from Sub-Clause 7.6, 'unforeseeable physical conditions' (which expressly excludes climatic conditions), and from Sub-Clause 7.8, suspension of the works (attributed by instruction or to the employer's or the contractor's causes).
  • This card resolves only the attribution of time risk; compensation for stoppage-period costs (idle labour and plant, standby personnel wages, care, clearance and repair costs, acceleration costs) is allocated separately under GB/T 50500-2024, Clauses 8.11.12 and 8.11.13, and GF-2017-0201 Sub-Clause 17.3.2, and cannot be inferred wholesale from 'the duration was extended'.
  • Critical-path determination must be benchmarked against the approved construction progress programme (the network programme); a claim recognises only critical-path delay or the excess over total float; delay to non-critical work yields no entitlement.
  • Only when both the procedural time limit (the agreed period or 28 days) and the substantive test are satisfied does the extension crystallise; the statute of limitations (three years under the Civil Code) and the contractual claim period are two different mechanisms, and expiry of the claim procedure is not automatically excused by an unexpired limitation period.
  • The force majeure clause does not protect a party already in breach: force majeure occurring after delay does not exempt liability for breach, and yields neither an extension nor exemption.

Further Reading

  • PRC Civil Code (Presidential Decree No. 45), Article 180 (definition of force majeure and exemption), Article 590 (exemption for force majeure, duties of notice and proof, the post-delay exception).
  • GF-2017-0201, Model Construction Contract: Sub-Clause 7.5 [Delays in the Duration], 7.6 [Unforeseeable Physical Conditions], 7.7 [Abnormally Adverse Climatic Conditions], 7.8 [Suspension of the Works], 17.1 to 17.4 [Force Majeure], Clause 18 [Insurance], Clause 19 [Claims].
  • GB/T 50500-2024, China national pricing standard for BOQ: Clause 8.11.8 (claims for extension, critical path and total float), Clause 8.11.12 (allocation of force majeure losses), Clause 8.11.13 (exceptional events such as government-ordered stoppages).
  • Fa Shi [2020] No. 25, SPC Interpretation (I) on Construction Contract Disputes, Article 10 (the extension is upheld where the contractor proves it applied as agreed even without signed confirmation; an agreement that a late application means no extension governs, subject to the proviso).
  • Related extensions: identification and calculation of the critical path and total float, the verification framework for the claim evidence chain (weather certificates, warning documents, the supervising engineer's stop instruction, site records, time-scaled network analysis), and the assessment and negative tests of stoppage-period costs (idle costs, standby wages) - see the related cards cited.