claim for extension of time (EOT)
- 01
Distinguishing claims for extension of time from cost claims: an axis-by-axis comparison of the two independent remedies, time and money, on causation threshold (critical path), basis of calculation (delay duration / total float vs actual-cost method / total-cost method), whether profit is claimable, evidence and time limits, plus the rules of combined calculation and joint approval where both are claimed together
An EOT claim asks for time, a cost claim asks for money; both are econom…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.31条、第8.11.1~8.11.13条T ZBD 100.5-2023 建设工程结算审核作业指引 第3.1.9条T ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.7.3~4.7.5条2026-11-01 - 02
Rules and workflow for determining the extendable days of time from the critical path and total float after the works programme changes (GB/T 50500-2024, Article 8.11.8 three tiers + Article 8.11.7 event-by-event independent accounting)
The extendable days equal 'the actual increment of the overall duration…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.3、8.11.5、8.11.7、8.11.8、8.11.9、8.11.10条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.7.5条JGJ/T 121-2015 · Specification for Engineering Network Planning Technology 第2.1.33、5.5.1条2026-10-29 - 03
Allocating liability when employer-cause and contractor-cause events delay completion concurrently or in succession: attribution by time segment, extension of time only for the net delay on the critical path, overlapping periods shared in proportion to responsibility, and delay damages charged only on the residual delay left after extension
Neither a 50/50 split nor full liability on either party: the governing…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.33、8.7.4、8.11.7、8.11.8、8.11.10、8.11.15、8.11.18、8.11.19条GB/T 51262-2017 建设工程造价鉴定规范 第5.7.4、5.7.6条T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.9.7条2026-10-29 - 04
Whether acceleration cost (for earlier completion) can be claimed when the employer demands acceleration: allocation of responsibility, the claimable net amount (after deducting the mid-term running costs of preliminaries saved by the shortened duration), approval before implementation, and the 28-day claim procedure
Claimable, but only the net amount. GB/T 50500-2024 cl. 8.11.17: where t…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.32条、第7.4.4条、第6.2.13条、第8.9.4条、第8.9.5条、第8.9.6条、第8.11.3条、第8.11.5条、第8.11.17条GF-2017-0201《建设工程施工合同(示范文本)》第7.9.1条、第7.9.2条《中华人民共和国民法典》第七百九十三条第一款、第五百八十四条、第八百零四条2026-10-29 - 05
Determining extension of time for works suspended by adverse weather: the three-gate test of force majeure or abnormally adverse climatic conditions (event nature -> critical-path causation -> claim procedure), measurement of the critical path and total float, and positive-versus-negative scenario comparison
An extension of time can be granted, but not on the basis that 'the weat…
《中华人民共和国民法典》(主席令第45号)第一百八十条《中华人民共和国民法典》(主席令第45号)第五百九十条GF-2017-0201《建设工程施工合同(示范文本)》第7.6项、第7.7项(异常恶劣的气候条件)2026-10-29 - 06
Whether a contractor that fails to apply for an extension of time (an EOT claim) within the contractually agreed period forfeits the right to extension: the two-paragraph rule of Article 10 of Fa Shi [2020] No. 25, the two exceptions of the employer's subsequent consent and the contractor's reasonable justification, and the three-way split by the state of the contractual agreement
Not necessarily forfeited. Fa Shi [2020] No. 25, Article 10, paragraph 1…
最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)(法释〔2020〕25号)第十条最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)(法释〔2026〕12号)第二十三条(2026年6月30日施行)https://www.court.gov.cn/fabu/xiangqing/504221.html中华人民共和国民法典(主席令第45号)第一百四十条、第八百零三条、第八百零四条2026-10-29 - 07
Delay claims for design changes: critical-path determination, the time/cost double ledger, and the 28-day procedure
Delay caused by events not attributable to the contractor, such as desig…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范TB 10402-2019 铁路建设工程监理规范2026-09-25 - 08
FIDIC Red Book 2017 EOT (8.5/20.2) vs GB/T 50500-2024 Section 8.11 delay-claim regime: the 28-day cadence, cost-and-time in one case, three-way liability, and the critical-path causation threshold
FIDIC 2017 Red Book EOT (Sub-Clause 8.5; procedure per 20.2) and GB/T 50…
FIDIC Conditions of Contract for Construction, 2nd Edition 2017, Sub-Clause 8.5/8.7/20.2, Clause 18GB/T 50500-2024 建设工程工程量清单计价标准 第8.11节2026-09-25 - 09
The non-equivalence of FIDIC 2017 Red Book delay machinery and the national-standard delay regime: delay fact / EOT / Delay Damages vs delay claims / extensions / delay damages / liquidated damages
Not equivalent. FIDIC never treats delay as a single term: it is a chain…
FIDIC Conditions of Contract for Construction (Red Book), Second Edition 2017, Sub-Clauses 8.2/8.5/8.8/10.1/20.2GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 2.0.33 条、第 8.11.3~8.11.19 条GB/T 50875-2013 · Standard glossary of project costs 第 3.4.6 条2026-09-25 - 10
Difference between free float and total float, and graded handling of schedule deviations in practice
Free float (FF) = the slack usable without delaying the earliest start o…
JGJ/T 121-2015 工程网络计划技术规程GB/T 50358-2017 建设项目工程总承包管理规范GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 11
Identifying the critical path and the effect of critical-activity delays on total duration and duration claims
A critical activity = the activity with the least total float; the criti…
JGJ/T 121-2015 工程网络计划技术规程GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25