Whether a contractor that fails to apply for an extension of time (an EOT claim) within the contractually agreed period forfeits the right to extension: the two-paragraph rule of Article 10 of Fa Shi [2020] No. 25, the two exceptions of the employer's subsequent consent and the contractor's reasonable justification, and the three-way split by the state of the contractual agreement
Not necessarily forfeited. Fa Shi [2020] No. 25, Article 10, paragraph 1: where the parties agree that an extension must be confirmed by the employer or the supervising engineer and the contractor obtains no confirmation, but can prove that it applied for the extension within the contractually agreed period and that the grounds meet the contract, the court shall support the extension; paragraph 2: where the parties agree that failure to apply in time is deemed no extension of time, 'the agreement governs, except where the employer consents to the extension after the agreed period or the contractor raises a reasonable justification'. Where the contract merely requires an application without fixing any consequence of lateness, forfeiture is not presumed, because under Civil Code Article 140(2) silence is a declaration of intent only where so provided by law, by the parties' agreement or by usage; the case moves to substantive review under Civil Code Articles 803 and 804.
Applicable Codes
- 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)(法释〔2020〕25号)第十条
- 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)(法释〔2026〕12号)第二十三条(2026年6月30日施行)https://www.court.gov.cn/fabu/xiangqing/504221.html
- 中华人民共和国民法典(主席令第45号)第一百四十条、第八百零三条、第八百零四条
- GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.3条、第8.11.5条
- GF-2020-0216 建设项目工程总承包合同(示范文本)通用合同条件第19.1~19.4条
- GF-2003-0213 建设工程施工专业分包合同(示范文本)第13条、第14条
- DBJ41/T 208-2018 建设工程监理工作标准 第9.4.4条
- DB/T 29-131-2015 天津市建设工程监理规程 第7.5.3条
- T/CAEC 006-2024 建筑工程监理文件资料管理标准 第7.3.8条
- 中华人民共和国民事诉讼法(2023修正)第六十八条
- 中华人民共和国仲裁法(2025修订)第九十条(2026年3月1日施行)
- 保障中小企业款项支付条例(2025修订)第八条、第九条
Scope of the Topic
A decision framework for the question 'does a contractor that fails to apply for an extension of time within the contractually agreed period necessarily forfeit the right to the extension'. The core basis is Article 10 of the SPC Interpretation on the Application of Law to Construction Contract Dispute Cases (I) (Fa Shi [2020] No. 25), read with Articles 140, 803 and 804 of the Civil Code and the procedural time-limit provisions of GB/T 50500-2024 and GF-2020-0216.
Core Conclusions
Conclusion: not necessarily forfeited. The judicial interpretation treats 'no application in time means no extension' as a question of the validity of an agreed clause, not as a statutory forfeiture imposed by law - only where the contract expressly agrees that failure to apply within the agreed period is deemed no extension of time does 'the agreement govern', and even then two exits remain (the employer's subsequent consent, and the contractor's reasonable justification).
I. Text of Article 10 of Fa Shi [2020] No. 25 (the two-paragraph rule)
Paragraph 1: 'Where the parties agree that an extension of time shall be confirmed by the employer or the supervising engineer through site instruction or similar means, and the contractor, though not having obtained confirmation of the extension, can prove that it applied to the employer or the supervising engineer for the extension within the period agreed in the contract and that the grounds for the extension meet the contract, the people's court shall support the contractor's claim to an extension on that basis.'
Paragraph 2: 'Where the parties agree that failure by the contractor to apply for an extension of time within the agreed period is deemed that the construction period is not extended, the agreement governs, except where the employer consents to the extension after the agreed period or the contractor raises a reasonable justification.'
II. Three-way split by the state of the contractual agreement
| State of the contractual agreement | Conclusion | Basis |
|---|---|---|
| Only agrees that an extension must be confirmed by the employer or the supervising engineer through site instruction or the like; no consequence of lateness agreed | Extension available even without confirmed instruction: where the contractor can prove (1) within the period agreed in the contract (2) to the employer or the supervising engineer (3) it applied for the extension and (4) the grounds meet the contract, the claim shall be supported | Fa Shi [2020] No. 25 Article 10 paragraph 1 |
| Expressly agrees that failure to apply in time is deemed no extension | In principle no extension under the agreement, but not inevitably: where the employer consents to the extension after the agreed period, or the contractor raises a reasonable justification, an extension is still available | Article 10 paragraph 2 |
| No procedural agreement on extension at all | No basis for forfeiture; proceed to substantive review and treat as statutory extension: where the employer fails to provide raw materials, equipment, the site, funds or technical data at the agreed time and to the agreed requirements, the contractor may extend the construction date and claim compensation for standstill, idle time and other losses; where the works are halted midway or slowed down due to the employer, the employer shall take measures to remedy or mitigate the loss and compensate the contractor for standstill, idle time, double handling, relocation of plant and machinery, stockpiled materials and components and other losses and actual expenses thereby caused | Civil Code Articles 803, 804 |
III. 'No consequence of lateness agreed' does not imply forfeiture
Civil Code Article 140(2): 'Silence may be deemed a declaration of intent only where it is provided by law, agreed by the parties, or consistent with the usage between the parties.' A contract that merely says an application 'shall be made' or 'shall be reported to the supervisor for confirmation', without an express clause that lateness is deemed no extension, lacks the agreed basis for fictively treating silence as waiver.
IV. Typical forms in which the two provisos are met
- Subsequent consent by the employer: issuing an extension record or confirmation sheet, confirmation in minutes of meetings, approval of the adjusted programme, or entering the extension or relief in later progress payments or settlement documents.
- Reasonable justification by the contractor: objective obstacles not attributable to the contractor (such as government stop-work controls) making timely submission impossible; the employer instructed continued construction and undertook to deal with the matter in the round; the conditions for applying were never met because of the employer's own causes.
V. The mirror rule - the employer that fails to answer in time faces deemed approval
GB/T 50500-2024 Clause 8.11.5(2): 'The employer shall, within the period agreed in the contract (28 days where the contract is silent) after receiving the contractor's works claim report or supplementary proof, reply to the contractor in writing with its position on the claim. Where the employer replies late or makes no reply, the contract governs; where the contract is silent, the works claim demanded by the contractor may be deemed approved.' Paragraph 1 of the same clause gives the employer the right to require supplementary proof in writing 'within the period agreed in the contract (14 days where the contract is silent)' after receiving the Notice of Claim. GF-2020-0216 general conditions Clause 19.2(2): where the Engineer fails to answer within 42 days after receiving the claim report or further proof, the claim is deemed approved.
VI. Baseline procedural time limits (28 days where the contract is silent)
GB/T 50500-2024 Clause 8.11.3: (1) submit a written Notice of Claim for works within the period agreed in the contract after the claim event occurs (28 days where the contract is silent), stating the causes and the claim intention - 'where the contractor fails to issue the Notice of Claim within that time, the contract governs'; (2) submit a written claim report within the same period after the Notice of Claim is issued, stating the causes, the contract clauses relied on and the additional payment and/or days of extension claimed, with records, proof and an itemised cost calculation sheet; (3) claims involving both additional payment and extension shall be raised together; (4) for continuously acting events, submit continuation notices at the intervals agreed in the contract (not exceeding 28 days where the contract is silent) or at reasonable intervals, listing the cumulative claimed costs and/or extension days; (5) submit the final claim report within the same period after the continuous influence ends. The clause also provides: 'Where the injured party fails to raise a claim within the agreed time after the claim event, the relevant works claim may be deemed waived, except where the contract provides otherwise or laws and regulations provide otherwise.'
VII. Contracts and standards carrying hard-forfeiture wording (stronger forfeiture, still subject to the provisos and to Civil Code Article 140)
- GF-2020-0216 general conditions Clause 19.1(1): the claiming party shall deliver the Notice of Claim within 28 days after it becomes or may be deemed to become aware of the claim event; 'a claiming party that fails to issue the Notice of Claim within those 28 days loses the right to demand an increase or reduction of payment, extension of the defects liability period and/or extension of time'; Clause 19.4 sets further limits: after receiving the completion payment certificate no claim may be raised for events arising before the taking-over certificate for the works is issued; the final closure application may raise only claims arising after issue of the taking-over certificate; the periods end upon acceptance of the final closure certificate.
- DBJ41/T 208-2018 Clause 9.4.4: the construction unit shall submit the Notice of Claim within 28 days after it becomes or may be deemed to become aware of the claim event; 'a construction unit that fails to issue the Notice of Claim within those 28 days is deemed to have waived the right to demand additional payment and/or extension of time'; the project supervision body shall complete its review within 14 days after receiving the claim report and forward it to the employer; the employer shall issue a signed claim decision within 28 days, and a late answer is deemed approval.
- GF-2003-0213 (specialist subcontracting) Clause 13.1: where the subcontractor cannot start on time it shall state its reasons for delayed start in writing no later than 5 days before the agreed start date; the contractor shall reply in writing within 48 hours; no reply is deemed consent and the time is extended accordingly; 'where the contractor does not agree to the delay request, or the subcontractor fails to raise the delayed-start request within the prescribed time, no extension of time is granted'. Clause 14.2: the subcontractor shall report in writing within 14 days after the events of Clause 14.1 occur; the contractor shall confirm within 14 days of receipt; failure to confirm or to comment is deemed consent to the extension.
VIII. At the litigation and arbitration stage: procedural lateness is not evidentiary forfeiture
Civil Procedure Law (2023 amendment) Article 68: a party shall provide evidence for its claims in good time; where evidence is provided late the people's court orders the party to state its reasons; where the party refuses to state them or the reasons do not hold, the court may, as the case may be, refuse to admit the evidence, or admit it while reprimanding or fining the party. Arbitration Law (2025 revision, effective 1 March 2026) Article 90: 'Where the law provides limitation periods for arbitration, those provisions apply; where it does not, the limitation rules for litigation apply.' (Article 74 of the 2017 revision is to the same effect.)
IX. The supervisor's review criteria
DB/T 29-131-2015 Clause 7.5.3: review of a Notice of Claim for extension of time requires that (1) the contractor's project department raised it within the period agreed in the construction contract; (2) the event was caused by causes outside the contractor and meets the construction contract; (3) the event affects the construction period agreed in the contract; where satisfied, it is reported to the employer. T/CAEC 006-2024 Clause 7.3.8: the project supervision body may refuse to accept a claim application raised beyond the period agreed in the construction contract; the sign-off times of the Notice of Claim and of the reply start the processing period agreed in the construction contract.
Applicability Boundaries
- Article 10 of Fa Shi [2020] No. 25 settles the validity of, and exceptions to, agreed clauses; it creates no statutory extension right. Where there is no procedural agreement, the contract is invalid, or there is no written contract, responsibility for delay is reviewed substantively under Civil Code Articles 803 and 804, regardless of procedural lateness.
- 'Not necessarily forfeited' does not mean exemption from proof: the party claiming the extension must still prove that it applied within the agreed period (written notice, proof of receipt or service) and that the grounds meet the contract. That 'the employer knew of the delay', that 'the supervisor's log records it' or that 'work on site truly stopped', without any act of application, does not satisfy paragraph 1 - 'knowing' is not 'having applied'.
- The 'forfeiture' and 'deemed waiver' wording of model texts and local standards is contractual or recommendatory; its validity is tested by the Article 10 provisos and Civil Code Article 140(2); conversely, where the contract does expressly so agree and no proviso applies, the court follows the agreement.
- Temporal boundary: Interpretation (II) (Fa Shi [2026] No. 12, adopted at the 1969th meeting of the SPC Adjudication Committee on 17 March 2026, published 29 June 2026) Article 23: 'This Interpretation takes effect on 30 June 2026. For first-instance construction contract disputes newly accepted by the people's courts after this Interpretation takes effect, this Interpretation applies. Where judicial interpretations previously issued by the Supreme People's Court are inconsistent with this Interpretation, this Interpretation prevails.' Before invoking Article 10 of Interpretation (I), check whether Interpretation (II) provides otherwise on extension or claim procedure; Interpretation (I) as a whole has not been repealed.
- Where the event is the employer's funds not being in place (for government-invested projects the funds required shall be secured in place under state provisions and construction shall not be financed by advances from the contractor - Regulation on Ensuring Payment to Small and Medium Enterprises (2025 revision) Article 8(2)), it may serve as an extension ground under 'failure to provide funds as agreed' in Civil Code Article 803; the payment periods of Article 9 of that Regulation (organs and public institutions within 30 days of delivery, or at most 60 days where the contract otherwise agrees; large enterprises within 60 days) bear no direct relation to forfeiture of the extension and the two do not substitute for each other.
Further Reading
- Fa Shi [2020] No. 25 Article 10 (validity of extension-procedure agreements and the two exceptions); Fa Shi [2026] No. 12 Article 23 (effective-date boundary); the full text of Interpretation (II) is on the SPC website, https://www.court.gov.cn/fabu/xiangqing/504221.html
- Civil Code Article 140 (fiction of silence), Article 803 (extension and standstill/idle-time compensation where the employer fails to provide construction conditions), Article 804 (compensation where the works halt or slow due to the employer)
- GB/T 50500-2024 Pricing Standard for Bills of Quantities of Construction Works, Clause 8.11.3 (periods and consequences for the Notice of Claim, claim report, continuation notices and final report), Clause 8.11.5 (employer review and reply; late reply deemed approval)
- GF-2020-0216 Model Conditions of Contract for Construction Project General Contracting, general conditions Clauses 19.1-19.4 (the dual 28-day nodes, the 42-day reply deemed approval, the end of claim periods)
- GF-2003-0213 Model Contract for Specialist Subcontracting of Construction Works, Clauses 13 and 14 (periods and consequences for delayed start and for delay)
- DBJ41/T 208-2018 Standard for Construction Supervision of Building Works, Clause 9.4.4; DB/T 29-131-2015 Tianjin Specification for Construction Supervision of Building Works, Clause 7.5.3; T/CAEC 006-2024 Standard for Management of Supervision Documents of Building Works, Clause 7.3.8
- Civil Procedure Law (2023 amendment) Article 68; Arbitration Law (2025 revision) Article 90
- Regulation on Ensuring Payment to Small and Medium Enterprises (2025 revision) Articles 8, 9
Keywords
- 工期顺延
- 逾期申请
- 法释〔2020〕25号第十条
- 视为工期不顺延
- 合理抗辩
- claim for extension of time (EOT)
- Notice of Claim
- 28天期限
- GB/T 50500-2024