Whether the employer's overdue non-reply to the final account documents is deemed acceptance of the submitted amount - the three-requirement test of Fa Shi [2020] No. 25, Article 21, and interface with GB/T 50500-2024

Where the contract stipulates 'overdue non-reply is deemed acceptance', under Fa Shi [2020] No. 25, Article 21, the people's court shall support the contractor's claim for settlement per the final account documents (submitted price); three requirements must be met simultaneously: an express contractual stipulation, delivery of complete settlement documents, and no reply within the agreed period. Absent such stipulation, claims based only on ministerial rules or model contract texts containing 'deemed acceptance' wording are not supported by the SPC and the overwhelming majority of courts. GB/T 50500-2024, Clause 10.3.8, points the same way but is a recommendatory national standard that becomes a contractual obligation only when incorporated by the contract; at the rule level, Article 16 of the former MOC Decree No. 107 has been carried over by Article 18 of MOHURD Decree No. 16, with 28 days as the default period absent agreement.

Applicable Codes

  • 《中华人民共和国民法典》第一百四十条、第一百八十八条、第一百九十五条、第八百零七条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号,2021年1月1日施行)第二十一条、第二十六条、第二十七条、第四十一条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号,2026年6月30日施行)第十三条、第二十一条、第二十三条
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第1.0.3、10.3.5、10.3.8、10.3.9、10.3.16条
  • 住建部令第16号《建筑工程施工发包与承包计价管理办法》(2014年2月1日施行)第十八条、第十九条
  • 财建〔2004〕369号《建设工程价款结算暂行办法》第十六条
  • 国务院令第802号《保障中小企业款项支付条例》(2025修订)第九条、第十条、第十三条、第十四条、第十七条
  • GB/T 51262-2017 · Code for Construction Cost Appraisal

Topic Positioning

Where the employer fails to reply within the time limit after receiving the final account documents and the contract stipulates 'deemed acceptance', can the contractor claim settlement directly at the submitted price? This card gives the application requirements of Article 21 of the SPC interpretation, the judicial attitude where the contract is silent, the position of GB/T 50500-2024 and the mechanism of incorporation by contract, for use in settlement demands and litigation strategy.

Core Conclusions

  1. With an express 'deemed acceptance' stipulation, Article 21 of the SPC Interpretation (I) on Construction Contract Disputes (Fa Shi [2020] No. 25) applies: 'Where the parties agree that the employer's failure to reply within the agreed period after receiving the final account documents is deemed acceptance of those documents, the agreement shall be honored. If the contractor claims settlement of the project price per the final account documents, the people's court shall support the claim.' (Carried over from Article 20 of Fa Shi [2004] No. 14.) Court support requires three simultaneous elements: (i) an express contractual stipulation; (ii) actual receipt of the final account documents by the employer (complete documents with proof of delivery); (iii) no reply within the agreed period.
  2. Without such stipulation, claims based only on ministerial rules (Measures for the Administration of Pricing in Contracting and Subcontracting of Building Works), Article 16 of Cai Jian [2004] No. 369, or 'deemed acceptance' wording in model contract texts are not supported by the SPC and the overwhelming majority of courts - choosing to apply a model text or rule containing a deemed-acceptance provision does not constitute the 'special agreement' in the sense of Article 21 of the interpretation.
  3. GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clause 10.3.8: 'Where the employer, within the agreed time after receiving the contractor's final account documents, fails to check the final account as agreed in the contract or fails to give checking comments, the final account documents submitted by the contractor shall be deemed accepted by the employer and the final account is confirmed.' Clause 10.3.5 (where the contractor submits late, the employer may compile from available materials and request confirmation; the contractor's overdue non-reply is deemed acceptance). The position is consistent with the judicial interpretation: both anchor 'deemed acceptance' in the framework of 'agreed time / as agreed in the contract'. Note the 2024 edition is a recommendatory national standard (GB/T), not a mandatory one like GB 50500-2013; effective 1 June 2025, it replaced the 2013 edition; General Provision 1.0.3 establishes the principles of 'law first, agreement honored': 'Pricing activities of construction works shall follow the principles of objectivity and fairness, free will, good faith, law first, and honoring agreements; where the contract provides otherwise, its provisions shall be followed.'
  4. The standard can be incorporated into the contract and turned into a contractual obligation: if the particular conditions state 'the final account shall be executed per GB/T 50500-2024', Clause 10.3.8 becomes a contractual obligation, and the employer's overdue failure to check or reply falls within the track of Article 21; but where the contract only generically states 'national standards and codes shall apply', whether this constitutes an 'express agreement' in the sense of Article 21 is disputed in practice and strictly examined. Safe drafting: write directly in the particular conditions 'if the employer fails to reply within X days after receiving the contractor's final account documents, the documents shall be deemed accepted'.
  5. Rule level: Article 16 of the former MOC Decree No. 107 (overdue non-replied final account documents deemed accepted; absent an express period, 28 days applies) was repealed by Article 27 of MOHURD Decree No. 16 (effective 1 February 2014), and its content is carried over by Article 18 of Decree No. 16 (overdue non-replied final account documents deemed accepted; 28 days by default absent agreement; confirmed final account documents serve as the basis for project final accounts).
  6. Practice: (i) check the contract - any deemed-acceptance clause or incorporation of the BOQ valuation standard; (ii) lock delivery - submit the final account documents with complete supporting materials in writing and keep proof of receipt or EMS waybills; the reply period runs from receipt of complete documents; (iii) documented demands - on expiry without reply, send a written demand letter fixing the fact of 'overdue non-reply', optionally stating that overdue silence will be deemed acceptance; (iv) litigation strategy - primary claim: settle at the submitted price (contract clause plus Fa Shi [2020] No. 25, Article 21, reinforced by GB/T 50500-2024, Clause 10.3.8); alternative: apply for a project cost expert determination, to avoid a dead end if the agreement is unclear.

Applicable Boundaries

A 'deemed acceptance' claim requires all three elements (express stipulation plus delivered complete documents plus no reply within the agreed period), with the period running from the employer's receipt of complete settlement materials; without a contractual stipulation, success rates are low and some courts deny deemed acceptance and turn to judicial cost expert determination instead. Outcomes depend on the contract wording, provincial high court positions and evidentiary completeness. For state-funded projects the employer must by rule engage a cost consultant for review, and a deemed-acceptance clause cannot exclude the statutory review procedure; this card concerns confirmation of the settlement amount, a different procedure from a payment application being deemed accepted when the payment certificate is not issued in time (GB/T 50500-2024, Clause 10.3.16).

Further Reading

Fa Shi [2020] No. 25, Article 21 (carrying over Fa Shi [2004] No. 14, Article 20); GB/T 50500-2024, Clauses 1.0.3, 10.3.5 and 10.3.8; current MOHURD Decree No. 16, Measures for the Administration of Pricing in Contracting and Subcontracting of Building Works, Article 18 (former MOC Decree No. 107, Article 16 repealed and carried over; 28 days by default); Cai Jian [2004] No. 369, Interim Measures for Settlement of Construction Project Prices, Article 16; for expert determination rules on settlement disputes, see the relevant chapters of GB/T 51262-2017, Code for Cost Expert Determination of Construction Works.

Keywords

  • 逾期不答复视为认可
  • 竣工结算文件
  • 送审价结算
  • 法释〔2020〕25号第二十一条
  • 民法典第一百四十条
  • 沉默视为意思表示
  • GB/T 50500-2024 10.3.8
  • 住建部令第16号第十八条