Finality of a confirmed final account and subsequent price re-adjustment: principles, exceptions, and the audit/government fiscal review boundary
A final account confirmed by both parties' signatures and seals is in principle final: the employer may not demand re-checking (GB/T 50500-2024, Clause 10.3.12), neither party should claim for pre-settlement events (Clause 8.11.22), and a countersigned final account cannot be unilaterally overturned by either party (DB42/T 823-2021, Clause 8.1.5). Adjustable exceptions: a supplementary agreement by mutual consent, other statutory provisions, grounds for rescission of the final account, an express contractual provision that settlement is subject to the audit/government fiscal review conclusion, and post-settlement or mutually confirmed omissions. Audit and government fiscal review are administrative supervision and in principle cannot automatically overturn a confirmed final account, unless the contract expressly states that the audit/review conclusions govern.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.2.3、10.3.3、10.3.7、10.3.8、10.3.9、10.3.10、10.3.12、8.11.22条
- 住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条、第十九条
- 建设部令第107号《建筑工程施工发包与承包计价管理办法》第十六条(已废止,仅旧合同适用)
- DB42/T 823-2021 · Specification for Quality Control of Construction Cost Consulting (Hubei)
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第11.3.8条(已废止,沿革引用)
- 法释〔2020〕25号《建设工程施工合同司法解释(一)》第二十九、三十条
- 法释〔2026〕12号《建设工程施工合同司法解释(二)》第十一条、第十三条
- 法工备函〔2017〕22号、国法秘备函〔2017〕447号(不得以审计结果作为竣工结算依据的纠正函)
- https://www.court.gov.cn/zixun/xiangqing/282111.html
- https://www.court.gov.cn/zixun/xiangqing/504221.html
Topic Positioning
Answers whether the project price can be re-adjusted after the final account is completed: the finality of a confirmed final account, the adjustable exceptions, and the audit/government fiscal review boundary.
Core Conclusions
A final account confirmed by both parties' signatures and seals is in principle final: GB/T 50500-2024, Clause 10.3.12 forbids the employer from demanding re-checking; Clause 8.11.22 provides that, absent other contractual agreement, neither party should claim over pre-settlement events; DB42/T 823-2021, Clause 8.1.5 provides that once jointly signed off, neither party has the right to unilaterally overturn the final account. Adjustable exceptions: (1) a supplementary agreement by mutual consent; (2) other provisions of laws and regulations; (3) rescindable grounds such as major misunderstanding, obvious unfairness, or fraud; (4) an express contractual provision that settlement is subject to the audit/government fiscal review conclusion; (5) post-settlement warranty deductions and mutually confirmed omissions. Audit and government fiscal review are administrative supervision and cannot in themselves overturn a confirmed civil settlement (Supreme People's Court [2008] Min Yi Ta Zi No. 4), unless the contract expressly makes their conclusions the settlement basis.
Applicable Boundaries
Applies where the final account has completed the submit-check-recheck-confirm loop and been signed and sealed per Clauses 10.3.7-10.3.12; final accounts still being checked or re-checked, or deemed accepted due to the employer's overdue failure to check (Clause 10.3.8), are not yet confirmed-final and may still be objected to or adjusted. Rescission grounds are subject to the Civil Code's exclusion periods (e.g., 90 days for major misunderstanding); absent an "audit governs" clause, audit disallowances cannot unilaterally force adjustment of a confirmed price.
Further Reading
GB/T 50500-2024, Clauses 10.3.7-10.3.12, 8.11.22, Chapter 11; DB42/T 823-2021, Clauses 8.1.4-8.1.5; Ministry of Construction Order No. 107, Article 16; Supreme People's Court [2008] Min Yi Ta Zi No. 4; Fa Gong Bei Han [2017] No. 22; Guo Fa Mi Bei Han [2017] No. 447.
Keywords
- 竣工结算确认
- 终局效力
- 重复核对
- 重复审核
- deemed acceptance / deemed approval
- 结算协议效力
- 结算造价确认表
- 未经对方同意