Settlement subject to government audit conclusion clauses cannot delay settlement indefinitely—the relationship between audit supervision and civil settlement, backstop deadlines in the settlement procedure, and the judicial-appraisal countermeasure under Article 13 of SPC Interpretation II

No. Audit is administrative supervision, not a precondition of civil settlement; a "settlement subject to government audit conclusion" clause only determines the basis for settlement (what number), not the payment deadline (when). Procedural backstops: the employer's overdue failure to reply to or reconcile the final account documents is deemed acceptance (Order 107 Article 16: 28 days absent agreement; GB/T 50500-2024 Article 10.3.8); overdue failure to verify and to issue a payment certificate is deemed acceptance of the payment application (Article 10.3.16); disputes over additional works must not delay settlement of the works within the contract scope (Article 10.1.8). New countermeasure under Article 13 of SPC Interpretation [2026] No. 12: where the parties agree that the price is determined by audit or government fiscal review of project cost results but, for reasons not attributable to the contractor, the result is not issued within a reasonable period (determined by the court absent agreement, but not exceeding one year from the date the contractor submits the final account documents) or is manifestly inconsistent with the contract, the contractor may apply for a construction cost expert assessment (judicial appraisal); where no agreement to settle by audit results exists, the employer's request to determine the price by audit results will not be supported.

Applicable Codes

  • 中华人民共和国审计法(2021修正)第二十三条
  • 中华人民共和国审计法实施条例(2010修订)第二十条
  • 最高人民法院〔2008〕民一他字第4号答复
  • 法释〔2026〕12号 建设工程施工合同纠纷案件适用法律问题的解释(二)第十三条、第二十三条
  • 法释〔2020〕25号 建设工程施工合同纠纷案件适用法律问题的解释(一)第二十一条、第二十七条
  • 保障中小企业款项支付条例(2025修订,国务院令第802号)第十二条、第十四条、第三十一条、第三十三条 https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml
  • 住建部令第16号 建筑工程施工发包与承包计价管理办法 第十八条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第10.1.8、10.3.5、10.3.8、10.3.16条

Topic Positioning

Where the contract provides that settlement is subject to government audit conclusion or government fiscal review of project cost results, can the employer indefinitely delay settlement payment on the ground that "the audit is incomplete"? This card clarifies the relationship between audit supervision and civil settlement, sets out the backstop deadlines in the settlement procedure, and incorporates the new judicial-appraisal countermeasure under Article 13 of SPC Interpretation [2026] No. 12.

Core Conclusions

No. Audit is administrative supervision, not a statutory precondition of civil settlement: Article 23 of the Audit Law supervises the construction entity's fund management and does not directly bind employer-contractor settlement; the SPC [2008] Min-Yi-Ta-Zi No. 4 reply makes clear that government fiscal review of project cost does not affect the validity or performance of the contract—only an express contractual agreement makes the review conclusion the basis for settlement; Article 11 of the Regulation on Guaranteeing Payments to Small and Medium-sized Enterprises prohibits government agencies, public institutions and large state-owned enterprises from mandating settlement by audit results (unless otherwise agreed in the contract). Even where a valid "settlement subject to government audit conclusion" clause exists, it only determines "at what number settlement is made", not "when payment is made"—the payment obligation falls due as soon as the settlement conditions are satisfied. Procedural backstops: the employer's overdue failure to reply to or reconcile the final account documents is deemed acceptance of the contractor's documents (Order 107 Article 16—28 days absent agreement; GB/T 50500-2024 Article 10.3.8); overdue failure to verify and to issue a payment certificate is deemed acceptance of the payment application, payable at the declared amount (Article 10.3.16); disputes over additional works must not delay settlement of the works within the contract scope (Article 10.1.8). [Interpretation II Article 13 (effective 30 June 2026)] Where the employer and the contractor agree that the contract price is determined by the audit result of the audit authority or the review conclusion of the government fiscal review body: (1) if the audit result or review conclusion is not issued within a reasonable period for reasons not attributable to the contractor, or the contractor has evidence that it is manifestly inconsistent with the construction contract, the people's court shall grant the contractor's application for a construction cost expert assessment (judicial appraisal); (2) where no reasonable period is agreed, the court determines it comprehensively, but not exceeding one year from the date the contractor submits the final account documents; (3) where the parties did not agree to settle by audit results, the employer's request to determine the contract price by audit results will not be supported. This is the judicial countermeasure outlet for "settlement subject to government audit conclusion" clauses—where the audit is delayed beyond one year, the contractor may apply directly for a construction cost expert assessment (judicial appraisal) and is no longer held hostage by the audit conclusion; together with "overdue non-reply = deemed acceptance" (Fa Shi [2020] No. 25 Article 21), these are two weapons on the same front: where the contract contains a deemed-acceptance clause -> settle at the submitted price; where audit is agreed but delayed -> apply for appraisal to bypass the audit.

Applicable Boundaries

Applies to settlement disputes in government-invested and SOE-let scenarios. Where the contract expressly makes the audit conclusion the basis for settlement, the validity of that clause is still respected—this card negates only its "payment-delaying" effect. The contractor should serve the final account documents in writing and retain signed proof of receipt in order to start the backstop deadlines. Interpretation II Article 13 applies by time of case acceptance (first-instance construction contract disputes newly accepted by the people's courts after 30 June 2026); applying for a construction cost expert assessment (judicial appraisal) requires proof that the result was "not issued within a reasonable period for reasons not attributable to the contractor" or is "manifestly inconsistent with the construction contract"—the burden of proof lies on the contractor. Audit continues to operate as an administrative supervision procedure under the Audit Law—two separate tracks from civil settlement remedies.

Further Reading

Audit Law, Article 23; SPC [2008] Min-Yi-Ta-Zi No. 4 reply; Regulation on Guaranteeing Payments to Small and Medium-sized Enterprises, Article 11; MOHURD Order No. 107, Measures for the Pricing of Construction Contracting, Article 16; GB/T 50500-2024, Articles 10.1.8, 10.3.5, 10.3.8, 10.3.16; Fa Shi [2020] No. 25 Article 21 (overdue non-reply deemed acceptance); Fa Shi [2026] No. 12 Article 13—official full text on the SPC website https://www.court.gov.cn/zixun/xiangqing/504221.html and the SPC Civil Division I press briefing https://www.court.gov.cn/zixun/xiangqing/504201.html . For the article-by-article impact of Interpretation II on existing rules, see the referenced "Interpretation II impact map" card; for the deemed-acceptance rule itself, see the referenced settlement-acceptance card.

Keywords

Cited By