settlement subject to government audit conclusion
- 01
Determining the basis for settlement where the awarded contract fixes the price and a later supplementary agreement switches settlement to the conclusions of government audit or government fiscal review of project cost: sorting supplementary agreements into departure-type, procedural-type and closing-type, the exceptions that can be valid, and the effective reach of audit clauses
In principle the fixed price agreed in the awarded contract is the basis…
《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》法释〔2026〕12号 第十一条、第十三条、第二十三条(2026年6月30日施行)《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》法释〔2020〕25号 第二条、第十九条、第二十二条、第二十三条、第二十九条《中华人民共和国招标投标法》(主席令第86号,2017修正)第四十六条2026-10-29 - 02
The access rules and negative exclusions for a contractor's application for judicial expert assessment of the construction cost where the contract stipulates determination of the price by the government audit result or the government fiscal review conclusion, but that conclusion is manifestly inconsistent with the construction contract (or not issued within a reasonable period for reasons not attributable to the contractor) (Fa Shi [2026] No. 12, Article 13)
Yes, but what the contractor obtains is a right of access to judicial ex…
法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十三条、第二十三条法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十九条、第二十条、第二十一条、第二十九条最高人民法院〔2008〕民一他字第4号答复2026-10-29 - 03
Settlement subject to government audit conclusion clauses cannot delay settlement indefinitely—the relationship between audit supervision and civil settlement, backstop deadlines in the settlement procedure, and the judicial-appraisal countermeasure under Article 13 of SPC Interpretation II
No. Audit is administrative supervision, not a precondition of civil set…
中华人民共和国审计法(2021修正)第二十三条中华人民共和国审计法实施条例(2010修订)第二十条最高人民法院〔2008〕民一他字第4号答复2026-10-29 - 04
The overlap of the two routes of 'deemed approval of the submitted final account upon failure to reply in time' and 'applying for judicial construction cost expert assessment' when the employer delays the audit or the government fiscal review: comparison of requirements, whether both may be asserted, and how to plead primary and alternative claims
The two routes may be raised side by side but only as layered primary an…
法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第十三条法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第二十一条、第二十九条、第三十二条GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.8条2026-10-26 - 05
Fa Shi [2026] No. 12 "Construction Interpretation II" and its overall impact on existing judicial interpretations, statutes, and pricing/appraisal standards (23 articles, effective 30 June 2026)
The SPC "Interpretation (II) on the Application of Law in Cases of Const…
法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》——https://www.court.gov.cn/fabu/xiangqing/504221.html法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》《中华人民共和国招标投标法》第46、55、59条2026-09-25 - 06
Settlement review vs fiscal appraisal vs audit: subject, nature, object, and effect
The final account is a civil-contract act of employer and contractor (ch…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51095-2015 建设工程造价咨询规范最高人民法院〔2008〕民一他字第4号答复2026-09-25 - 07
Validity of "settlement per government audit results" clauses in government-invested projects, and drafting guardrails (deadlines / pricing basis / re-review / payment segregation)
The audit clause itself is valid: government fiscal review of project co…
最高法〔2008〕民一他字第4号答复《保障中小企业款项支付条例》第十一条《审计法》第二十三条2026-09-25