Reviewing the employer's defence of long-term refusal to pay the project price on the ground that 'the final account is not settled / review is not completed': whether the payment obligation has fallen due (Civil Code Articles 799, 577, 579), the three trigger points for interest on arrears (Fa Shi [2020] No. 25 Article 27), settlement at the submitted price requires an 'deemed approval upon failure to respond in time' agreement (Article 21), and the statutory cost of delay (the 18-month priority right, SME payment periods and overdue interest)

Refusal to pay cannot stand. The final account is only the procedure that fixes 'how much is payable'; it is not the condition on which the payment obligation arises: once the works pass completion acceptance, the payment obligation has fallen due, and for works actually delivered, interest on the arrears runs from the date of delivery (Fa Shi [2020] No. 25 Article 27); the employer may not indefinitely defer payment on the ground of its own delay in settling. But 'cannot refuse payment' does not mean 'pay the submitted price': only where the contract expressly agrees that 'failure to respond within the agreed period after receipt of the final account documents is deemed approval' may settlement be made at the contractor's submitted price (Article 21); absent such an agreement, the cost is determined through judicial assessment; and clauses making the price 'subject to audit / government fiscal review' cannot drag on indefinitely either -- where the conclusion is not issued within a reasonable period for reasons not attributable to the contractor (no more than one year from submission of the final account documents) or obviously contradicts the contract, judicial assessment may be applied for (Fa Shi [2026] No. 12 Article 13).

Applicable Codes

  • 《中华人民共和国民法典》第799条、第807条、第577条、第579条、第159条
  • 法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第21条、第26条、第27条、第41条(2021年1月1日施行)
  • 法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第13条、第21条、第23条(2026年6月30日施行)
  • 住建部令第16号 建筑工程施工发包与承包计价管理办法 第十八条、第十九条、第二十七条(2014年2月1日施行)
  • GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.8、10.3.16、10.3.17条
  • 国务院令第802号 保障中小企业款项支付条例(2025修订)第9、10、12、14、15、17、31条(2025年6月1日施行)
  • https://www.court.gov.cn/fabu/xiangqing/504221.html
  • https://www.court.gov.cn/zixun/xiangqing/282111.html
  • https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml
  • https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_2006185954536067072.html
  • https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_1946029306944364544.html
  • http://zjt.shandong.gov.cn/art/2025/8/28/art_119936_10348905.html
  • http://zjt.shandong.gov.cn/art/2026/7/24/art_102884_10354808.html?xxgkhide=1
  • https://jst.zj.gov.cn/col/col1229129246/art/2025/art_8ea56a6732b71198c56d8ba6e5713d1e.html

Topic Positioning

After receiving the final account documents, the employer neither checks them nor responds, and refuses payment long-term on the ground that 'settlement is unfinished'. Does that defence stand? This card splits the question into three layers -- whether the payment obligation has fallen due, whether the amount can follow the submitted price, and what delay costs -- and gives directly citable provisions and criteria.

Core Conclusions

1. Payment obligation layer: refusal does not stand

  • Civil Code Article 799: 'On completion of the construction project, the employer shall timely organize acceptance according to the construction drawings and descriptions and the state-issued construction acceptance specifications and quality inspection standards. Where acceptance is passed, the employer shall pay the price as agreed and take over the project.' The condition giving rise to the payment obligation is passing acceptance, not completion of settlement.
  • Civil Code Article 577: a party that fails to perform its contractual obligations or performs them inconsistently with the agreement bears liability for breach including continued performance, remedial measures or compensation; Article 579: where a party fails to pay a price, remuneration, rent or interest, or fails to perform its other monetary obligations, the other party may demand payment.
  • Interest accrual (Fa Shi [2020] No. 25 Article 27): 'Interest is computed from the date the project price becomes payable. Where the parties have no agreement on the time of payment, or the agreement is unclear, the following times are the payable dates: (1) where the construction project has been actually delivered, the date of delivery; (2) where the construction project has not been delivered, the date of submission of the final account documents; (3) where the construction project is not delivered and the project price is not settled, the date on which the parties file the action.'
  • Interest standard (Article 26 of the same interpretation): 'Where the parties have agreed on the standard for computing interest on the unpaid project price, the agreement governs. Absent agreement, interest accrues at the loan rate of the same type and period, or at the Loan Prime Rate of the same period.'
  • Conclusion: delaying settlement does not push back the interest start date -- where the works have been delivered, interest runs from the delivery date, not from the date the settlement is confirmed.

2. Settlement amount layer: no agreement does not mean paying the submitted price

  • Fa Shi [2020] No. 25 Article 21: 'Where the parties agree that the employer's failure to respond within the agreed period after receiving the final account documents constitutes approval of the final account documents, the matter is handled under the agreement. Where the contractor requests that the project price be settled per the final account documents, the people's court supports it.' The requirement is an 'agreement of the parties'; 'deemed approval' operating at the level of departmental rules or pricing standards cannot alone replace a contract agreement.
  • The pricing standard runs in the same direction: GB/T 50500-2024 Article 10.3.8 'where the employer, within the agreed time after receiving the contractor's final account documents, neither checks the final account as agreed nor raises checking comments, the final account documents submitted by the contractor are deemed approved by the employer and the final account is confirmed as complete'; Article 10.3.16 'where the employer, after receiving the contractor's application for payment of the final account price, neither verifies it within the prescribed time nor issues the final account payment certificate to the contractor, the contractor's application for payment of the final account price is deemed approved by the employer', and the listed amount is payable within the prescribed time; Article 10.3.17 'where the employer fails to pay the final account price as agreed, the contractor may demand payment and may claim against the employer under Article 8.11.9 of this standard'. GB/T 50500-2024 is a recommended national standard; it becomes a contractual obligation only through incorporation by the contract.
  • Departmental rules: MOHURD Order No. 16, Measures for the Administration of Pricing in the Awarding and Contracting of Construction Works, Article 18(2) -- where the awarding party fails to respond within the agreed period after receiving the final account documents, 'the matter is handled under the contract; where the contract is silent, the final account documents are deemed approved'; the final paragraph of that article: on the period, 'absent an express agreement, the relevant state provisions govern; where the state has none, the agreed period is taken as 28 days'. Article 19: final account documents confirmed by the signatures of both parties serve as the basis for the project's final financial settlement, 'neither party may, without the other party's consent, entrust a construction cost consultancy to review again the final account documents already effective', and the awarding party shall timely pay the final account price.
  • Repeal warning: the former Ministry of Construction Order No. 107 was expressly repealed by Article 27 of MOHURD Order No. 16 ('These Measures take effect on 1 February 2014. The Measures for the Administration of Pricing in the Awarding and Contracting of Construction Works issued by the former Ministry of Construction on 5 November 2001 (Ministry of Construction Order No. 107) are repealed at the same time.'); when citing the departmental-rule basis of 'deemed approval', no longer cite Article 16 of Order No. 107.

3. Delay-cost layer: delay does not mean exemption

  • Priority of payment: Fa Shi [2020] No. 25 Article 41, 'the contractor shall exercise its priority of payment out of the construction project price within a reasonable period, not exceeding 18 months at most, from the date the employer ought to pay the construction project price'; Civil Code Article 807: where the employer fails to pay the price as agreed, the contractor may demand payment within a reasonable period and, failing payment, may -- unless the nature of the construction project makes discount or auction unsuitable -- agree with the employer to discount the project, or petition the people's court to auction it under law, and the price of the construction project enjoys priority of payment out of the proceeds of the discount or auction.
  • Refinement of the start date (Fa Shi [2026] No. 12 Article 21): where the contract fixes the payable date and the date of payment is varied by agreement for objective reasons such as an extension of time, the period runs from the varied payable date; where no date is agreed or the agreement is unclear but the settlement agreement expressly fixes the payable date, the period runs from that date.
  • Audit / government fiscal review clauses (Fa Shi [2026] No. 12 Article 13): where the price is agreed to be determined by the audit conclusion or the review conclusion, but the conclusion is not issued within a reasonable period for reasons not attributable to the contractor, or the contractor has evidence proving it obviously contradicts the contract, the contractor's application for judicial assessment of the construction cost is permitted by the people's court; the reasonable period follows any agreement, failing which the court fixes it comprehensively by the scale of the works, the cost amount and the complexity, 'not exceeding one year from the contractor's submission of the final account documents'; where the price was not agreed to be determined by the audit result, the employer's request to determine the project price by the audit result or review conclusion is not supported. Article 12 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises: government organs, public institutions and state-owned large enterprises shall not compel acceptance of the audit organ's audit result as the settlement basis, except where laws or administrative regulations provide otherwise.
  • Hard SME payment periods (State Council Order No. 802, 2025 revision, effective 1 June 2025): Article 9 -- government organs and public institutions pay within 30 days of delivery of the goods, works or services, and a contractual agreement may extend this to no more than 60 days at most; large enterprises pay within 60 days and may not agree to condition payment on receipt of a third-party payment or to pay proportionally to a third party's payment progress; with progress settlement or periodic settlement, the payment period runs from the date both parties confirm the settled amount. Article 10 -- where payment is conditioned on passing acceptance, the period runs from the date of passing acceptance; where acceptance is delayed, from expiry of the agreed acceptance period. Article 14 -- no refusal or delay of payment on the ground of a change of the legal representative or principal responsible person or the running of internal payment processes, or, where the contract is silent, on the ground of awaiting completion-acceptance filing or the final-account audit. Article 15 -- where part is disputed but the other parts can be performed, the undisputed parts are paid timely. Article 17 -- overdue interest: the agreed rate may not be lower than the 1-year Loan Prime Rate at the time of contract conclusion; absent agreement, 0.05% per day. Article 31 -- lists failure to pay within the periods, delayed acceptance, and delay by internal processes or the final-account audit: the superior organ or supervisory department orders correction; on refusal to correct, the responsible leaders and directly liable personnel are sanctioned under law.

4. Scenario x conclusion table

Scenario Can payment be refused / conclusion Basis
Completion acceptance passed and the works actually delivered; refusal on 'settlement unfinished' No; interest from the delivery date Civil Code 799; Fa Shi [2020] No. 25 Art. 27(1)
Contract expressly agrees 'failure to respond within the agreed period after receipt of the final account documents is deemed approval' No; settle at the submitted price Fa Shi [2020] No. 25 Art. 21
Contract adopts GB/T 50500-2024; no checking, no comments in time No; the final account documents are deemed approved GB/T 50500-2024 10.3.8; MOHURD Order No. 16 Art. 18(2)
Settlement confirmed or payment certificate issued, still unpaid No; payment may be demanded and a claim made GB/T 50500-2024 10.3.16, 10.3.17; MOHURD Order No. 16 Art. 19
No 'deemed approval' agreement; the submitted price claimed on departmental rules alone The amount cannot simply follow the submitted price; refer to judicial assessment Fa Shi [2020] No. 25 Art. 21 (requires an 'agreement of the parties')
Price agreed subject to audit / government fiscal review, long unissued No indefinite delay; beyond the one-year reasonable period or on obvious contradiction, assessment may be sought Fa Shi [2026] No. 12 Art. 13
Employer is a government organ, public institution or large enterprise; counterparty an SME Pay within 30 days (up to 60 by agreement) / 60 days; undisputed parts first State Council Order No. 802 Arts. 9, 14, 15
Final account documents not served or incomplete The response period has not started; 'failure to respond in time' fails; payment may be deferred Fa Shi [2020] No. 25 Art. 21 elements; MOHURD Order No. 16 Art. 18
Quality failed and repair refused / acceptance not passed The payment condition is unmet; the corresponding price may be withheld Civil Code Art. 799
Contract expressly conditions payment on 'payment after settlement review and confirmation' and the condition failed for reasons not attributable to the employer Payment may be deferred; but where the employer improperly prevents the condition for its own benefit, the condition is deemed fulfilled Civil Code Art. 159; Fa Shi [2026] No. 12 Art. 13

Boundaries of Application

  • 'No refusal' resolves only whether the obligation is due, not the amount: absent an agreement that 'failure to respond in time is deemed approval', most rulings still refer the cost to judicial assessment, and the chance of full support of the submitted price drops markedly.
  • Claiming 'deemed approval' requires all of: works quality passed (acceptance passed, or premature use of the works without taking-over), the final account documents served and complete, and no response within the agreed or default period (28 days absent agreement); service and the list of documents must be evidenced, or the response period does not start.
  • A deferral defence stands only where the contract genuinely conditions payment on settlement review / government fiscal review and the condition failed without obstruction by the employer; obstruction is assessed under Civil Code Article 159 (where a party improperly prevents a condition from being fulfilled for its own benefit, the condition is deemed fulfilled; where it improperly procures fulfilment, the condition is deemed unfulfilled).
  • Time effect: Fa Shi [2026] No. 12 Article 23 -- 'This Interpretation takes effect on 30 June 2026. It applies to first-instance construction contract dispute cases newly accepted by the people's courts after its entry into effect. Where judicial interpretations previously issued by the Supreme People's Court conflict with this Interpretation after its entry into effect, this Interpretation prevails.' First-instance cases newly accepted after 30 June 2026 therefore follow Interpretation (II); cases accepted earlier still follow Fa Shi [2020] No. 25. The 2025 revision of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises took effect on 1 June 2025 (State Council Order No. 802, revised and promulgated 17 March 2025); article numbers of the former Order No. 728 must be converted when cited.
  • Terminology cross-check: Civil Code Articles 799, 807, 577, 579, 159; Fa Shi [2020] No. 25 Articles 21, 26, 27, 41; Fa Shi [2026] No. 12 Articles 13, 21, 23; MOHURD Order No. 16 Articles 18, 19, 27; GB/T 50500-2024 Articles 10.3.8, 10.3.16, 10.3.17; State Council Order No. 802 Articles 9, 10, 12, 14, 15, 17, 31.