When interest on unpaid project payments starts accruing — agreement first, plus three "deemed payable date" nodes

Interest runs from the date the project price becomes payable: where the contract expressly states payment dates, they govern (the start day itself excluded, accruing from the next day); absent or unclear agreement: for delivered works, from delivery; undelivered, from the contractor's submission of the final account documents; neither delivered nor settled, from the date of suit (Fa Shi [2020] No. 25, Article 27, continuing Fa Shi [2004] No. 14, Article 18 — long consistent in judicial practice). Supporting: overdue non-response to settlement documents is deemed acceptance (Order No. 107, Article 16; 28 days absent agreement); for late payment by government agencies/public institutions/large enterprises to SMEs, the agreed rate may not be below the 1-year LPR at contract conclusion, and absent agreement 0.05% per day (Decree No. 728, Article 15).

Applicable Codes

  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第9条、第26条、第27条、第41条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号,2026年6月30日施行)第21条、第23条,https://www.court.gov.cn/fabu/xiangqing/504221.html
  • 《保障中小企业款项支付条例》(2025修订,国务院令第802号,2025年6月1日施行)第9条、第10条、第14条、第15条、第17条,https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml
  • 《中华人民共和国民法典》第201条、第799条、第807条、第188条、第195条
  • 《中华人民共和国民事诉讼法》(2023修正)第123条
  • 住建部令第16号《建筑工程施工发包与承包计价管理办法》第18条、第19条
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.3.8条

Topic Positioning

The starting point of interest on unpaid project payments: agreement first, with three "deemed payable date" nodes absent agreement, plus the interest-rate calibers.

Core Conclusions

  1. Agreement first: with expressly agreed payment dates, interest accrues from the day after the agreed payable date, the start day excluded (Civil Code, Article 201).
  2. Three nodes absent or unclear agreement (Fa Shi [2020] No. 25, Article 27, continuing Fa Shi [2004] No. 14, Article 18; consistent judicial practice; original text to be verified): actually delivered -> from delivery; undelivered -> from the contractor's submission of the final account documents; undelivered and unsettled -> from the date of suit.
  3. Interface: after the settlement documents are submitted within the period (28 days absent agreement), the employer's overdue non-response is deemed acceptance (Order No. 107, Article 16; GB/T 50500-2024, Clause 10.3.8) — the submission date is the accrual start.
  4. Rates: for late payment by government agencies/public institutions/large enterprises to SMEs, the agreed rate may not be below the 1-year LPR, absent agreement 0.05% per day (State Council Decree No. 728, Article 15).

Applicable Boundaries

Resolves only the starting point — rates follow agreement or the regulations; the node rules apply absent or unclear agreement; advance-funding interest and other special agreements are excluded.

Further Reading

Fa Shi [2020] No. 25, Article 27 (formerly Fa Shi [2004] No. 14, Article 18); Decree No. 728, Article 15; Civil Code, Article 201; Ministry of Construction Order No. 107, Article 16; GB/T 50500-2024, Clauses 10.3.8, 10.3.16, 3.3.4; T/YJXB 0001-2023, Clause 5.0.13.