When interest on unpaid project payments starts accruing — agreement first, plus three "deemed payable date" nodes
Interest runs from the date the project price becomes payable: where the contract expressly states payment dates, they govern (the start day itself excluded, accruing from the next day); absent or unclear agreement: for delivered works, from delivery; undelivered, from the contractor's submission of the final account documents; neither delivered nor settled, from the date of suit (Fa Shi [2020] No. 25, Article 27, continuing Fa Shi [2004] No. 14, Article 18 — long consistent in judicial practice). Supporting: overdue non-response to settlement documents is deemed acceptance (Order No. 107, Article 16; 28 days absent agreement); for late payment by government agencies/public institutions/large enterprises to SMEs, the agreed rate may not be below the 1-year LPR at contract conclusion, and absent agreement 0.05% per day (Decree No. 728, Article 15).
Applicable Codes
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第9条、第26条、第27条、第41条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号,2026年6月30日施行)第21条、第23条,https://www.court.gov.cn/fabu/xiangqing/504221.html
- 《保障中小企业款项支付条例》(2025修订,国务院令第802号,2025年6月1日施行)第9条、第10条、第14条、第15条、第17条,https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml
- 《中华人民共和国民法典》第201条、第799条、第807条、第188条、第195条
- 《中华人民共和国民事诉讼法》(2023修正)第123条
- 住建部令第16号《建筑工程施工发包与承包计价管理办法》第18条、第19条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.3.8条
Topic Positioning
The starting point of interest on unpaid project payments: agreement first, with three "deemed payable date" nodes absent agreement, plus the interest-rate calibers.
Core Conclusions
- Agreement first: with expressly agreed payment dates, interest accrues from the day after the agreed payable date, the start day excluded (Civil Code, Article 201).
- Three nodes absent or unclear agreement (Fa Shi [2020] No. 25, Article 27, continuing Fa Shi [2004] No. 14, Article 18; consistent judicial practice; original text to be verified): actually delivered -> from delivery; undelivered -> from the contractor's submission of the final account documents; undelivered and unsettled -> from the date of suit.
- Interface: after the settlement documents are submitted within the period (28 days absent agreement), the employer's overdue non-response is deemed acceptance (Order No. 107, Article 16; GB/T 50500-2024, Clause 10.3.8) — the submission date is the accrual start.
- Rates: for late payment by government agencies/public institutions/large enterprises to SMEs, the agreed rate may not be below the 1-year LPR, absent agreement 0.05% per day (State Council Decree No. 728, Article 15).
Applicable Boundaries
Resolves only the starting point — rates follow agreement or the regulations; the node rules apply absent or unclear agreement; advance-funding interest and other special agreements are excluded.
Further Reading
Fa Shi [2020] No. 25, Article 27 (formerly Fa Shi [2004] No. 14, Article 18); Decree No. 728, Article 15; Civil Code, Article 201; Ministry of Construction Order No. 107, Article 16; GB/T 50500-2024, Clauses 10.3.8, 10.3.16, 3.3.4; T/YJXB 0001-2023, Clause 5.0.13.
Keywords
- 工程款利息起算
- 应付款之日
- 视为应付款时间
- 法释〔2020〕25号第二十七条
- 提交竣工结算文件之日
- 逾期付款利息
- Regulation on Ensuring Payment to Small and Medium-sized Enterprises
- 法释〔2026〕12号第二十一条
Related Cards
- →
Start point of the exercise period (18 months at most) of the contractor's priority right to payment for construction works - determining 'the date the project price ought to be paid': where the payment date was varied by agreement due to objective causes, take the varied date; where a settlement agreement expressly fixes the date, take that date (Fa Shi [2026] No. 12, Article 21); where neither exists, the three presumptions of Article 27 of Fa Shi [2020] No. 25, and the effective-date threshold of Article 23
The exercise period of the priority right is 18 months at most, running from 'the date the project price ought to be paid', with the start point determined in sequence: (1) where the payment date agreed in the contract was varied by agreement for objective causes such as extension of time, take the varied date (Fa Shi [2026] No. 12, Article 21, paragraph 1); (2) where the contract is silent or unclear but the settlement agreement expressly fixes the payment date, take that date (Article 21, paragraph 2); (3) where neither exists, presume under Article 27 of Fa Shi [2020] No. 25: works delivered - the date of delivery; not delivered - the date of submitting the final account documents; neither delivered nor settled - the date of filing suit. Article 21 settles only the start point and does not alter the 18-month length of the period; the interpretation took effect on 30 June 2026 and applies to first-instance cases newly accepted after that date.
- →
Works put into use before completion acceptance: payment, quality liability and warranty rules (the employer's unauthorized use deemed acceptance of quality)
The employer's unauthorized use of un-accepted works equals deemed acceptance of quality (presumed qualification): the project price remains payable, with the date of transfer of possession serving as the completion date and the payment due date (interest at the 1-year LPR absent an agreed rate); quality risk passes to the employer except for foundations and the main structure (for which the contractor remains liable within the reasonable service life), and only for the parts actually used; warranty duties are not discharged - minimum warranty periods per Article 40 of the Regulations on Quality Management of Construction Works (waterproofing 5 years; heating and cooling 2 heating/cooling seasons; electrical wiring, water supply and drainage piping, equipment installation and finishing 2 years; foundations and main structure, the reasonable design life); the employer additionally bears an administrative fine of 2%-4% of the contract price (Article 58).
- →
Whether the employer's overdue non-reply to the final account documents is deemed acceptance of the submitted amount - the three-requirement test of Fa Shi [2020] No. 25, Article 21, and interface with GB/T 50500-2024
Where the contract stipulates 'overdue non-reply is deemed acceptance', under Fa Shi [2020] No. 25, Article 21, the people's court shall support the contractor's claim for settlement per the final account documents (submitted price); three requirements must be met simultaneously: an express contractual stipulation, delivery of complete settlement documents, and no reply within the agreed period. Absent such stipulation, claims based only on ministerial rules or model contract texts containing 'deemed acceptance' wording are not supported by the SPC and the overwhelming majority of courts. GB/T 50500-2024, Clause 10.3.8, points the same way but is a recommendatory national standard that becomes a contractual obligation only when incorporated by the contract; at the rule level, Article 16 of the former MOC Decree No. 107 has been carried over by Article 18 of MOHURD Decree No. 16, with 28 days as the default period absent agreement.
- →
Payment time limits under the 2025 revision of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises: 30 days (60 days at most) for state organs and public institutions, 60 days for large enterprises, when the period starts (acceptance and settlement), the ban on back-to-back clauses, the four permitted securities, and interest on overdue payment (1-year LPR floor / 0.05% per day)
Under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): where state organs and public institutions procure works and the like from small and medium-sized enterprises, payment must be made within 30 days from delivery, and any contractual agreement may not extend the limit beyond 60 days; large enterprises must pay within 60 days and may agree periods reasonably per industry norms, but may not make payment conditional on receipt of third-party payment; where payment is by progress or periodic settlement, the payment period runs from the date the parties confirm the settled amount, and where acceptance is a payment condition, from the date of passing acceptance - or, where acceptance is delayed, from the expiry of the agreed acceptance period. Late payment attracts interest on overdue payment: an agreed rate may not be lower than the 1-year LPR at the time of contracting; absent agreement, 0.05% per day.
- →
Checklist of payment compliance obligations under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): 30-day and 60-day-maximum payment terms for state organs and public institutions and 60-day terms for large enterprises, and the starting points of those terms; prohibition of third-party payment conditions; delayed acceptance treated as expiry of the term; prohibition of compulsory commercial bills of exchange; no compelling use of audit conclusions as the settlement basis; security limited to four types and not restricted to cash; overdue interest at 0.05% per day; payment of undisputed portions first; and information disclosure requirements
State organs and public institutions must pay within 30 days of delivery of the goods, works or services, and where the contract provides otherwise, the term may never exceed 60 days; large enterprises must pay within 60 days and may not agree that receipt of payment from a third party is a condition of payment, nor pay SMEs in proportion to the progress of a third party's payment (Article 9). The payment term runs from the date of passing inspection or acceptance, or from the date the parties confirm the settlement amount under progress-based or periodic settlement; where a state organ, public institution or large enterprise delays inspection or acceptance, the term runs from the expiry of the agreed inspection or acceptance period (Article 10). The agreed overdue interest rate may not be lower than the 1-year LPR at the time of conclusion of the contract; failing agreement, interest accrues at 0.05% per day (Article 17). In project construction only four types of security may be collected - tender security, performance security, works quality retention money and migrant worker wage security - and they may not be restricted to cash; guarantee letters from financial institutions must be accepted (Article 13); state organs, public institutions and state-owned large enterprises must not compel the use of the audit authority's audit conclusion as the basis for settlement (Article 12).
- →
Validity of 'back-to-back' clauses by which a large enterprise and an SME agree that 'payment is conditional on receipt of payment from a third party (the owner)' or that 'payment is made in proportion to the owner's payment progress' (void); handling of the payment period and overdue interest after nullity (three-step determination of the period + the 60-day / 30-day benchmarks and starting points under Article 9 of the Regulation + Article 27 of Fa Shi [2020] No. 25 on the starting point of interest + Article 21 of Fa Shi [2026] No. 12 on the starting-point rule); and the boundaries of applicable parties and temporal effect
Void (nullity is limited to that clause). Under Article 1 of Fa Shi [2024] No. 11, where a large enterprise agrees with an SME in construction, goods procurement or services that receipt of third-party payment is the precondition of payment, the clause violates Articles 6 and 8 of the Regulation on Ensuring Payment to SMEs (Articles 7 and 9 after the 2025 revision) and is void under Article 153(1) of the Civil Code; 'payment in proportion to the owner's payment' and disguised formulations are equally void. After nullity the original payment period is treated as not agreed: first a supplementary agreement; failing that, the period is reasonably determined under Article 510 of the Civil Code and Article 2 of the Reply, by reference to industry norms and trade usage (direct application of item 4 of Article 511, 'performance at any time', is inappropriate), with the statutory day counts of Article 9 of the Regulation as the benchmark - large enterprises 60 days from delivery, government agencies and public institutions 30 days (agreed periods capped at 60 days), counted from the date of delivery / passing acceptance (delayed acceptance: from expiry of the agreed acceptance period) / confirmation of the settled amount by both parties. Interest: as agreed if agreed; if the agreement is unlawful or absent, at the one-year LPR (Article 2 of the Reply); Article 17 of the Regulation separately provides that the agreed rate shall not be lower than the one-year LPR at the time of conclusion and that, absent agreement, 0.05% per day applies. Interest runs from the date the works price falls due; where the payment time is not agreed or is unclear, it is determined under the three situations of Article 27 of Fa Shi [2020] No. 25.
Cited By
- ←
Assessment and remedies once the 18-month period of the construction payment priority has run out: nature of the period and the layered consequences of expiry, back-solving the accrual date to rescue the claim, the differing effects of a written demand on the peremptory period versus the 3-year limitation period, and correction of the outdated from-completion six-month local position
Where 19 months have passed since 'the date the employer ought to pay for the works', absent an agreed variation of the payment date or a settlement agreement fixing another date, the 18-month period under Article 41 of Fa Shi [2020] No. 25 (a peremptory period - no interruption, suspension or extension) has expired, the priority right is extinguished and no priority claim can be made out of the discount or auction proceeds; but the principal debt survives and its 3-year limitation period (Article 188 of the Civil Code) is far from expiring - suit for the principal, interest and liquidated damages remains available, only demoted to an ordinary claim. A written demand cannot stretch the 18 months but constitutes 'a demand for performance made to the obligor' under Article 195(1) of the Civil Code, interrupting the 3-year period and fixing the accrual facts. Note also: 'the date of completion' is not the accrual point under the current position (that was the six-month local rule in Article 14 of the Jiangsu High Court's 2018 answers).
- ←
After a back-to-back clause (payment conditioned on receipt of third-party payment) is held invalid: the start date and rate of interest on works payments owed to SMEs - the order for fixing a reasonable payment period (supplementary agreement -> industry norms / trade usage -> the 60-day benchmark of the Regulation), a scenario table of the date payment falls due (delivery date / settlement confirmation date / acceptance date / the three fallback tests), rate standards (agreed rate not below the 1-year LPR at contracting; without agreement, 1-year LPR or 0.05% per day), and the boundary of stacking liquidated damages with doubled delayed-performance interest at the enforcement stage
Interest runs neither from the date the employer actually pays nor from the date of signing, but from the day after expiry of the reasonable payment period re-determined under Article 2 of the Reply after the clause is invalidated; the most direct industry yardstick for the reasonable period is Article 9, paragraph 2 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (State Council Decree No. 802) - a large enterprise pays within 60 days of delivery; for progress or periodic settlement, the period runs from the date both parties confirm the settled amount; where acceptance is agreed as a payment condition, from the date acceptance passes (delayed acceptance: from expiry of the agreed acceptance period); only where none of these applies does it fall to the three fallback tests of Fa Shi [2020] No. 25, Article 27 (delivery date / date of submitting the final account documents / date of suit). Rate: as agreed if agreed, but not below the 1-year LPR at the time of contracting (Regulation, Article 17); where the agreement is unlawful or absent, interest accrues at the one-year LPR published by the National Interbank Funding Center (Fa Shi [2024] No. 11, Article 2); the Regulation, Article 17 separately provides 0.05% per day where nothing is agreed. For the same overdue period, liquidated damages and overdue interest are not double-counted; but after the case enters enforcement, the overdue interest determined by judgment and the doubled debt interest for the delayed-performance period can coexist (Civil Procedure Law Article 264).
- ←
Independence of the employer's payment obligation where fiscal funds for a government-invested project are not disbursed in place: the fiscal appropriation relationship is not a payment condition; funds must be secured in place and contractors must not be required to advance financing (Articles 19, 22 and 34 of the Government Investment Regulation; Article 8 of the SME Payment Regulation, State Council Order No. 802); validity grading of pay-after-appropriation clauses (30 days, 60-day maximum, for state organs and public institutions; large enterprises must not condition payment on third-party payment; invalidity under Fa Shi [2024] No. 11; fiction of condition fulfilment under Articles 153 and 159 of the Civil Code); audit and fiscal review fix only the settlement amount, not the payment date; interest accrual and demand documentation
Payment can be demanded. Non-disbursement of fiscal funds is a budget-appropriation relationship between the employer and the finance authority, not a payment condition or an exemption vis-a-vis the contractor: the payment obligation arises from acceptable completion and the contract (Articles 799, 579 and 465 of the Civil Code). Article 19 of the Government Investment Regulation requires the finance department to disburse 'promptly and in full', Article 22 requires funds to be secured in place and prohibits building on contractor advance financing, and Article 34(5) lists requiring the contractor to advance financing for a government-invested project among the sanctionable scenarios, so proceeding while the funds are absent is itself the employer's violation. As to pay-after-appropriation clauses: where the contractor is a small or medium enterprise and the employer is a state organ or public institution, payment is due within 30 days of delivery, extendable by agreement to no more than 60 days (Article 9(1) of the Order No. 802 Regulation); where the employer is a large enterprise, clauses conditioning payment on receipt of third-party payment or paying in proportion to third-party receipts are void (Article 1 of Fa Shi [2024] No. 11; Article 153(1) of the Civil Code), and a condition long obstructed may be deemed fulfilled under Article 159. Audit or fiscal review only decides how much to settle, not when to pay. Interest runs from the date the payment falls due (Article 27 of Fa Shi [2020] No. 25); absent an agreed rate, the loan prime rate applies (Article 26) or 0.05% per day (Article 17 of the Order No. 802 Regulation).
- ←
After termination of the construction contract, the boundary of the payment defence for parts of the works the employer has actually taken over and put to use (without completion acceptance): a blanket refusal to pay on the ground of 'not accepted' is barred; refusal is allowed only 'to the corresponding extent' for undelivered parts and for foundation and main structure defects; repair costs require prior notice of repair
No blanket refusal. Termination only ends the unperformed part; for completed works of acceptable quality the corresponding price is still payable as agreed (Civil Code Article 806(3)); where the employer makes premature use of parts not accepted, the date of taking over possession of the works is the completion date (Fa Shi [2020] No. 25, Article 9(iii)), and later claims on the ground that 'the quality of the used part does not conform to the agreement' are not supported (Article 14 of the same interpretation, excepting the foundation and the main structure). Refusal of payment is limited to: parts not delivered for use, foundation and main structure defects of used parts, and repair costs where repair was requested but still not carried out; and under Civil Code Article 526 only the 'corresponding' request for performance may be refused, not the whole price held back; retention money may be reserved on the base of the price of the works payable to the contractor (Fa Shi [2026] No. 12, Article 14).
- ←
Whether the contractor may claim the works price where the works are in use but completion taking-over was not obtained: maturity of the payment obligation (Fa Shi [2020] No. 25 Article 9(3), transfer of possession deemed completion; Article 14 cutting off the quality defence) and determination of the amount (Article 27 deemed due dates, Article 21 the submitted price, GB/T 50500-2024 Clause 10.3.14 final account proceeds, retention deducted), the situations barring the claim (Civil Code Articles 799 and 793(2)) and the cut-over point of the 2026 Interpretation (II)
The claim lies and the payment obligation is already due: where the works, not having undergone completion taking-over, are used by the employer without authorisation, the date of transfer of possession is the date of completion under Fa Shi [2020] No. 25 Article 9(3), the contractually agreed payment condition thereby matures, and the employer's defences of 'not taken over' or 'the used part does not conform to the agreed quality' fail under Article 14; yet maturity of the obligation does not mean the amount fixes itself - settlement still runs under the contract (with a 'failure to answer in time deemed approval' clause, settlement on the submitted price under Article 21; otherwise review or appraisal), retention money is withheld, and liability for foundations and the main structure is not discharged. Where the works are neither delivered nor taken over and quality fails (Civil Code Article 799), or the contract is void and the works still fail after remedial work (Article 793(2)), payment as agreed cannot be claimed.
- ←
Interest, liquidated damages and damages for late payment of the project price do not enjoy the contractor's priority right of payment out of the works - the scope locked by the composition of the project price, separating principal and interest in blended settlements, and 'agreement cannot expand the statutory priority scope'
Not included. The scope of the priority right is confined to the project price itself: Article 40(1) of Fa Shi [2020] No. 25 provides that the scope 'is determined under the provisions of the relevant administrative department of the State Council on the scope of construction project prices', and paragraph 2 states expressly that 'where the contractor claims priority for interest, liquidated damages or damages arising from late payment of the construction project price, the people's court will not support the claim'. The interest claim itself stands and may be sued for (the rate follows Article 26 of the same interpretation, the start date Article 27), but only as an ordinary claim, without priority over mortgages or other claims; Article 17 of the 2026 Interpretation (II) (Fa Shi [2026] No. 12) further requires the court to ascertain and 'state in the operative part of the judgment' the amount of project price enjoying the priority right and the corresponding works, and paragraph 2 restates that suspension and idle-resource losses are not supported.
- ←
Reviewing the employer's defence of long-term refusal to pay the project price on the ground that 'the final account is not settled / review is not completed': whether the payment obligation has fallen due (Civil Code Articles 799, 577, 579), the three trigger points for interest on arrears (Fa Shi [2020] No. 25 Article 27), settlement at the submitted price requires an 'deemed approval upon failure to respond in time' agreement (Article 21), and the statutory cost of delay (the 18-month priority right, SME payment periods and overdue interest)
Refusal to pay cannot stand. The final account is only the procedure that fixes 'how much is payable'; it is not the condition on which the payment obligation arises: once the works pass completion acceptance, the payment obligation has fallen due, and for works actually delivered, interest on the arrears runs from the date of delivery (Fa Shi [2020] No. 25 Article 27); the employer may not indefinitely defer payment on the ground of its own delay in settling. But 'cannot refuse payment' does not mean 'pay the submitted price': only where the contract expressly agrees that 'failure to respond within the agreed period after receipt of the final account documents is deemed approval' may settlement be made at the contractor's submitted price (Article 21); absent such an agreement, the cost is determined through judicial assessment; and clauses making the price 'subject to audit / government fiscal review' cannot drag on indefinitely either -- where the conclusion is not issued within a reasonable period for reasons not attributable to the contractor (no more than one year from submission of the final account documents) or obviously contradicts the contract, judicial assessment may be applied for (Fa Shi [2026] No. 12 Article 13).
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.