Regulation on Ensuring Payment to Small and Medium-sized Enterprises
- 01
Statutory payment terms and late-payment liability for construction sums owed to small and medium-sized enterprises (SMEs), covering progress payments and settlement sums: 30 days, capped at 60, for government agencies and public institutions; 60 days for large enterprises; rules for when the clock starts; the overdue-interest benchmark; and the priority right to payment out of the works price (State Council Decree No. 802, Regulation on Ensuring Payment to SMEs, 2025 revision, Articles 9 to 20; Civil Code Article 807; Fa Shi [2020] No. 25, Articles 26 and 41)
Government agencies and public institutions procuring works from SMEs mu…
国务院令第802号《保障中小企业款项支付条例》(2025修订)第八条、第九条、第十条、第十一条、第十二条、第十三条、第十四条、第十五条、第十七条、第十八条、第二十条《中华人民共和国民法典》第八百零七条法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十六条、第四十一条2026-11-01 - 02
After a back-to-back clause (payment conditioned on receipt of third-party payment) is held invalid: the start date and rate of interest on works payments owed to SMEs - the order for fixing a reasonable payment period (supplementary agreement -> industry norms / trade usage -> the 60-day benchmark of the Regulation), a scenario table of the date payment falls due (delivery date / settlement confirmation date / acceptance date / the three fallback tests), rate standards (agreed rate not below the 1-year LPR at contracting; without agreement, 1-year LPR or 0.05% per day), and the boundary of stacking liquidated damages with doubled delayed-performance interest at the enforcement stage
Interest runs neither from the date the employer actually pays nor from…
法释〔2024〕11号《最高人民法院关于大型企业与中小企业约定以第三方支付款项为付款前提条款效力问题的批复》第一条、第二条(2024年8月27日施行)《保障中小企业款项支付条例》(2025修订,国务院令第802号,2025年6月1日施行)第九条、第十条、第十四条、第十五条、第十七条 https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十六条、第二十七条2026-10-31 - 03
Whether the seller's price claim stands where the purchaser refuses acceptance after the materials are delivered (refusing the goods, refusing to sign, delaying acceptance): the three-layer allocation of and boundaries between the sales contract layer of the Civil Code (delivery + conforming quality as the basis of the claim, transfer of risk, consignation, fulfilment of conditions, notice periods), the compulsory construction inspection layer (no use without inspection) and the payment-period control layer of the SME payment regulation
Payment can in principle be demanded: the price claim rests on delivery…
《中华人民共和国民法典》(主席令第45号)第159条、第525条、第526条、第570条、第571条、第577条、第608条、第610条、第621条、第623条、第628条《建设工程质量管理条例》(国务院令第714号,2019年修订)第29条、第37条《建筑工程施工质量验收统一标准》GB 50300-2013 第3.0.3条2026-10-29 - 04
When interest on unpaid project payments starts accruing — agreement first, plus three "deemed payable date" nodes
Interest runs from the date the project price becomes payable: where the…
《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第9条、第26条、第27条、第41条《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号,2026年6月30日施行)第21条、第23条,https://www.court.gov.cn/fabu/xiangqing/504221.html《保障中小企业款项支付条例》(2025修订,国务院令第802号,2025年6月1日施行)第9条、第10条、第14条、第15条、第17条,https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml2026-10-29 - 05
Grading the validity of the payment condition 'the works price is paid only after the audit authority's audit conclusion or the government fiscal review conclusion has been obtained' set by employers (including large state-owned enterprises): the divide between validity as a settlement basis and failure as a payment defence, the counter-move of judicial construction cost expert assessment where the audit is overdue or manifestly inconsistent, fictive fulfilment of conditions, and the subject and time boundaries set by the 2025 revision of the Regulation on Ensuring Payment to Small and Medium Enterprises and by Fa Shi [2026] No. 12
Layered conclusions: (1) as a 'settlement basis' - where the contract ex…
法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第十三条、第二十三条 https://www.court.gov.cn/zixun/xiangqing/504221.html法释〔2020〕25号 建设工程施工合同纠纷案件适用法律问题的解释(一)第二十七条、第四十一条保障中小企业款项支付条例(2025修订,国务院令第802号,2025年6月1日施行)第八条、第九条、第十条、第十二条、第十四条、第十七条、第三十一条、第三十三条 https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml2026-10-29 - 06
Article 11 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802) prohibiting compulsory acceptance of commercial bills of exchange: the SME contractor's right to refuse bills when a large enterprise pays for works, comparison of situations that may and may not be refused, and the linkage with standard-form clause rules and delay in acceptance under the Civil Code and with defences under the Negotiable Instruments Law
In principle the contractor may refuse. Article 11 expressly prohibits g…
《保障中小企业款项支付条例》(2020年7月5日国务院令第728号公布,2025年3月17日国务院令第802号修订,2025年6月1日施行)第2、3、7、9、10、11、13、14、15、17、24、25、26、29、31、33、34条《中华人民共和国民法典》(主席令第45号)第496、497、509、543、577、579、589条《中华人民共和国票据法》(主席令第49号)第13、17、53、68条2026-10-29 - 07
Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802), Chapter III Supervision and Administration: supervision and inspection of overdue payments, inquiry letters, interviews and supervision notifications; the complaint acceptance authority and transfer within 10 working days of formal acceptance; a written handling result from the complaint handling authority within 30 days (no more than 90 days in complex cases); supervision directive letters, interviews, public notification and ordered rectification; credit default records with publication on the National Public Credit Information Shared Platform and joint restriction measures; audit supervision; the enterprise size type self-test platform and official determination; public interest legal services
The complaint acceptance authority (the department in charge of comprehe…
《保障中小企业款项支付条例》(2025修订,国务院令第802号)第二十一条至第三十条https://www.gov.cn/gongbao/2025/issue_11966/202504/content_7017465.html2026-10-29 - 08
Validity of 'back-to-back' clauses by which a large enterprise and an SME agree that 'payment is conditional on receipt of payment from a third party (the owner)' or that 'payment is made in proportion to the owner's payment progress' (void); handling of the payment period and overdue interest after nullity (three-step determination of the period + the 60-day / 30-day benchmarks and starting points under Article 9 of the Regulation + Article 27 of Fa Shi [2020] No. 25 on the starting point of interest + Article 21 of Fa Shi [2026] No. 12 on the starting-point rule); and the boundaries of applicable parties and temporal effect
Void (nullity is limited to that clause). Under Article 1 of Fa Shi [202…
《保障中小企业款项支付条例》(2025修订,国务院令第802号,2025年6月1日施行)第3、7、8、9、10、11、12、13、14、15、17条《最高人民法院关于大型企业与中小企业约定以第三方支付款项为付款前提条款效力问题的批复》(法释〔2024〕11号,2024年8月27日施行)第1条、第2条《中华人民共和国民法典》第153条第1款、第156条、第497条、第510条、第511条第4项2026-10-29 - 09
The evidentiary path for a subcontracting enterprise to prove it is a small or medium-sized enterprise (SME) protected under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises: no statutory SME certificate exists, so the size type is determined under the statutory classification standard at the point of contract conclusion (operating revenue + total assets), with a requirements table, evidentiary materials, the official determination procedure for disputes, and the precondition that the counterparty qualifies
China runs no certification-and-licence system for SMEs: under Article 3…
《保障中小企业款项支付条例》(2025年3月17日中华人民共和国国务院令第802号修订公布,2025年6月1日施行;原2020年7月5日国务院令第728号公布)第二条、第三条、第七条、第二十一条至第三十条《中小企业划型标准规定》(工信部联企业〔2011〕300号)《中华人民共和国中小企业促进法》2026-10-29 - 10
Checklist of payment compliance obligations under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): 30-day and 60-day-maximum payment terms for state organs and public institutions and 60-day terms for large enterprises, and the starting points of those terms; prohibition of third-party payment conditions; delayed acceptance treated as expiry of the term; prohibition of compulsory commercial bills of exchange; no compelling use of audit conclusions as the settlement basis; security limited to four types and not restricted to cash; overdue interest at 0.05% per day; payment of undisputed portions first; and information disclosure requirements
State organs and public institutions must pay within 30 days of delivery…
《保障中小企业款项支付条例》(2025修订,国务院令第802号)第2—20条 https://www.gov.cn/gongbao/2025/issue_11966/202504/content_7017465.html《中华人民共和国民法典》第153条第1款、第510条、第511条第4项《最高人民法院关于大型企业与中小企业约定以第三方支付款项为付款前提条款效力问题的批复》(法释〔2024〕11号) http://gongbao.court.gov.cn/Details/a56bf04193752b0ae2dd77152dbeb3.html2026-10-29 - 11
Payment time limits under the 2025 revision of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises: 30 days (60 days at most) for state organs and public institutions, 60 days for large enterprises, when the period starts (acceptance and settlement), the ban on back-to-back clauses, the four permitted securities, and interest on overdue payment (1-year LPR floor / 0.05% per day)
Under the Regulation on Ensuring Payment to Small and Medium-sized Enter…
《保障中小企业款项支付条例》(2025修订,国务院令第802号)第八条、第九条、第十条、第十一条、第十二条、第十三条、第十四条、第十五条、第十七条、第十八条《保障中小企业款项支付条例》(2020年版,国务院令第728号)《中华人民共和国民法典》第五百一十一条(履行期限)2026-10-29 - 12
Validity of a quality retention money percentage exceeding the 3% cap, and routes for return or payment of the excess (including expiry of the defects liability period, substitution by performance security or a guarantee bond, and the time-point distinctions for contract termination and for a void contract with incomplete works)
The 3% cap comes from Jian Zhi [2017] No. 138 Article 7 and GB/T 50500-2…
建质〔2017〕138号《建设工程质量保证金管理办法》(2017修订)第二条、第三条、第六条、第七条、第九条、第十条、第十一条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.5.1条、第10.5.5条国办发〔2016〕49号《国务院办公厅关于清理规范工程建设领域保证金的通知》第三条、第四条2026-10-29 - 13
The contractor's four-level remedy ladder when the owner delays payment (demand -> suspension and claims -> administrative complaint -> termination/priority of payment)
Four escalating levels — "gentle demand -> pressure by suspension -> adm…
GB/T 50500-2024 建设工程工程量清单计价标准保障中小企业款项支付条例(国务院令第728号)中华人民共和国民法典2026-09-25 - 14
The employer's time requirement for reviewing progress payments (GB/T 50500-2024 §9.1/§9.4): the reasonable-time fallback, the certificate-confirmation procedure, and common deadline conventions
GB/T 50500-2024 sets no fixed review days: Clause 9.4.11 requires the em…
GB/T 50500-2024 第9.1.6~9.1.11条GB/T 50500-2024 第9.4.9~9.4.12条GF-2017-0201 通用条款第12.4.4条2026-09-25 - 15
Measuring the impact of progress payment collection delays on the advance-funding peak and financing costs (three-tier interest rate bases + claim grounds)
Each month of collection delay adds roughly one month of net cash outflo…
保障中小企业款项支付条例(国务院令第728号)第十五条GB/T 50500-2024 建设工程工程量清单计价标准 第9.4.12、8.11.9条T/YJXB 0001-2023 建设工程停工承包人费用计算标准 第4.0.13、4.0.14条2026-09-25