The contractor's four-level remedy ladder when the owner delays payment (demand -> suspension and claims -> administrative complaint -> termination/priority of payment)

Four escalating levels — "gentle demand -> pressure by suspension -> administrative complaint -> legal remedies": (1) written demand (GB/T 50500-2024 §10.2.12/§10.3.17) + undisputed portion first (§9.4.11) + overdue interest (Decree No. 728, Article 15: agreed rate no less than the 1-year LPR, 0.05% per day absent agreement); (2) statutory suspension rights (prepayment §9.2.4, safety measure fees §9.3.3) + 28-day dual-node claims (§9.4.12); (3) complaint to the SME authority (Decree No. 728, Article 17, with credit blacklisting); (4) termination + priority of payment for the project price (Civil Code Articles 563/807, 18-month exclusion period).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • 保障中小企业款项支付条例(国务院令第728号)
  • 中华人民共和国民法典
  • 法释〔2020〕25号

Topic Positioning

The contractor's escalating remedy ladder when the owner delays payment (demand -> suspension and claims -> administrative complaint -> termination/priority of payment).

Core Conclusions

Four levels: (1) Demand — written demand is the precondition of everything later (GB/T 50500-2024 §10.2.12 process settlement payments, §10.3.17 final account payments); disputed items — undisputed portion paid first (§9.4.11); where government agencies/public institutions/large enterprises pay SMEs late, overdue interest no less than the 1-year LPR, 0.05% per day absent agreement (Decree No. 728, Article 15). (2) Pressure — where prepayments or safety-production measure fees remain unpaid after demand, the contractor may suspend work and claim (§9.2.4, §9.3.3); overdue progress payments are claimable (§9.4.12), observing the 28-day intention + 28-day report dual nodes; suspension rights over progress payments depend on the contract. (3) Administrative — complain to the provincial or higher SME authority (Article 17), serious cases entering credit blacklisting; "refusing payment pending audit/acceptance approval" and "forced commercial bills" are liable under Article 25; government projects may not require advance funding (Article 26). (4) Legal — after demand, termination per Civil Code Article 563, plus priority of payment out of the works' discounted/auctioned price (Article 807).

Applicable Boundaries

Statutory suspension rights cover only prepayments and safety-production measure fees; priority of payment presupposes qualified quality and a direct contract with the employer, covers only the project price, with an 18-month exclusion period; the SME clauses apply only to government agencies/public institutions/large enterprises paying SMEs late; proof of service of demand letters underlies every level.

Further Reading

GB/T 50500-2024, Sections 9.2-9.4, 10.2, 10.3 and Clause 8.11.9; Decree No. 728, Articles 15, 17, 25, 26; Civil Code, Articles 563, 807; Fa Shi [2020] No. 25, Articles 35-41.