The contractor's four-level remedy ladder when the owner delays payment (demand -> suspension and claims -> administrative complaint -> termination/priority of payment)
Four escalating levels — "gentle demand -> pressure by suspension -> administrative complaint -> legal remedies": (1) written demand (GB/T 50500-2024 §10.2.12/§10.3.17) + undisputed portion first (§9.4.11) + overdue interest (Decree No. 728, Article 15: agreed rate no less than the 1-year LPR, 0.05% per day absent agreement); (2) statutory suspension rights (prepayment §9.2.4, safety measure fees §9.3.3) + 28-day dual-node claims (§9.4.12); (3) complaint to the SME authority (Decree No. 728, Article 17, with credit blacklisting); (4) termination + priority of payment for the project price (Civil Code Articles 563/807, 18-month exclusion period).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- 保障中小企业款项支付条例(国务院令第728号)
- 中华人民共和国民法典
- 法释〔2020〕25号
Topic Positioning
The contractor's escalating remedy ladder when the owner delays payment (demand -> suspension and claims -> administrative complaint -> termination/priority of payment).
Core Conclusions
Four levels: (1) Demand — written demand is the precondition of everything later (GB/T 50500-2024 §10.2.12 process settlement payments, §10.3.17 final account payments); disputed items — undisputed portion paid first (§9.4.11); where government agencies/public institutions/large enterprises pay SMEs late, overdue interest no less than the 1-year LPR, 0.05% per day absent agreement (Decree No. 728, Article 15). (2) Pressure — where prepayments or safety-production measure fees remain unpaid after demand, the contractor may suspend work and claim (§9.2.4, §9.3.3); overdue progress payments are claimable (§9.4.12), observing the 28-day intention + 28-day report dual nodes; suspension rights over progress payments depend on the contract. (3) Administrative — complain to the provincial or higher SME authority (Article 17), serious cases entering credit blacklisting; "refusing payment pending audit/acceptance approval" and "forced commercial bills" are liable under Article 25; government projects may not require advance funding (Article 26). (4) Legal — after demand, termination per Civil Code Article 563, plus priority of payment out of the works' discounted/auctioned price (Article 807).
Applicable Boundaries
Statutory suspension rights cover only prepayments and safety-production measure fees; priority of payment presupposes qualified quality and a direct contract with the employer, covers only the project price, with an 18-month exclusion period; the SME clauses apply only to government agencies/public institutions/large enterprises paying SMEs late; proof of service of demand letters underlies every level.
Further Reading
GB/T 50500-2024, Sections 9.2-9.4, 10.2, 10.3 and Clause 8.11.9; Decree No. 728, Articles 15, 17, 25, 26; Civil Code, Articles 563, 807; Fa Shi [2020] No. 25, Articles 35-41.
Keywords
Related Cards
- →
Contractor cash-flow risk control when progress-payment review runs overdue: deemed approval of measurements, payment of undisputed portions, and four-layer defense (GB/T 50500-2024)
Review deadlines are not bottomless: absent contractual deadlines, GB/T 50500-2024 Article 7.1.5 establishes "overdue silence = measurement accepted," Article 9.4.11 "undisputed portions paid first," and Article 9.1.7 payment no less than 80% of cumulative completed work value; overdue non-payment supports claims under 9.4.12, and in extreme cases priority-of-payment under Civil Code Article 807 (exercisable within 18 months) and the Regulation on Payment to SMEs. Defense deploys across four layers: contract clauses - process management - legal remedies - self-rescue financing.
- →
Priority right of payment for construction project prices: entitled parties, exercise procedure, scope of coverage and the 18-month exercise period
Under Civil Code Article 807 and Fa Shi [2020] No. 25, Articles 35-41: the priority right is exercised by the contractor that concluded the construction contract with the employer (decoration contractors and contractors of uncompleted but quality-qualified works may also qualify when conditions are met), premised on the works being quality-qualified; the exercise path is demand, then overdue non-payment, then agreed discount of the works or petition to the court for auction according to law; the coverage is limited to the project price (labour cost, materials cost, plant and small tools cost, overheads (company and site), profit, statutory levies and fees, taxes and duties (VAT under the current standard), etc.), while interest for late payment, liquidated damages and damages rank as ordinary claims only; the right must be exercised within a reasonable period not exceeding 18 months from the date the price becomes payable - a peremptory period; it takes priority over mortgages and other claims, except the delivery claim of commodity-housing consumers who have paid all or most of the price.
- →
Quantifying advance-funding pressure when contract payment proportions are too low, and standard floors (GB/T 50500-2024: 80% progress payments, 10%-30% advance payment)
Every 10-point drop in the payment proportion adds roughly 10% of the contract amount in advance funding: peak advance = (1 - payment proportion) x contract amount; average advance ~= peak/2; annual financing cost ~= average advance x annual rate. GB/T 50500-2024: progress payments should not be below 80% of cumulative completed work value (9.1.7); in-process settlement not below 80% (10.2.4); advance payment not below 10% and not above 30% of contract price (9.2.2). Advance funding stacks migrant-wage, supply-chain, and tax-prepayment chain risks; the Regulation on Payment to SMEs (30/60-day terms and overdue interest) can be invoked for relief.
- →
Calculation of progress payments (GB/T 50500-2024 §9.1/§9.4): the cumulative-difference method, the 11-item composition of cumulative completed value, and payment/deduction rules
Current payable progress payment = cumulative completed value to date − cumulative paid price − current deductions (GB/T 50500-2024 Clauses 9.1.6, 9.4.9); absent an agreed ratio, payment should be no less than 80% of cumulative completed value (9.1.7); the cumulative value comprises 11 items — contract BOQ price, BOQ errors/omissions adjustments, provisional sums, adjustments of provisional prices after procurement, main contractor's attendance and coordination provisions, dayworks, changes in costs, regulation/policy changes, variations, additional works, claims; the statutory safety provisions advance may not be recovered from progress payments (9.1.7, 9.3.2), advances recovered per the agreement (9.2.6); disputed items certified and paid first on undisputed parts (9.4.11); payment applications must list construction workers' wages separately (9.4.9).
- →
Full workflow of agreeing and paying construction advance payments (GB/T 50500-2024 Section 9.2): nature, proportion, procedure, guarantee, and recovery
The construction advance payment (materials advance) is paid by the Employer before commencement for the Contractor's materials preparation - earmarked and interest-free. For labour-and-material contracts, the payment proportion should not be less than 10% of the signed contract price (net of provisional sums, dayworks and provisional sums for nominated specialist subcontract works) and should not exceed 30% of the signed contract price (for major multi-year projects, prepaid annually at the same proportion in accordance with the annual plan). The Contractor applies -> the Employer reviews and pays (an equal-value guarantee may be agreed); recovery is made as agreed in the contract, or, if not agreed, in one or more instalments; on termination of the contract, any unrecovered portion is recovered in full.
Cited By
- ←
Statutory payment terms and late-payment liability for construction sums owed to small and medium-sized enterprises (SMEs), covering progress payments and settlement sums: 30 days, capped at 60, for government agencies and public institutions; 60 days for large enterprises; rules for when the clock starts; the overdue-interest benchmark; and the priority right to payment out of the works price (State Council Decree No. 802, Regulation on Ensuring Payment to SMEs, 2025 revision, Articles 9 to 20; Civil Code Article 807; Fa Shi [2020] No. 25, Articles 26 and 41)
Government agencies and public institutions procuring works from SMEs must pay within 30 days of delivery; a contract may provide otherwise, but the payment term must not exceed 60 days; for large enterprises the outer limit is 60 days. Where the contract adopts stage settlement, periodic settlement or the like, the payment term runs from the date both parties confirm the settled amount (State Council Decree No. 802, Article 9). Late payment carries overdue interest: any agreed rate must be no lower than the 1-year loan prime rate at the time of contract conclusion; absent agreement, interest accrues at a daily rate of 0.05% (Article 17). The contractor may further claim the priority right to payment out of the construction price under Civil Code Article 807; that right must be exercised within 18 months at most, counted from the date on which the employer became obliged to pay the construction price (Fa Shi [2020] No. 25, Article 41).
- ←
Independence of the employer's payment obligation where fiscal funds for a government-invested project are not disbursed in place: the fiscal appropriation relationship is not a payment condition; funds must be secured in place and contractors must not be required to advance financing (Articles 19, 22 and 34 of the Government Investment Regulation; Article 8 of the SME Payment Regulation, State Council Order No. 802); validity grading of pay-after-appropriation clauses (30 days, 60-day maximum, for state organs and public institutions; large enterprises must not condition payment on third-party payment; invalidity under Fa Shi [2024] No. 11; fiction of condition fulfilment under Articles 153 and 159 of the Civil Code); audit and fiscal review fix only the settlement amount, not the payment date; interest accrual and demand documentation
Payment can be demanded. Non-disbursement of fiscal funds is a budget-appropriation relationship between the employer and the finance authority, not a payment condition or an exemption vis-a-vis the contractor: the payment obligation arises from acceptable completion and the contract (Articles 799, 579 and 465 of the Civil Code). Article 19 of the Government Investment Regulation requires the finance department to disburse 'promptly and in full', Article 22 requires funds to be secured in place and prohibits building on contractor advance financing, and Article 34(5) lists requiring the contractor to advance financing for a government-invested project among the sanctionable scenarios, so proceeding while the funds are absent is itself the employer's violation. As to pay-after-appropriation clauses: where the contractor is a small or medium enterprise and the employer is a state organ or public institution, payment is due within 30 days of delivery, extendable by agreement to no more than 60 days (Article 9(1) of the Order No. 802 Regulation); where the employer is a large enterprise, clauses conditioning payment on receipt of third-party payment or paying in proportion to third-party receipts are void (Article 1 of Fa Shi [2024] No. 11; Article 153(1) of the Civil Code), and a condition long obstructed may be deemed fulfilled under Article 159. Audit or fiscal review only decides how much to settle, not when to pay. Interest runs from the date the payment falls due (Article 27 of Fa Shi [2020] No. 25); absent an agreed rate, the loan prime rate applies (Article 26) or 0.05% per day (Article 17 of the Order No. 802 Regulation).
- ←
Whether the contractor may suspend the works when the employer pays progress payments late, and the scope of compensation for suspension losses: the statutory right to suspend exists only for the advance payment and the statutory safety provisions, late progress payment generates only a claim; the model contract text's 28-day procedural suspension right; suspension and idle-time losses enjoy no priority right to payment out of the works price
For a simple late progress payment, neither the law nor the pricing standard gives the contractor an 'automatic right to suspend': GB/T 50500-2024, Clause 9.4.12, says only that 'where the employer does not pay the progress payments as agreed in the contract or pays late, the contractor may claim from the employer under Clause 8.11.9 of this standard', whereas for the advance payment (Clause 9.2.4) and the statutory safety provisions (Clause 9.3.3), if still unpaid after being urged, 'the contractor has the right to suspend the works'. With contractual basis, suspension is possible: under GF-2017-0201, where the employer pays late and fails to correct after written notice, and still does not correct within 28 days after receiving the notice, the contractor may suspend the works 'in the affected parts' and notify the supervising engineer; where suspension lasts 28 full days and defeats the contract purpose, the contract may be terminated, and the employer must pay the 7 categories of sums within 28 days after termination. Compensation is in principle claimable: Civil Code Articles 803 and 804 plus GB/T 50500-2024 Clause 8.11.9 (idle labour, material losses, idle plant, etc.) and Clause 8.11.10 (profit may additionally be claimed for employer-responsible causes), but suspension and idle-time losses enjoy no priority right to payment out of the works price (Fa Shi [2026] No. 12, Article 17, paragraph 2).
- ←
When a notice of termination of a construction contract takes effect: effectiveness on arrival (Article 565 of the Civil Code), the precondition of a termination right (Article 53 of Fa Shi [2023] No. 13; Article 46 of the 2019 Conference Minutes), automatic termination and termination by suit or arbitration, and the preclusive period of the termination right (Article 564)
The contract is terminated when the notice of termination reaches the other party (paragraph 1 of Article 565 of the Civil Code), but the people's court must substantively examine whether the notifying party held a statutory or agreed right to terminate: where it did, the contract terminates on arrival of the notice; where it did not, no effect of termination occurs even if the other party failed to sue within the agreed or a reasonable objection period (Article 46 of the 2019 Conference Minutes; Article 53 of Fa Shi [2023] No. 13). Where the party sues or applies for arbitration directly without notice, the contract terminates when the copy of the statement of claim or of the arbitration application is served on the other party; where the suit is withdrawn and a later suit is upheld, termination occurs when the copy of the statement of claim in the later suit is served (except where, after withdrawal, a notice was given and has reached the other party - Article 54 of Fa Shi [2023] No. 13). The termination right must be exercised within the preclusive period: where a statutory or agreed period exists, the right lapses on its expiry; absent agreement, the right lapses if not exercised within one year from the day the holder knew or should have known of the grounds, or within a reasonable period after being urged by the other party (Article 564). Where termination is by mutual agreement without dealing with breach liability, settlement and winding up, the contract is still found terminated and those issues are handled under Articles 566 and 567.
- ←
The system of legal consequences where the judgment debtor fails to perform under an effective judgment or ruling: the scope of doubled debt interest for delayed performance and of the delayed performance fine, computed from expiry of the specified performance period; the property reporting obligation, with fines and detention for refusal or false reporting; enforcement deterrence measures such as exit restriction, credit-system records and media publication; and the eight findings of 'serious circumstances' for the crime of refusing to execute judgments or rulings
A judgment debtor failing to perform a monetary obligation within the period specified in the legal document must pay doubled debt interest for the period of delayed performance; failing to perform other obligations within the period, it must pay a delayed performance fine (Civil Procedure Law, 2023 revision, Article 264); the delayed-performance interest or delayed performance fine is computed from the date the performance period specified in the judgment, ruling or other legal document expires (Fa Shi [2015] No. 5, Article 504). The judgment debtor must also report its property as of the current date and the year before receiving the enforcement notice; on refusal or false reporting, the court may, according to the circumstances, fine or detain the debtor, its legal representative, or the principally responsible persons or directly responsible persons of the relevant entity (Article 252); on non-performance, the court may take, or notify relevant entities to assist in taking, exit restriction, recording in the credit system, publication of non-performance information through media and other measures (Article 266). A person obliged to execute who is able to execute and commits any of the eight categories of acts listed in Fa Shi [2015] No. 16, Article 2, is found under Criminal Law, Article 313, to fall under 'other circumstances of being able to execute but refusing, with serious consequences', constituting the crime of refusing to execute judgments or rulings.
- ←
The contractor's creditor's right of revocation against an employer transferring assets to evade works-payment debts: the constitutive requirements of Articles 538 / 539 of the Civil Code, the quantitative standards of 'manifestly unreasonable low price 70% / high price 30%', the scope / preclusive period / consequences of revocation under Articles 540-542, and the division of labour with subrogation, nullity for malicious collusion, bankruptcy avoidance and property preservation
Yes. Provided the employer has carried out a gratuitous disposition of property rights under Article 538 of the Civil Code (waiving claims, waiving security for claims, transferring property without consideration, or the like) or has maliciously extended the performance period of a due claim, or has done any of the Article 539 acts - transferring property at a manifestly unreasonable low price, acquiring property at a manifestly unreasonable high price, or providing security for another's debt (the latter three require that the counterparty knew or ought to have known) - and the realisation of the contractor's works-payment claim is affected, the contractor may request the people's court to revoke the act; once revoked, the act has no legal binding force ab initio under Article 542, the disposed property returns to the employer's assets available for satisfaction, and the contractor is then paid through a works-payment suit plus enforcement. Three boundaries: the exercise is limited to the extent of the claim, and necessary costs are borne by the debtor (Article 540); the right extinguishes if not exercised within 1 year from knowing or ought to have known of the ground, or within 5 years from the date of the act (Article 541); the direct effect of revocation is that the counterparty returns property to the employer, compensates at value or performs the due debt - the contractor cannot collect from the counterparty directly. 'Manifest unreasonableness' is judged by the standard of ordinary operators in the locality of the transaction, by reference to the market price there at the time or the guidance price of the price authorities: a transfer price below 70% is in general a manifestly unreasonable low price, an acquisition price more than 30% above is in general a manifestly unreasonable high price, and kinship or affiliation lifts those thresholds (Article 42 of Fa Shi [2023] No. 13).
- ←
Whether losses from suspension of the works and idle time can be brought within the priority right of repayment of the construction project price (Fa Shi [2026] No. 12 Article 17(2): not supported; the debt claim may be pursued but enjoys no priority ranking)
No. Article 17(2) of Fa Shi [2026] No. 12 reads: 'Where a contractor claims the priority right of repayment of the construction project price for losses such as suspension of the works or idle time caused by reasons attributable to the employer, the people's court shall not support the claim.' In character such losses are economic loss caused by the employer's breach (claim money), of the same category as the interest, liquidated damages and damages excluded by Article 40(2) of Fa Shi [2020] No. 25: the debt itself is established, can be sued for and paid, but enjoys no ranking ahead of mortgages and other claims; the character is not changed by the loss being certified in a site instruction record or included in the settlement total, and under Article 17(1) of the same interpretation the court must state in the operative part of the judgment 'the amount of the construction price enjoying the priority right of repayment and the corresponding works'.
- ←
Article 11 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802) prohibiting compulsory acceptance of commercial bills of exchange: the SME contractor's right to refuse bills when a large enterprise pays for works, comparison of situations that may and may not be refused, and the linkage with standard-form clause rules and delay in acceptance under the Civil Code and with defences under the Negotiable Instruments Law
In principle the contractor may refuse. Article 11 expressly prohibits government agencies, public institutions and large enterprises from compelling an SME to accept commercial bills of exchange, electronic receivables vouchers and other non-cash payment methods, or from using them to covertly extend the payment period. The method of payment is part of the content of performance: a change requires the parties' consent (Civil Code Article 543), and unilateral payment by bill does not satisfy full performance in accordance with the contract (Article 509); the contractor may claim payment of the monetary debt (Article 579). But where the contract clearly and reasonably provides for bills (acceptor, tenor, proportion) and the contractor accepted this on signing, in principle it cannot refuse; refusal without justified reason may amount to delay in acceptance (Article 589: no interest during the delay, and compensation for the increased expenses).
- ←
The undisputed-portion-first payment principle in price disputes: progress payment, final account, and wage protection
Where the project price is disputed, the undisputed portion must be paid first: at the progress payment stage, payment certificates are issued and paid for undisputed BOQ items per GB/T 50500-2024, Clause 9.4.11; where final account re-checking raises objections, the unobjected portion undergoes a partial final account (incomplete final account) first (10.3.7); additional works (10.1.8) and quality disputes (10.3.14) may not delay the undisputed portions; and labor costs may never be withheld under any dispute per Article 35 of the Regulations on Wage Payment for Migrant Workers. The disputed portion itself goes negotiation -> review/mediation -> arbitration/litigation.
- ←
Payment-order and arbitration remedies for works-payment and goods-payment debts: the application conditions for a payment order (payment of money or negotiable instruments, no other debt dispute, serviceability) and the two 15-day periods, and the court's review standard (Articles 225 and 227 of the Civil Procedure Law, 2023 amendment); the arbitrable scope, exclusion of litigation by an arbitration agreement, one final award and its exceptions, the three elements and invalidity situations of an arbitration agreement, and the time limit for validity objections (Arbitration Law, 2025 revision, Articles 3-6, 10, 11 and 27-31)
Where a creditor requests payment of money or negotiable instruments, there is no other debt dispute between creditor and debtor, and the payment order can be served on the debtor, the creditor may apply to the competent basic-level people's court for a payment order; after acceptance, where review finds the creditor-debtor relationship clear and lawful, the court shall issue the payment order within 15 days of acceptance, and the debtor shall within 15 days of receipt clear the debt or submit a written objection; where the debtor neither objects within the period nor performs, the creditor may apply for enforcement (Articles 225 and 227 of the Civil Procedure Law, 2023 amendment). Where the parties have reached an arbitration agreement and one party sues in a people's court, the court will not accept the case (unless the arbitration agreement is void or the law provides otherwise); arbitration has no hierarchical or territorial jurisdiction and applies one final award - after the award is made, an application to arbitrate the same dispute again or to sue is not accepted (Articles 5, 6 and 10 of the Arbitration Law, 2025 revision); an arbitration agreement lacking any of the three elements - the expression of intent to apply for arbitration, the matters to be arbitrated, and the chosen arbitration institution - is void if not supplemented (Articles 27 and 29).
- ←
Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802), Chapter III Supervision and Administration: supervision and inspection of overdue payments, inquiry letters, interviews and supervision notifications; the complaint acceptance authority and transfer within 10 working days of formal acceptance; a written handling result from the complaint handling authority within 30 days (no more than 90 days in complex cases); supervision directive letters, interviews, public notification and ordered rectification; credit default records with publication on the National Public Credit Information Shared Platform and joint restriction measures; audit supervision; the enterprise size type self-test platform and official determination; public interest legal services
The complaint acceptance authority (the department in charge of comprehensive administration of SME promotion work at or above provincial level) shall transfer a complaint to the complaint handling authority within 10 working days of formal acceptance; the complaint handling authority shall produce a handling result within 30 days of receiving the complaint materials and give written feedback to the complainant; where the case is complex, an extension may be granted upon approval, but the handling period may in no case exceed 90 days (Article 25). Where the respondent fails to give timely feedback or feedback as required, the handling authority shall issue it a supervision directive letter; where it still refuses to cooperate after receiving the letter, the handling authority may interview it, publicly notify it and order rectification. Where the overdue payment is determined in accordance with laws and regulations to be a credit default, the default is recorded in the credit records; where the circumstances are serious or cause seriously adverse social impact, the information is published on the National Public Credit Information Shared Platform and the National Enterprise Credit Information Publicity System, with restriction measures against government agencies and public institutions in official consumption, office premises and budget arrangements, and restrictions by laws and regulations against large enterprises in fiscal fund support, investment project approval, financing access, market access, qualification rating, and awards and honours (Article 26). The complainant must have a contractual relationship with the respondent; false and malicious complaints are not protected.
- ←
Validity of 'back-to-back' clauses by which a large enterprise and an SME agree that 'payment is conditional on receipt of payment from a third party (the owner)' or that 'payment is made in proportion to the owner's payment progress' (void); handling of the payment period and overdue interest after nullity (three-step determination of the period + the 60-day / 30-day benchmarks and starting points under Article 9 of the Regulation + Article 27 of Fa Shi [2020] No. 25 on the starting point of interest + Article 21 of Fa Shi [2026] No. 12 on the starting-point rule); and the boundaries of applicable parties and temporal effect
Void (nullity is limited to that clause). Under Article 1 of Fa Shi [2024] No. 11, where a large enterprise agrees with an SME in construction, goods procurement or services that receipt of third-party payment is the precondition of payment, the clause violates Articles 6 and 8 of the Regulation on Ensuring Payment to SMEs (Articles 7 and 9 after the 2025 revision) and is void under Article 153(1) of the Civil Code; 'payment in proportion to the owner's payment' and disguised formulations are equally void. After nullity the original payment period is treated as not agreed: first a supplementary agreement; failing that, the period is reasonably determined under Article 510 of the Civil Code and Article 2 of the Reply, by reference to industry norms and trade usage (direct application of item 4 of Article 511, 'performance at any time', is inappropriate), with the statutory day counts of Article 9 of the Regulation as the benchmark - large enterprises 60 days from delivery, government agencies and public institutions 30 days (agreed periods capped at 60 days), counted from the date of delivery / passing acceptance (delayed acceptance: from expiry of the agreed acceptance period) / confirmation of the settled amount by both parties. Interest: as agreed if agreed; if the agreement is unlawful or absent, at the one-year LPR (Article 2 of the Reply); Article 17 of the Regulation separately provides that the agreed rate shall not be lower than the one-year LPR at the time of conclusion and that, absent agreement, 0.05% per day applies. Interest runs from the date the works price falls due; where the payment time is not agreed or is unclear, it is determined under the three situations of Article 27 of Fa Shi [2020] No. 25.
- ←
The evidentiary path for a subcontracting enterprise to prove it is a small or medium-sized enterprise (SME) protected under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises: no statutory SME certificate exists, so the size type is determined under the statutory classification standard at the point of contract conclusion (operating revenue + total assets), with a requirements table, evidentiary materials, the official determination procedure for disputes, and the precondition that the counterparty qualifies
China runs no certification-and-licence system for SMEs: under Article 3(1) of State Council Order No. 802, SMEs means medium, small and micro enterprises determined under the classification standards for SMEs approved by the State Council, and paragraph 2 further provides that 'whether an enterprise is a small or medium-sized enterprise or a large enterprise is determined by its size type at the time the contract is concluded'. The subcontracting enterprise therefore only has to prove, under the industry chapter of the Provisions on Classification Standards for Small and Medium-sized Enterprises (joint document [2011] No. 300 of the Ministry of Industry and Information Technology and other departments), its size data at the point of contract conclusion (for construction, the dual indicators of operating revenue and total assets) to qualify as a protected SME; qualification grades, social security headcount or after-the-fact size are not the test. Where the size type is disputed, it may apply for a determination to the department in charge of SME promotion of the people's government at or above county level 'at the location of the party asserting SME status' (Article 29(2)) -- the strongest evidence. Front threshold: the Regulation binds only government organs, public institutions and large enterprises (Article 2); where the counterparty main contractor is itself an SME, the Regulation does not apply.
- ←
Payment time limits under the 2025 revision of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises: 30 days (60 days at most) for state organs and public institutions, 60 days for large enterprises, when the period starts (acceptance and settlement), the ban on back-to-back clauses, the four permitted securities, and interest on overdue payment (1-year LPR floor / 0.05% per day)
Under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): where state organs and public institutions procure works and the like from small and medium-sized enterprises, payment must be made within 30 days from delivery, and any contractual agreement may not extend the limit beyond 60 days; large enterprises must pay within 60 days and may agree periods reasonably per industry norms, but may not make payment conditional on receipt of third-party payment; where payment is by progress or periodic settlement, the payment period runs from the date the parties confirm the settled amount, and where acceptance is a payment condition, from the date of passing acceptance - or, where acceptance is delayed, from the expiry of the agreed acceptance period. Late payment attracts interest on overdue payment: an agreed rate may not be lower than the 1-year LPR at the time of contracting; absent agreement, 0.05% per day.
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.