Engineering Knowledge Cards.
Confidence HighUpdated 2026-11-01

Statutory payment terms and late-payment liability for construction sums owed to small and medium-sized enterprises (SMEs), covering progress payments and settlement sums: 30 days, capped at 60, for government agencies and public institutions; 60 days for large enterprises; rules for when the clock starts; the overdue-interest benchmark; and the priority right to payment out of the works price (State Council Decree No. 802, Regulation on Ensuring Payment to SMEs, 2025 revision, Articles 9 to 20; Civil Code Article 807; Fa Shi [2020] No. 25, Articles 26 and 41)

Government agencies and public institutions procuring works from SMEs must pay within 30 days of delivery; a contract may provide otherwise, but the payment term must not exceed 60 days; for large enterprises the outer limit is 60 days. Where the contract adopts stage settlement, periodic settlement or the like, the payment term runs from the date both parties confirm the settled amount (State Council Decree No. 802, Article 9). Late payment carries overdue interest: any agreed rate must be no lower than the 1-year loan prime rate at the time of contract conclusion; absent agreement, interest accrues at a daily rate of 0.05% (Article 17). The contractor may further claim the priority right to payment out of the construction price under Civil Code Article 807; that right must be exercised within 18 months at most, counted from the date on which the employer became obliged to pay the construction price (Fa Shi [2020] No. 25, Article 41).

Applicable Codes

  • 国务院令第802号《保障中小企业款项支付条例》(2025修订)第八条、第九条、第十条、第十一条、第十二条、第十三条、第十四条、第十五条、第十七条、第十八条、第二十条
  • 《中华人民共和国民法典》第八百零七条
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十六条、第四十一条
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.4.11条、第9.4.12条

Topic positioning

The payment terms and late-payment rules seen from the contractor's side: the statutory time limits, starting points and overdue interest for construction sums paid by government agencies, public institutions and large enterprises to SMEs under the Regulation on Ensuring Payment to SMEs (State Council Decree No. 802, 2025 revision), together with the interest benchmark and the time limit of the priority right under ordinary civil-commercial rules.

Core conclusions

1. Payment terms (State Council Decree No. 802)

  • Article 9: 'Government agencies and public institutions procuring goods, works or services from SMEs shall pay within 30 days from delivery of the goods, works or services; where the contract provides otherwise, its terms apply, but the payment term must not exceed 60 days. Large enterprises procuring goods, works or services from SMEs shall pay within 60 days from delivery; where the contract provides otherwise, its terms apply, but the payment term shall be agreed reasonably in line with industry norms and trading practice and payment shall be made promptly, and it must not be agreed that receipt of a third party's payment is a condition for paying the SME, nor that the SME is paid in proportion to that third party's payment progress.' Where laws, administrative regulations or other state provisions prescribe other payment terms, those provisions govern. 'Where the contract stipulates settlement by performance progress, periodic settlement or the like, the payment term runs from the date on which both parties confirm the settled amount.'
  • Article 10 (acceptance as the payment condition): where passing inspection or acceptance is the payment condition, the payment term runs from the date inspection or acceptance passes; the parties shall agree in the contract a clear and reasonable inspection or acceptance period and complete it within that period; where a government agency, public institution or large enterprise delays inspection or acceptance, the payment term runs from expiry of the agreed inspection or acceptance period.
  • Article 8 (funding safeguards): the funds needed for government-invested projects shall be secured in place under the relevant state provisions, and construction units must not be required to advance-finance the works.

2. No delaying payment through agreement or procedure

  • Article 11: where non-cash payment methods such as commercial bills or electronic receivables vouchers are used, they shall be clearly and reasonably agreed in the contract; SMEs must not be forced to accept them, and non-cash methods must not be used to stretch the payment term in disguised form.
  • Article 12: government agencies, public institutions and large state-owned enterprises must not compel the use of an audit authority's audit conclusion as the basis for settlement, except as otherwise provided by law or administrative regulation.
  • Article 13: apart from the bid security, performance security, works quality retention money and migrant-worker wage security established by law, no further security may be taken in any form during construction; security must not be limited to cash - where an SME tenders a guarantee or the like issued by a financial institution, it shall be accepted; when the security period expires it shall be promptly accounted for and refunded.
  • Article 14: payment to an SME must not be refused or delayed on the grounds of a change of legal representative or principal officer, the running of internal payment procedures, or - absent contractual agreement - awaiting completion filing, final-account audit or the like.
  • Article 15: where part of a transaction is disputed but the dispute does not affect performance of the rest, the undisputed part shall be paid promptly.

3. Late-payment liability and remedies

  • Overdue interest (Article 17): 'A government agency, public institution or large enterprise that delays payment to an SME shall pay overdue interest. Where the parties have agreed the overdue-interest rate, the agreed rate must be no lower than the 1-year loan prime rate at the time the contract was concluded; absent agreement, overdue interest accrues at a daily rate of 0.05%.'
  • Ordinary civil-commercial basis: Fa Shi [2020] No. 25, Article 26 - where the parties have agreed the standard for interest on the unpaid construction price, the agreement governs; absent agreement, interest accrues at the then rate for loans of the same type over the same period, or at the then loan prime rate.
  • Priority right to payment out of the price: Civil Code Article 807 - where the employer fails to pay the price as agreed, the contractor may press it to pay within a reasonable period; if the employer still fails to pay by the end of that period, then unless the nature of the works makes discounting or auction unsuitable, the contractor may agree with the employer to have the works discounted, or apply to the people's court to auction them according to law, and the construction price is paid with priority out of the proceeds of the discount or auction. Time limit per Fa Shi [2020] No. 25, Article 41: the contractor shall exercise the right within a reasonable period, but no more than 18 months, counted from the date on which the employer became obliged to pay the construction price.
  • Linking to progress payments: where the employer fails to pay progress payments as agreed or pays late, the contractor may claim under GB/T 50500-2024 clause 8.11.9 (via clause 9.4.12); where the parties dispute the measurement or pricing of some BOQ items, the employer shall issue a payment certificate and pay progress payments for the undisputed part (clause 9.4.11) - the same thrust as Article 15 of Decree 802.

4. Disclosure and compliance duties (around Article 20) Government agencies and public institutions shall, by 31 March each year, publish by website, newspapers or other means easily known to the public the number and amounts of contracts on which sums owed to SMEs remain unpaid from the previous year; large enterprises shall fold this into their annual reports and publish it through the National Enterprise Credit Information Publicity System (Article 18); and SMEs or their staff who press for payment or lodge complaints must not be intimidated or retaliated against (Article 20).

Applicability boundaries

  • The payment terms, overdue interest and prohibitions of Decree 802 govern dealings between government agencies, public institutions and large enterprises on the one hand and SMEs on the other; commercial dealings between non-SMEs, and payment terms between equal parties generally, remain governed by the contract and the Civil Code (the interest standard reverting to Fa Shi [2020] No. 25, Article 26).
  • The start of the payment term is judged in layers: ordinary dealings run from delivery; where stage or periodic settlement is agreed, from confirmation of the settled amount; where passing acceptance is the agreed condition, from acceptance passing - and where acceptance is dragged out, from expiry of the agreed acceptance period.
  • The 18 months on the priority right is an outer limit on exercise (in substance an exclusion period) running from 'the date the employer became obliged to pay the construction price'; once missed, the priority position is lost, so fix the evidence of the payable date first.
  • Decree 802 runs alongside model conditions and pricing standards: the concrete payment dates and post-certificate payment days agreed in the contract still govern, the statutory limits standing as an uncrossable ceiling and backstop.

Further reading

  • State Council Decree No. 802, Regulation on Ensuring Payment to SMEs (2025 revision), Chapter 2 on payment provisions, Articles 8 to 20 (payment terms, starting points, non-cash payment, audit conclusions as the settlement basis, security, prohibition of delay, prompt payment of undisputed parts, overdue interest, disclosure and compliance).
  • Civil Code of the People's Republic of China, Article 807 (pressing for payment, discount or auction, priority of the construction price).
  • Fa Shi [2020] No. 25, Interpretation (I) by the Supreme People's Court of Issues on the Application of Law in Cases of Construction Contract Disputes, Article 26 (interest standard on unpaid construction prices) and Article 41 (18-month outer limit on the priority right and its start date).
  • GB/T 50500-2024, clauses 9.4.11 (prompt payment of the undisputed part) and 9.4.12 (claim for late payment pointing to clause 8.11.9).

Keywords