Full workflow of agreeing and paying construction advance payments (GB/T 50500-2024 Section 9.2): nature, proportion, procedure, guarantee, and recovery
The construction advance payment (materials advance) is paid by the Employer before commencement for the Contractor's materials preparation - earmarked and interest-free. For labour-and-material contracts, the payment proportion should not be less than 10% of the signed contract price (net of provisional sums, dayworks and provisional sums for nominated specialist subcontract works) and should not exceed 30% of the signed contract price (for major multi-year projects, prepaid annually at the same proportion in accordance with the annual plan). The Contractor applies -> the Employer reviews and pays (an equal-value guarantee may be agreed); recovery is made as agreed in the contract, or, if not agreed, in one or more instalments; on termination of the contract, any unrecovered portion is recovered in full.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50875-2013 工程造价术语标准
- 国务院令第724号 保障农民工工资支付条例
Topic Positioning
The full workflow of the construction advance payment (materials advance) from agreement to recovery: nature, amount proportion, payment procedure, guarantee and recovery, per GB/T 50500-2024 Chapter 9 Section 9.2, distinguishing it from prepayment of the mandatory health, safety and environmental (HSE) provisions and disbursement of wage-related labour costs.
Core Conclusions
(1) Nature (9.2.1): working-capital assistance during the construction preparation stage, earmarked, with no interest charged by the Employer. (2) Amount (9.2.2, 9.2.3): base = signed contract price less provisional sums, dayworks and provisional sums for nominated specialist subcontract works; for labour-and-material contracts, not less than 10% of the base and not more than 30% of the signed contract price; major multi-year projects prepaid annually at the same proportion in accordance with the annual plan. (3) Procedure (9.2.4): application -> review and payment; on delay, the Contractor may give notice, and if payment is still not made, may suspend the works and claim. (4) Guarantee (9.2.5): to be provided before payment, equal in amount to the advance payment, decreasing as recovery proceeds and valid until fully recovered. (5) Recovery (9.2.6): the contract agreement prevails; absent agreement, recovery in one or more instalments; on termination of the contract, any unrecovered portion is recovered in full.
Applicable Boundaries
Covers only the construction advance payment. Prepayment of the mandatory health, safety and environmental (HSE) provisions (9.3.2: >=50% within 28 days of commencement, not recovered from progress payments, recovered in full at final account) and disbursement of wage-related labour costs (Regulation on Ensuring Wage Payment to Migrant Workers, Article 24: cycle <= 1 month) are independent rules - do not mix them; the 10%-30% band is advisory and must comply with provincial and sector rules; recovery-point calculations are set out in the referenced card.
Further Reading
GB/T 50500-2024 Chapter 9: 9.2.1-9.2.6 (advance payment), 9.1.7 (payment proportion >= 80%), 9.3.2 (prepayment of the HSE provisions); terminology per GB/T 50875-2013 Articles 3.4.1-3.4.2; wage-related labour costs per State Council Order No. 724, Articles 24 and 29.
Keywords
- 工程预付款
- 备料款
- 材料预付款
- 预付款支付比例
- 预付款保函
- 预付款扣回
- 合同价款期中支付
- interim payment