Deduction of employer-supplied (free-issue) materials from payments and allocation of costs: deduction mechanism, procurement/custody fee and wastage responsibility (GB/T 50500-2024, T/ZBD 100.4-2023)

Where employer-supplied (free-issue) material prices are not included in the all-in unit rate (stripped pricing), settlement naturally requires no deduction; where the contract stipulates prior inclusion, deduct from the settlement amount at actual consumption (issued quantity − stock) × the supply contract unit price. Procurement and custody costs follow the material and belong to the procuring party (the employer); the cost of the contractor's custody and assistance services is borne by the employer and charged under the main contractor's attendance and coordination provisions; wastage within the valid wastage rate is borne by the employer, over-drawing attributable to the contractor is borne by the contractor, and employer-caused causes (non-conforming specifications, untimely supply) are borne by the employer.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.2.4条、第3.2.11条、第3.6.1条、第3.6.2条、第3.6.3条、第3.6.4条、第3.6.5条、第3.6.6条、第3.7.4条、第6.2.4条、第8.5节、Ch. 8、App. G.1Table G.1.1
  • GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第3.2.1条、第3.2.3条、第3.2.4条、第3.2.5条、第10.3.5条、App. L.1
  • T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.5.7条
  • GB/T 50875-2013 · Standard glossary of project costs 第2.2.17条
  • 陕西省建设工程费用规则第5.3节(简易计税综合系数法,发包人提供材料项目的税前造价口径)

Topic Positioning

This card covers the settlement treatment rules for employer-supplied (free-issue) materials (materials provided by the employer, installed by the contractor): how they are deducted from payments, who bears the procurement and custody fees, and how wastage and over-drawing are allocated by responsible party, per GB/T 50500-2024, China national pricing standard for BOQ (Standard for Valuation of Construction Works with Bills of Quantities), and T/ZBD 100.4-2023, Guideline for Construction Cost Expert Assessment (Judicial Appraisal) of Construction Works.

Core Conclusions

  • Deduction mechanism: under BOQ-based pricing, employer-supplied material prices are not included in the all-in unit rate (already stripped at tender pricing), so settlement naturally involves no "deduction" issue; if the contract stipulates prior inclusion in the works cost, deduct at actual consumption — actual consumption = actual issued quantity − stock; where the issued quantity exceeds the due consumption, return the excess to stock first, and any amount not returned to stock is deducted from the material cost as agreed in the contract, with the deduction unit price determined per the corresponding supply contract, deducted from the interim settlement by construction stage or the final account amount.
  • Procurement and custody costs: a component of the norm-based material price for estimating, following the material and belonging to the procuring party — for employer-supplied (free-issue) materials the employer procures, so the employer bears them.
  • Custody fee: the cost of the contractor's coordination assistance and material custody services for employer-supplied (free-issue) materials is borne by the employer and charged under the main contractor's attendance and coordination provisions.
  • Wastage: wastage within the valid wastage rate agreed in the tender documents is borne by the employer; over-drawing attributable to the contractor (beyond drawing quantities + the valid wastage rate) is borne by the contractor at the supply contract unit price; employer-caused causes (material specifications/models inconsistent with the tender documents causing excess wastage, untimely supply) are borne by the employer.

Applicable Boundaries

Applies to settlement treatment and dispute assessment of employer-supplied (free-issue) materials under BOQ-based pricing; premised on the employer specifying in the tender documents the scope of materials supplied and a reasonable valid wastage rate. Does not apply to contractor-procured materials; contractor supply changed to employer supply is a reverse variation — deduct the material cost and procurement/custody cost from the all-in unit rate (separate rules). In construction cost expert assessment (judicial appraisal), verify the original vouchers of procurement, issued, returned and stock quantities.

Further Reading

See GB/T 50500-2024, China national pricing standard for BOQ, Clauses 3.6.3 and 3.6.4 (over-drawing deduction and wastage bearing), Clauses 3.2.4 and 3.6.1 (employer-supplied materials not included in the all-in unit rate), Clause 3.7.4 (price stripping upon contractor-to-employer supply change); T/ZBD 100.4-2023, Guideline for Construction Cost Expert Assessment (Judicial Appraisal) of Construction Works, Clause 4.5.7 (expert assessment procedure for employer-supplied material settlement disputes); for the definition of procurement and custody costs see GB/T 50875-2013, Standard for Construction Cost Terminology, Clause 2.2.17.