Free-issue materials (by the employer) in final account: deduction basis, consumption verification, over-draw and over-consumption liability, and supply-mode conversion pricing (GB/T 50500-2024, T/ZBD 100.5-2023)
Free-issue material amounts are deducted from the final account amount per actual drawn quantities x mutually confirmed prices; actual consumption = drawn quantity - inventory; over-draws not returned are deducted per contract; wastage within the effective wastage rate falls on the employer; contractor-caused over-draws are borne by the contractor and deducted from the final account; employer-caused ones (wrong specifications, untimely supply) fall on the employer; custody and coordination fees may be included in the main contractor's attendance and coordination provisions; when contractor-supplied materials convert to free-issue, the all-in unit rate is stripped of material costs and procurement and storage charges to form an installation all-in unit rate, with VAT on the deducted amount reduced accordingly.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- T/ZBD 100.5-2023 建设工程结算审核作业指引
- T/ZBD 100.4-2023 建设工程造价鉴定作业指引
Topic Positioning
Free-issue materials (by the employer) in final account: amount deduction, consumption verification, over-draw/over-consumption liability, custody service fees, and supply-mode conversion pricing.
Core Conclusions
Free-issue material amounts are deducted from the final account amount per actual drawn quantity x mutually confirmed price; under stripped pricing (materials not included in the all-in unit rate), no recovery is required — only reconciliation by drawn quantities. Actual consumption = actual drawn quantity - inventory; over-draws should be returned to store, unreturned ones deducted per contract. Review must compare against contractually agreed quantities; over-draws need replenishment orders or supplementary agreements, otherwise the excess is not credited and is deducted from the final account amount. Liability: wastage within the effective wastage rate falls on the employer; contractor-caused over-draw costs are borne by the contractor and deducted from the final account; employer-caused ones (mismatched specifications, untimely supply) are borne by the employer. The contractor's custody, coordination, and unloading-assistance costs are borne by the employer and may be included in the main contractor's attendance and coordination provisions. Converting contractor-supplied to free-issue materials requires the contractor's written consent: the all-in unit rate less material costs and procurement and storage charges forms the installation all-in unit rate, with VAT on the deducted amount correspondingly reduced. Review collects goods receipt and acceptance slips, material return slips, and employer's material price approval sheets — and, where consumption is disputed, design documents and tender price composition.
Applicable Boundaries
Applies to final accounts for employer-contractor works priced on a bill of quantities basis, unless otherwise agreed in the contract; not applicable to free-issue machinery, free-issue equipment, or materials covered by a provisional sum for specified materials (the latter per Section 8.4).
Further Reading
GB/T 50500-2024 "China national pricing standard for BOQ", Clauses 3.6.2-3.6.4, 3.7.4, Section 8.4; T/ZBD 100.5-2023 "Guidelines for final account review", Clauses 2.1.8, 3.1.5/3.1.6; T/ZBD 100.4-2023 "Guidelines for construction cost expert assessment (judicial appraisal)", Clause 4.5.7.