main contractor's attendance and coordination provisions
- 01
Effect of signed-off interim settlements by construction stage on the final account: the no-re-measurement and no-re-pricing principle, statutory exceptions that can overturn it, submission and deemed-approval rules for late response, and a clause comparison linking the two settlements (GB/T 50500-2024 + Cai Jian [2022] No. 183)
Except that preliminaries and main contractor's attendance and coordinat…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第7.1.5~7.1.8、8.11.22、10.2.3、10.2.4、10.2.7、10.2.8、10.3.1、10.3.3、10.3.5、10.3.8、10.3.12、10.3.16条《财政部 住房和城乡建设部关于完善建设工程价款结算有关办法的通知》(财建〔2022〕183号)第二条http://czj.pingliang.gov.cn/zfxxgk/fdzdgknr/lzyj/sjzc/art/2022/art_64fff948f92c4e7890840e739d50d0e9.html2026-10-25 - 02
Cost items expressly excluded from the all-in unit rate in BOQ-based pricing (VAT, statutory levies and fees, main contractor's attendance and coordination provisions, provisional sums, employer-borne costs, statutory safety provisions), the correct billing position of each, and audit identification of mixed allocation
Under GB/T 50500-2024 Clause 2.0.9 the all-in unit rate 'includes labour…
GB/T 50500-2024 第 2.0.9、2.0.13、2.0.17 条GB/T 50500-2024 第 3.1.6、3.2.2、3.2.4、3.2.5、3.2.9、3.2.11、3.6.1、3.7.4 条GB/T 50500-2024 第 4.2.6 条、第 6.2.4 条、第 8.3.1 条、App. E Table E.4.5、App. G.1 Table G.1.12026-10-25 - 03
Deduction of employer-supplied (free-issue) materials from payments and allocation of costs: deduction mechanism, procurement/custody fee and wastage responsibility (GB/T 50500-2024, T/ZBD 100.4-2023)
Where employer-supplied (free-issue) material prices are not included in…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.2.4条、第3.2.11条、第3.6.1条、第3.6.2条、第3.6.3条、第3.6.4条、第3.6.5条、第3.6.6条、第3.7.4条、第6.2.4条、第8.5节、Ch. 8、App. G.1Table G.1.1GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第3.2.1条、第3.2.3条、第3.2.4条、第3.2.5条、第10.3.5条、App. L.1T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.5.7条2026-10-25 - 04
Composition differences between interim settlement by construction stage and the final account: stage settlement on three elements plus a five-item payment application, the final account on 13 listed items (GB/T 50500-2024 clauses 10.2 / 10.3)
Interim settlement by stage prices at settlement nodes: its composition…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.13、2.0.34、2.0.35条GB/T 50500-2024 第10.2.1、10.2.3、10.2.5、10.2.6、10.2.7、10.2.10条GB/T 50500-2024 第10.3.1、10.3.2、10.3.3、10.3.4、10.3.15条2026-10-18 - 05
GB/T 50500-2024 charging scope of the main contractor's attendance and coordination provisions: charged on free-issue materials and the employer's specialist subcontracts, not on the contractor's own subcontracting
Per GB/T 50500-2024, free-issue materials (materials provided by the emp…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 06
Deduction rules when subcontractors use the main contractor's machinery, materials, and temporary works and site establishment costs: characterization, pricing, and settlement points (GB/T 50500-2024)
The main contractor providing machinery/materials/temporary works and si…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.4-2023 建设工程造价鉴定作业指引建设部令第124号 房屋建筑和市政基础设施工程施工分包管理办法2026-09-25 - 07
Charging MEP design-development (detail design) costs: cost nature and attribution, market-based pricing, and the five-stage workload proportions
MEP design development is an independent design stage; its cost belongs…
T/CIAS-2-2020 建筑机电施工图深化设计技术标准T/ZBD 100.2-2022 建设项目投资估算编制作业指引SJG 86-2020 建筑和市政工程估算编制规程2026-09-25 - 08
Correspondence between the subcontract BOQ and the main contract BOQ: four-layer mapping of scope, BOQ elements, price, and fees
The subcontract BOQ is not built from scratch but the implementation-lev…
GB/T 50500-2024 建设工程工程量清单计价标准GB 50860-2013 构筑物工程工程量计算规范GB/T 50358-2017 建设项目工程总承包管理规范2026-09-25 - 09
Free-issue materials (by the employer) in final account: deduction basis, consumption verification, over-draw and over-consumption liability, and supply-mode conversion pricing (GB/T 50500-2024, T/ZBD 100.5-2023)
Free-issue material amounts are deducted from the final account amount p…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 10
Main contractor's attendance and coordination fee: bases to which percentage rates are applied and rates — calculation bases for the three service targets, the C = A × B pricing formula, construction payment settlement adjustment, and tender price ceiling estimation (GB/T 50500-2024)
Main contractor's attendance and coordination fee = calculation base A ×…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.17条、第3.2.9条、第5.2.6条、第8.5.4条、App. ETable E.4.5湖北省建筑安装工程费用定额(2024)「九、总承包服务费」「十、甲供材」https://zjw.beijing.gov.cn/bjjs/zwgk46/zcwj8/index.shtml2026-09-25 - 11
In-process settlement linked to final account: preliminaries and main-contract service fees are interim payments that must be recalculated at final settlement (GB/T 50500-2024 Clauses 10.2.3/10.2.7/10.3.3)
For projects with in-process settlement, preliminaries costs (and main-c…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.2.3、10.2.7、10.3.3、7.3.1条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (已废止,仅对照)第11.2.2、11.2.3条2026-09-25 - 12
GB/T 50500-2024 pricing and settlement adjustment of main contractor's attendance and coordination provisions: per-item risk-inclusive pricing, percentage-rate based adjustment, interim settlement by construction stage, and recomputation at final account
Where the fee is priced per item, it is risk-inclusive except for deduct…
GB/T 50500-2024 第2.0.17、3.2.9、4.2.6、6.2.9、8.4.8、8.5.1~8.5.5、10.2.6、10.3.3条2026-09-25 - 13
Deducting unexecuted (unbuilt) items from the contract price: disallowance rules at final account (re-measurable vs lump-sum contract bases, linked deductions, and contractor compensation)
Unexecuted work must be disallowed from the contract-price BOQ: under re…
T/ZBD 100.5-2023 第3.1.4~3.1.6条GB/T 50500-2024 第8.9.1/8.9.2/8.9.8条GB/T 50500-2024 第8.5.3/8.6.5条2026-09-25