Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

GB/T 50500-2024 pricing and settlement adjustment of main contractor's attendance and coordination provisions: per-item risk-inclusive pricing, percentage-rate based adjustment, interim settlement by construction stage, and recomputation at final account

Where the fee is priced per item, it is risk-inclusive except for deductions or adjustments under Clauses 8.4.8, 8.5.1-8.5.3 and 8.5.5, and shall not be adjusted at final account; where percentage-rate based and the contract is silent or unclear on the pricing basis, adjust per those clauses and compute at settlement from the contract prices of specialist subcontract works, of directly-let specialist works, and of employer-supplied (free-issue) material supply contracts; interim settlement by construction stage takes each specialist subcontract's cumulative completed price as a proportion of its contract price, multiplied by the adjusted total of the provisions; the final account shall recompute the whole of the provisions per Section 8.5 — amounts listed in stage settlements during construction are not a basis for the final account.

Applicable Codes

  • GB/T 50500-2024 第2.0.17、3.2.9、4.2.6、6.2.9、8.4.8、8.5.1~8.5.5、10.2.6、10.3.3条

Topic Positioning

Pricing and adjustment of the main contractor's attendance and coordination provisions at settlement under GB/T 50500-2024: the different treatment of per-item pricing (risk-inclusive) and percentage-rate based pricing, and the computation bases for interim settlement by construction stage and for the final account. Applies to the preparation and audit of settlements involving employer-supplied (free-issue) materials and employer-let specialist works.

Core Conclusions

  1. Scope and composition (Clause 3.2.9): the provisions are the VAT-exclusive price of the corresponding billed (BOQ) item for the main contractor's performance of the contract responsibilities relating to attendance and coordination as set out in the tender documents and contract, covering the management, coordination and cooperation responsibilities towards suppliers of employer-supplied (free-issue) materials, specialist subcontractors under provisional sums for nominated specialist subcontract works (other than those performed by the contractor), and specialist subcontractors directly let by the employer; they comprise the management and coordination of employer-supplied (free-issue) materials, the material custody fee and profit, the coordination and cooperation fees and profit for specialist subcontract works, and the coordination and cooperation fees for directly-let specialist works. Per Clause 2.0.17, the provisions shall include profit; specialist works and labour works subcontracted by the contractor itself shall not attract the provisions.
  2. Per-item pricing = risk-inclusive (Clause 8.5.4): "If the main contractor's attendance and coordination provisions are priced per item, then, apart from deductions or adjustments under Clauses 8.4.8, 8.5.1 to 8.5.3 and 8.5.5 of this standard, they shall be risk-inclusive, and no adjustment shall be made at construction payment settlement." That is, they are borne as the contractor's risk-inclusive amount, with no adjustment save as provided in the contract or required by the relevant rules.
  3. Percentage-rate based pricing (Clause 8.5.4): "If the provisions are priced on a percentage-rate basis and the contract does not stipulate the pricing basis for the percentage rate, or the stipulation is unclear, the provisions shall be adjusted in accordance with Clauses 8.4.8, 8.5.1 to 8.5.3 and 8.5.5 of this standard, and at construction payment settlement they may be computed from the contract prices of specialist subcontract works and of directly-let specialist works, and from the supply contract prices of employer-supplied (free-issue) materials." Under percentage-rate based pricing, adjustment may also be made using the formulas given in the standard.
  4. Interim settlement by construction stage (Clause 10.2.6): the cumulative provisions for each specialist subcontract may be computed as the proportion that the cumulative completed price of that specialist subcontract, as confirmed by the employer and contractor, bears to its contract price, multiplied by the adjusted total of the provisions determined under Section 8.5; for employer-supplied (free-issue) materials and directly-let specialist works, the cumulative provisions may be computed by the same method as for specialist subcontract works.
  5. Final account (Clause 10.3.3): at the final account, the employer and contractor shall recompute and determine the provisions stated in the interim settlement by construction stage documents — computing, in accordance with Section 8.5, the provisions for all specialist subcontract works, directly-let specialist works and employer-supplied (free-issue) materials; "the provisions listed in stage settlements during construction shall not be a basis for the final account."

Applicable Boundaries

  • Applies to employer-contractor activities priced on a bill of quantities basis under GB/T 50500-2024; where the contract provides otherwise, the contract governs; whether pricing is per item or percentage-rate based is determined by the BOQ pricing mode and the contract (the provisions are entered separately in the "bill of provisional sums and other charges").
  • "Risk-inclusive, no adjustment" applies only to per-item pricing; percentage-rate based pricing, adjustments provided in the contract, and recomputation at the final account are not subject to that lock.
  • Percentage-rate levels and pricing bases follow the contract and the norms for on-costs and expenses currently in force where the project is located; the specific adjustment cases under Clauses 8.4.8, 8.5.1 to 8.5.3 and 8.5.5 are to be verified against the original text of the standard.

Further Reading

  • GB/T 50500-2024 China national pricing standard for BOQ: Clause 2.0.17 (definition), 3.2.9 (scope and composition), 4.2.6 (computation method), 6.2.9 (pricing of the bill of provisional sums and other charges), 8.4.8 and 8.5.1 to 8.5.5 (deductions and adjustments), 10.2.6 (interim settlement by construction stage), 10.3.3 (final account).
  • For the charging scope (employer-supplied (free-issue) materials and employer-let specialist works attract the provisions; subcontracts let by the contractor itself do not), see the related card.