GB/T 50500-2024 charging scope of the main contractor's attendance and coordination provisions: charged on free-issue materials and the employer's specialist subcontracts, not on the contractor's own subcontracting
Per GB/T 50500-2024, free-issue materials (materials provided by the employer) and the employer's specialist subcontracts (those within the contract other than what the contractor itself performs, and those directly awarded outside the contract) both attract the main contractor's attendance and coordination provisions; the contractor's own specialist and labour subcontracting does not. The percentage rate is subject to the current norms for on-costs and expenses of the project location.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50875-2013 工程造价术语标准
Topic Positioning
This card explains the charging scope of the main contractor's attendance and coordination provisions under GB/T 50500-2024, the China national pricing standard for BOQ: whether it is charged on free-issue materials and the employer's specialist/direct subcontract works, and the clearly excluded boundary cases, for filling in the "bill of provisional sums and other charges" at tender and for final account review.
Core Conclusions
Both free-issue materials and the employer's specialist subcontract works attract the main contractor's attendance and coordination provisions. Clause 2.0.17 defines three covered objects: ① materials provided by the employer (free-issue materials) — custody and supporting services; ② specialist subcontracts within the contract scope (except those performed by the contractor itself) — cooperation, coordination, on-site management, use of temporary works and site establishment, compilation of as-built documents, etc.; ③ the employer's directly awarded specialist works outside the contract scope — coordination and cooperation responsibilities. The cost composition is in Clause 3.2.9: the free-issue materials part includes supply coordination, material custody cost, and profit; the specialist subcontract part includes coordination/cooperation costs and profit for shop drawings, work faces, progress, etc. Explicitly excluded: the contractor's own specialist and labour subcontracting does not attract the provisions — "the main contractor's own subcontracting" versus "the employer's nominated/direct subcontracting" is the essential distinction. Free-issue materials are not included in the all-in unit rate or the works cost, but the custody service fee is charged separately; if free-issue materials are changed mid-course to contractor procurement, the previously charged attendance and coordination provisions are deducted (Clause 8.5.1). At tender, fill it in separately under the "bill of provisional sums and other charges", priced either as a per-item lump sum or by percentage rate (Clause 6.2.9).
Applicable Boundaries
Applies to tendering/awarding priced on a bill of quantities basis; GB/T is a recommended national standard — after contracting, the contract terms govern. The percentage rate varies by region — the current norms for on-costs and expenses / pricing documents of the project location govern; this card contains no specific rate figures and must not be applied across regions. Labour subcontracting and the contractor's own subcontracting do not attract the provisions; the specific allocation of custody responsibility for free-issue materials follows the contract.
Further Reading
See GB/T 50500-2024 Clause 2.0.17 (definition of the main contractor's attendance and coordination provisions), Clause 3.2.9 (cost composition), Clause 6.2.9 (pricing of the bill of provisional sums and other charges), Clause 8.5.1 (deduction of the provisions upon change of free-issue materials); for terminology compare GB/T 50875-2013, Standard for Construction Cost Terminology, Clause 2.1.15; for percentage rates see local pricing documents such as the norms for on-costs and expenses for the cost of works (construction and installation) of the project location.