Charging MEP design-development (detail design) costs: cost nature and attribution, market-based pricing, and the five-stage workload proportions
MEP design development is an independent design stage; its cost belongs to survey-design and technical-service fees (design fees), counted into the other costs of project construction, not into installation costs; market-based pricing (tiered by investment / by workday / by floor area / by development content and stage), with five-stage workload proportions 20/50/70/90/100% usable as a contract-splitting reference; do not double-charge with the general contractor's service fee (which contains only the coordination fee for subcontract development drawings).
Applicable Codes
- T/CIAS-2-2020 建筑机电施工图深化设计技术标准
- T/ZBD 100.2-2022 建设项目投资估算编制作业指引
- SJG 86-2020 建筑和市政工程估算编制规程
- GB/T 50500-2024 建设工程工程量清单计价标准
Topic Positioning
The cost nature, attribution, and charging method of MEP installation design development (BIM models, MEP coordination, combined supports/hangers, prefabrication drawings, etc.), answering "who pays the development cost and how it is calculated".
Core Conclusions
- Design development should be an independent design stage (T/CIAS-2-2020 Clause 1.0.4); its cost belongs to survey-design and technical-service fees (design fees) (T/ZBD 100.2-2022 Clause 5.5.7), counted into the other costs of project construction, not into installation costs or measure costs.
- Whoever commissions pays: commissioned by the employer to a design institute/third party → counted into other costs paid by the employer; self-performed by the EPC general contractor → included in the general contract price; performed by the contractor as a construction obligation → included in the quotation/management fee or listed separately per the contract.
- Market-based pricing with no mandatory rate (T/CIAS-2-2020 Clause 1.0.4), common calibers: tiered by the project's estimated investment, by consulting service workdays, by floor area, or by development content and stage (SJG 86-2020 Clause 4.4.7).
- Five-stage workload reference proportions (T/CIAS-2-2020 Clause 9.0.2): MEP model design 20% → MEP coordination 50% → refinement 70% → decoration coordination 90% → prefabrication processing 100%; doing only the first two stages is about 50%, and contracts may pay by stages accordingly.
- Distinguish from the general contractor's service fee: under GB/T 50500-2024 Clause 3.2.9, the general contractor's service fee includes the coordination fee for the subcontractors' development drawings but not the development preparation cost itself — the two must not be double-charged.
Applicable Boundaries
Applies to charging the design development of MEP specialties after construction drawings; prefabricated-MEP processing drawings are generally completed by the fabricator with the cost included in its fabrication quotation — mind the demarcation from development costs. The five-stage proportions are reference values only, not mandatory rates; specifics follow the tender documents, special contract conditions, and the local fee quota.
Further Reading
T/CIAS-2-2020 Technical Standard for Deepening Design of Building MEP Construction Drawings, Clauses 1.0.4, 3.2.2, 9.0.2; T/ZBD 100.2-2022 Working Guideline for Preparing Construction Project Investment Estimates, Clause 5.5.7; SJG 86-2020 Rules for Preparing Building and Municipal Engineering Estimates, Clause 4.4.7; GB/T 50500-2024 Standard for Valuation of Construction Works with Bills of Quantities, Clause 3.2.9.