Deduction rules when subcontractors use the main contractor's machinery, materials, and temporary works and site establishment costs: characterization, pricing, and settlement points (GB/T 50500-2024)
The main contractor providing machinery/materials/temporary works and site establishment costs to its own subcontractors is a compensated transfer/lease/service, does not attract the main contractor's attendance and coordination provisions, and must be deducted under separate headings agreed in the subcontract. Materials are recovered by the strip-off method or 'actual consumption (requisition − return − stock) x supply contract unit price'; the portion exceeding the valid wastage rate is borne by the subcontractor and deducted directly from the settlement price; machinery is deducted per agreed machine-shift/monthly rent, and temporary works and site establishment costs per measurement or apportionment, with care against double charging against the subcontract quotation.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- T/ZBD 100.4-2023 建设工程造价鉴定作业指引
- 建设部令第124号 房屋建筑和市政基础设施工程施工分包管理办法
- TB 10402-2019 铁路建设工程监理规范
Topic Positioning
The rules for compliant deduction when the main contractor provides machinery, materials, and temporary works and site establishment costs to its own subcontractors — first characterize the nature, then give pricing and recovery methods in three categories, preventing settlement disputes caused by deductions without a contractual basis.
Core Conclusions
The nature of the deduction is a compensated transfer/lease/service of resources, not the main contractor's attendance and coordination provisions: the latter applies only to materials provided by the employer and specialist works awarded directly by the employer (or not implemented by the contractor); the contractor's own subcontracting does not attract it (GB/T 50500-2024, Clause 2.0.17). Therefore the deduction must be made under separate headings in the subcontract or a supplementary agreement (material supply transfer, machinery lease, temporary works and site establishment costs) specifying unit prices, measurement, and settlement. Materials fall into three modes: (1) strip-off (material cost not included in the subcontract all-in unit rate) — naturally no recovery at settlement; (2) include first, recover later — recover at actual consumption x supply contract unit price, actual consumption = actual requisition − returned quantity − stock (T/ZBD 100.4-2023, Clause 4.5.7); (3) over-requisition deduction — the contract agrees a valid wastage rate; the portion exceeding 'drawing quantity x (1 + wastage rate)' is borne by the subcontractor and deducted by the main contractor directly from progress/final account payments at the supply unit price (GB/T 50500-2024, Clause 3.6.3). Machinery is deducted at the agreed plant rate per machine-shift x actual machine-shifts or monthly rent, stating whether the unit price includes the operator and fuel/power, whether idle-time fees count, and mobilization/demobilization and damage compensation; before signing, check whether the subcontract quotation already includes plant costs to prevent double charging. Water and power for temporary works and site establishment are metered and deducted as measured; where metering is impossible, apportioned by output value or headcount; temporary buildings by room/month rent or per-capita quota norms; sites by area x occupation period; turnaround materials by daily rent x days x quantity.
Applicable Boundaries
Applies to resource-use settlement between the main contractor and its own subcontracts (specialist subcontracts, labour subcontracts); for recovery rules on free-issue materials (by the employer) supplied to the contractor, see the cited card. Works from unlawful subcontracting or contract transfer (re-letting of the whole works) are not subject to measurement and valuation for payment (railway practice) (TB 10402-2019, Clause 6.0.6) and this deduction logic does not apply. For all unit prices, wastage rates, and apportionment methods, the contractual agreement takes precedence; where unclear, negotiate according to the principle of fairness and reasonableness.
Further Reading
GB/T 50500-2024 Clause 2.0.17 (main contractor's attendance and coordination provisions terminology), Clause 3.2.4 (pricing of materials provided by the employer), Clause 3.6.3 (over-requisitioned material deduction); T/ZBD 100.4-2023 Clause 4.5.7 (verification of consumption and return-to-store of free-issue materials (by the employer)); Ministry of Construction Order No. 124 Article 10 (subcontract conclusion and filing); TB 10402-2019 Clause 6.0.6 (situations where measurement and valuation for payment is not carried out (railway practice)).
Keywords
- 分包扣款
- 总包供料
- 机械租赁
- 临设使用费
- 超领材料
- main contractor's attendance and coordination provisions