Establishing monthly settlement and payment ledgers for subcontractors: two-tier architecture, field design, and the monthly cycle
Ledgers are two-tier: a project subcontract payment master ledger + a per-contract monthly settlement ledger (four blocks: measurement / settlement / payment / deductions), with ledger-to-ledger agreement. Monthly cycle: measurement certification and sign-off → stage settlement during construction lock-in → progress payment reviewed on six items → pay undisputed parts first → month-end reconciliation. Unpaid balance = cumulative amount due for settlement − cumulative amount paid − retention balance. Based on GB/T 50500-2024, GB/T 50319-2013, GB/T 51095-2015 and local cost standards.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50319-2013 建设工程监理规范
- GB/T 51095-2015 建设工程造价咨询规范
- DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范
- DB37/T 5130-2018 建设工程造价咨询服务规范
- T/ZSQX 023-2023 城镇给排水项目工程总承包管理规程
- DB37/T 5096-2017 建设工程项目管理咨询规范
Topic Positioning
The system architecture, core fields, and monthly cycle of subcontractor monthly settlement and payment ledgers — unifying monthly measurement, stage settlement during construction, progress payments, various deductions, and reconciliation checks onto one set of two-tier ledgers, for direct adoption by the main contractor's commercial/cost staff.
Core Conclusions
The ledger has two tiers: a project subcontract payment master ledger (organised by subcontract, summarizing the current month's amounts due for settlement and payable, cumulative settled and paid, unpaid balance, retention balance, for monthly cost analysis and cash-flow planning) + per-contract monthly settlement ledgers (one per contract, with four blocks: measurement, settlement, payment, deductions), with ledger-to-ledger agreement. Monthly cycle in five steps: (1) the subcontractor declares → verify against the construction drawings and contract BOQ → both parties certify the measurement results (GB/T 50500-2024 Clause 7.1.7; after certification they serve as the basis for settlement); (2) form the monthly interim settlement document by construction stage — once signed it is locked and the final account does not recompute it (Clause 10.2.3); (3) progress payments reviewed on six items: contract price implemented this period, ± variations, ± claims, advance payment release/deduction, retention withheld, other additions/deductions (GB/T 50319-2013 Clause 5.3.1) — these six items are the monthly ledger columns; (4) pay the undisputed part first per the progress payment certificate (Clause 9.4.11), recorded on the day of payment; (5) at month-end reconcile with the per-contract ledgers, bank statements, and the subcontractor in writing. Monthly detail fields: current/cumulative completed price, current amount due for settlement (completed price ± variation records ± claims), current deductions (retention, advance payment recovery, employer-supplied materials, water and power, plant, fines itemized), current amount payable, actually paid, cumulative paid, unpaid balance = cumulative amount due for settlement − cumulative amount paid − retention balance. The codes require ledgers to be established by contract, containing the completed contract price, amounts paid, advance payments, and unpaid amounts (GB/T 51095-2015 Clause 7.3.3, DBJ/T 15-153-2019 Clause 7.4.3).
Applicable Boundaries
Applies to the main contractor's stage settlement during construction and payment management over specialist and labour subcontracts; for the pricing rules for deductions of employer-supplied materials, plant and temporary works see the cited card on subcontract deduction rules; works from unlawful subcontracting or contract transfer are not measured and valued for payment, and this process does not apply. Payment ratios, time limits, retention ratios, etc. follow the subcontract agreement.
Further Reading
GB/T 50500-2024 Clause 7.1.7 (measurement certification and sign-off), Clauses 9.1.10/9.4.11 (payment certificate confirmation and payment of undisputed parts), Clause 10.2.3 (stage settlement during construction lock-in); GB/T 50319-2013 Clause 5.3.1 (six-item progress payment review); GB/T 51095-2015 Clause 7.3.3, DB37/T 5130-2018 Clause 7.4.7, DBJ/T 15-153-2019 Clause 7.4.3 (ledger content and layering); T/ZSQX 023-2023 Clause 12.4.7 (subcontract settlement documents and review); DB37/T 5096-2017 Clause 11.2.5 (ledger system and traceability).
Keywords
- 分包结算台账
- 付款台账
- 计量与支付台账
- 月度结算
- interim payment
- subcontract administration
- interim settlement by construction stage
- 合同价款支付台账