interim settlement by construction stage
Concept Guide
Concept
Background Promoted by the Ministry of Housing and Urban-Rural Development and other departments around 2020, interim settlement by construction stage moves settlement of the works from a single exercise after completion to a series of agreed milestones during construction. It targets the twin problems of settlements dragging on after completion and payment arrears.
Mechanics
- Milestone-based: settlement units follow progress milestones or as agreed in the contract; on completing each milestone the parties produce an interim settlement document for the work and value completed.
- Finality on signing: once reviewed and signed by both parties (with the engineer/QS), the document is not re-audited at completion but only aggregated. This is what distinguishes it from ordinary progress payments.
- Linked to payment: the signed amount becomes the basis for later payment, fixing the payment obligation at each milestone and squeezing out arrears.
- Disputed items carved out: undisputed value is settled first, so a single dispute cannot hold the whole settlement hostage.
- Contract points: milestone definition and measurement basis, submission and review periods, deemed-acceptance effect of failure to reply, treatment of variations, claims and price adjustment, and linkage with the final settlement.
Versus progress payment Progress payments address cash flow only; interim settlement by construction stage progressively fixes the settlement itself.
Risk note Finality depends on the completeness and clarity of the signing procedure; signing quantities without prices weakens it.
FIDIC Mapping
Corresponding / adjacent terms FIDIC has no equivalent for interim settlement by construction stage (absent). The adjacent mechanisms are Sub-Clause 14.3 [Application for Interim Payment], 14.6 [Issue of Interim Payment Certificate], 14.10 [Statement at Completion] and 14.13 [Final Statement].
Key differences Interim payment under FIDIC is payment on account: applied for under 14.3 and certified by the Engineer under 14.6, it is no more than an assessment of value at the time. A certificate already issued is not final: where a significant error or discrepancy is found, the Engineer may withhold or adjust in a subsequent Statement (14.6), and the Contractor may include amounts it considers due in its next Statement. The account closes only gradually, through the Statement at Completion (14.10) and the Final Statement (14.13). In short, FIDIC interim payment stays open to review and non-final, with finality reached at the Final Statement; a Chinese interim settlement document, once signed, is final and not re-audited at completion. The policy contrast is deliberate: China finalises stage by stage to cut post-completion disputes and arrears, while FIDIC keeps each period provisional with one concluding account so that correction rights survive.
Usage cautions
- Do not read each IPC as a settled account: certification does not extinguish later correction or claims, so correspondence should preserve room for supplementation and adjustment.
- Do not import Chinese finality wording into a FIDIC contract: it conflicts with the correction mechanism at 14.6 and the closing of the account at 14.13; redraft as “undisputed portions confirmed, final adjustment reserved”.
- Terminology and effect: the benchmark English term is interim settlement by construction stage, and a FIDIC certificate or statement is not a settlement agreement in the Chinese sense — its effect rests on the contract, not on the label.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 施工过程结算 | interim settlement by construction stage | 无对应术语;近缘 Sub-Clause 14.3 Application for Interim Payment、Sub-Clause 14.6 Issue of Interim Payment Certificate | absent | FIDIC 期中支付为账目式付款,可复核、非终局,最终由 Final Statement 与 14.13 最终付款证书收口;过程结算签认即终局,制度取向不同。 |
| 过程结算文件的终局性 | finality of the signed interim settlement document | Sub-Clause 14.6 Issue of Interim Payment Certificate、Sub-Clause 14.13 Issue of Final Payment Certificate | distinct | FIDIC 下已签发 IPC 仍可在后续报表扣减更正,承包人也得在最终报表主张余额;不存在签认后不可复核的节点结算。 |
| 竣工后不再重复审核 | no re-audit after completion | Sub-Clause 14.10 Statement at Completion、Sub-Clause 14.13 Issue of Final Payment Certificate | distinct | 14.10 报表是竣工时点的账目,14.13 最终付款证书才定案;中国过程结算签认后仅作汇总,两者终局时点与效力层次不同。 |
Updated 2026-09-13
- 01
Two-stage comparison of requirement elements between interim settlement by construction stage and the final account (GB/T 50500-2024): timing, definition of completed works, payment percentage, price calculation, dispute handling and node division
Interim settlement by construction stage is the calculation, adjustment…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.34、2.0.35、10.1.3、10.1.9、10.2.3、10.2.4、10.2.7、10.2.8、10.2.9、10.2.10、10.2.11、10.3.1、10.3.2、10.3.3、10.3.6、10.3.7、10.3.14、10.3.15、10.3.16、10.5.1、9.4.11条GB 50500-2013 建设工程工程量清单计价规范 第11.3.2、11.3.3、11.4.2条财建〔2004〕369号 建设工程价款结算暂行办法 第十六条2026-11-01 - 02
GB 50500-2013 terms for measurement of the works and construction payment settlement (final account): definitions, clause anchors, side-by-side comparison, and the rules that carry confirmed measurements into the settlement summary, with the corresponding clauses of GB/T 50500-2024
GB 50500-2013 clause 2.0.43 defines 'measurement of the works' as the ca…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.34、2.0.35、7.1.1、7.1.4、7.1.5、7.1.7、7.1.8、8.11.22、9.4.1、9.4.13、10.1.4、10.2.1、10.2.3、10.2.7、10.3.1、10.3.2、10.3.3、10.3.4、10.3.7、10.3.8、10.3.10、10.3.11、10.3.16条、Ch. 11GB/T 50875-2013 · Standard glossary of project costs 第3.4.3、3.4.9条GF-2017-0201《建设工程施工合同(示范文本)》第12.3.2、12.3.3、12.3.4项、第12.4.2、12.4.3、12.4.4项2026-11-01 - 03
Interim payment and final settlement of preliminaries: statutory safety provisions prepayment and recovery points (9.3.2 - at least 50% within 28 days of commencement), progress-payment methods (9.4.4 - agreed breakdown or element-works ratios), the three-stage preliminaries breakdown table (6.2.13, Appendix E Table E.3.3), interim versus final settlement (10.2.7, 10.3.3) and the three-class treatment in settlement review
Statutory safety provisions prepay at not less than 50% of the total wit…
GB/T 50500-2024 第6.2.13条(措施项目费用分拆表)GB/T 50500-2024 第9.3.2条(安全生产措施费预付与扣回)GB/T 50500-2024 第9.4.4条(措施项目进度款)2026-10-25 - 04
Reconciling the three output-value bases of construction output, measured output and settlement output: item-by-item basis distinction, four classes of difference attribution, the disallowance-and-resubmission tests, and the tie-out with stage settlement documents
Construction output value (physical-progress statistics basis), measured…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第7.1.5、7.1.7、7.1.8、8.9.1、8.11.3、8.11.21、9.4.1、9.4.9、9.4.13、10.1.6、10.2.1、10.2.3、10.2.4、10.2.8、10.3.2、10.3.14条GB/T 50319-2013 · Code for Construction Project Supervision 第5.3.1、6.3.4条DBJ41/T 208-2018 · Standard for Construction Project Supervision Work (Henan) 第7.3.2条2026-10-25 - 05
Effect of signed-off interim settlements by construction stage on the final account: the no-re-measurement and no-re-pricing principle, statutory exceptions that can overturn it, submission and deemed-approval rules for late response, and a clause comparison linking the two settlements (GB/T 50500-2024 + Cai Jian [2022] No. 183)
Except that preliminaries and main contractor's attendance and coordinat…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第7.1.5~7.1.8、8.11.22、10.2.3、10.2.4、10.2.7、10.2.8、10.3.1、10.3.3、10.3.5、10.3.8、10.3.12、10.3.16条《财政部 住房和城乡建设部关于完善建设工程价款结算有关办法的通知》(财建〔2022〕183号)第二条http://czj.pingliang.gov.cn/zfxxgk/fdzdgknr/lzyj/sjzc/art/2022/art_64fff948f92c4e7890840e739d50d0e9.html2026-10-25 - 06
Node division modes, payment percentage floors and post-confirmation re-review rules for interim settlement by construction stage: GB/T 50500-2024 Clauses 10.1.3/10.2.3/10.2.4/10.3.15/10.5.1, Cai Jian [2022] No. 183 and local implementation documents
Nodes, procedures and methods are governed by the contract (GB/T 50500-2…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.35条、第9.1.7条、第9.4.1条、第10.1.3条、第10.2.3条、第10.2.4条、第10.3.15条、第10.5.1条财政部、住房城乡建设部《关于完善建设工程价款结算有关办法的通知》(财建〔2022〕183号)第二条,https://www.gov.cn/zhengce/zhengceku/2022-06/30/content_5698595.htm新疆维吾尔自治区住房和城乡建设厅等《关于在房屋建筑和市政基础设施工程中开展施工过程结算试点工作的通知》(2022年3月24日)第四条,https://zjt.xinjiang.gov.cn/xjzjt/c113238/202205/917d2c70463647c6a159e0e4c12575a5.shtml2026-10-25 - 07
Composition differences between interim settlement by construction stage and the final account: stage settlement on three elements plus a five-item payment application, the final account on 13 listed items (GB/T 50500-2024 clauses 10.2 / 10.3)
Interim settlement by stage prices at settlement nodes: its composition…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.13、2.0.34、2.0.35条GB/T 50500-2024 第10.2.1、10.2.3、10.2.5、10.2.6、10.2.7、10.2.10条GB/T 50500-2024 第10.3.1、10.3.2、10.3.3、10.3.4、10.3.15条2026-10-18 - 08
GB/T 50500-2024 key points of the new China national pricing standard for BOQ for contractors (risk allocation / price adjustment for fluctuation / pricing of preliminary items / interim settlement by construction stage)
The new GB/T 50500-2024 changed from mandatory to recommended (GB/T). Co…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-29 - 09
Preventing over-settlement and duplicate settlement of subcontracted quantities: dual-signature locking of measurement + interim settlement by construction stage merged into the final account + the list of items not measured
Preventing over-settlement/duplicate settlement relies on procedural con…
GB/T 50500-2024 第7.1.7、7.1.8、7.5.5、9.1.13、10.2.3、10.3.12条TB 10402-2019 第6.0.1~6.0.8条DB37/T 5028-2022 第6.2.4条2026-09-25 - 10
The full path of site instructions/variation records into the final account: measurement certification, incorporation into settlement, and procedural time limits
Site instructions/variation records are measured as actually incurred an…
GB/T 50500-2024 建设工程工程量清单计价标准 第7.1、7.5、10.1~10.3节T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准 第10.6.1~10.6.3条GB/T 50875-2013 工程造价术语标准 第3.4.8条2026-09-25 - 11
Complete list of final-account compilation materials: input basis (codes' five/ten categories + practice's ten categories), deliverable composition, and linkage with stage settlement during construction
Compiling final-account materials splits into "input basis + output deli…
GB/T 51095-2015 第8.2.2、8.2.4条GB/T 50326-2017 第18.3.3条GB/T 50500-2024 第2.0.35、10.1.4、10.3.1、10.3.4条2026-09-25 - 12
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works w…
GB/T 50500-2024 建设工程工程量清单计价标准(第9.1~9.4、10.1~10.3、10.5节)财建〔2004〕369号 建设工程价款结算暂行办法建质〔2017〕138号 建设工程质量保证金管理办法2026-09-25 - 13
Identifying duplicate measurement in subcontract final accounts: a four-layer investigation method — contract interfaces, stage settlements during construction, measurement rules, and cost composition
Identify duplicate measurement in subcontract final accounts by investig…
T/ZBD 100.5-2023 工程结算审核作业指引GB/T 50500-2024 建设工程工程量清单计价标准DB37/T 5130-2018 建设工程造价咨询服务规范2026-09-25 - 14
Establishing monthly settlement and payment ledgers for subcontractors: two-tier architecture, field design, and the monthly cycle
Ledgers are two-tier: a project subcontract payment master ledger + a pe…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50319-2013 建设工程监理规范GB/T 51095-2015 建设工程造价咨询规范2026-09-25 - 15
In-process settlement linked to final account: preliminaries and main-contract service fees are interim payments that must be recalculated at final settlement (GB/T 50500-2024 Clauses 10.2.3/10.2.7/10.3.3)
For projects with in-process settlement, preliminaries costs (and main-c…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.2.3、10.2.7、10.3.3、7.3.1条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (已废止,仅对照)第11.2.2、11.2.3条2026-09-25 - 16
Document verification in subcontract final account disputes: a five-tier order of evidentiary weight (contract sets the tone → certification and sign-off lock quantities → drawings verify quantities → price evidence verifies prices → supporting evidence validates)
Documents in subcontract final account disputes are checked in tiers of…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 17
Quantifying advance-funding pressure when contract payment proportions are too low, and standard floors (GB/T 50500-2024: 80% progress payments, 10%-30% advance payment)
Every 10-point drop in the payment proportion adds roughly 10% of the co…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works《保障中小企业款项支付条例》(国务院令第728号)《保障农民工工资支付条例》2026-09-25 - 18
GB/T 50500-2024 pricing and settlement adjustment of main contractor's attendance and coordination provisions: per-item risk-inclusive pricing, percentage-rate based adjustment, interim settlement by construction stage, and recomputation at final account
Where the fee is priced per item, it is risk-inclusive except for deduct…
GB/T 50500-2024 第2.0.17、3.2.9、4.2.6、6.2.9、8.4.8、8.5.1~8.5.5、10.2.6、10.3.3条2026-09-25 - 19
Definition, classification hierarchy, and bases for handling the final account for construction works (GB/T 50500-2024)
The final account is the total-price settlement handled by the employer…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50326-2017 建设工程项目管理规范GB/T 51095-2015 建设工程造价咨询规范2026-09-25 - 20
Price reference time point for final account: adjust period by period per each measurement period's published price information (government guidance prices) during construction and aggregate; interim settlements by construction stage (China's 2020 milestone-based interim settlement system; no exact international equivalent) are incorporated without recomputation (not a single issue at the month of completion)
A final account has no 'single settlement-period price information': con…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2、Ch. 10、App. E.6.1GB/T 50875-2013 工程造价术语标准T/ZBD 100.1-2022 建设工程造价数据建设通用标准2026-09-25 - 21
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based prici…
GB/T 50500-2024 建设工程工程量清单计价标准(住建部公告 2024 年第 212 号;第1.0.1~1.0.3条、Ch. 8、App. A~G、前言)GB 50500-2013 建设工程工程量清单计价规范(已废止,对照)GB/T 50854-2024~GB/T 50862-2024 各专业工程量计算标准(配套计量体系)2026-09-25 - 22
Interim settlement by construction stage (stage settlement) in GB/T 50500-2024 (Section 10.2): node agreements, procedure flow, price calculation, and differences from the one-off final account under GB 50500-2013
GB/T 50500-2024 first establishes "interim settlement by construction st…
GB/T 50500-2024 建设工程工程量清单计价标准GB 50500-2013 建设工程工程量清单计价规范法释〔2004〕14号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释第二十条2026-09-25