Engineering Knowledge Cards.

interim settlement by construction stage

22 knowledge cards · sorted by most recently updated

Concept Guide

Concept

Background Promoted by the Ministry of Housing and Urban-Rural Development and other departments around 2020, interim settlement by construction stage moves settlement of the works from a single exercise after completion to a series of agreed milestones during construction. It targets the twin problems of settlements dragging on after completion and payment arrears.

Mechanics

  • Milestone-based: settlement units follow progress milestones or as agreed in the contract; on completing each milestone the parties produce an interim settlement document for the work and value completed.
  • Finality on signing: once reviewed and signed by both parties (with the engineer/QS), the document is not re-audited at completion but only aggregated. This is what distinguishes it from ordinary progress payments.
  • Linked to payment: the signed amount becomes the basis for later payment, fixing the payment obligation at each milestone and squeezing out arrears.
  • Disputed items carved out: undisputed value is settled first, so a single dispute cannot hold the whole settlement hostage.
  • Contract points: milestone definition and measurement basis, submission and review periods, deemed-acceptance effect of failure to reply, treatment of variations, claims and price adjustment, and linkage with the final settlement.

Versus progress payment Progress payments address cash flow only; interim settlement by construction stage progressively fixes the settlement itself.

Risk note Finality depends on the completeness and clarity of the signing procedure; signing quantities without prices weakens it.

FIDIC Mapping

Corresponding / adjacent terms FIDIC has no equivalent for interim settlement by construction stage (absent). The adjacent mechanisms are Sub-Clause 14.3 [Application for Interim Payment], 14.6 [Issue of Interim Payment Certificate], 14.10 [Statement at Completion] and 14.13 [Final Statement].

Key differences Interim payment under FIDIC is payment on account: applied for under 14.3 and certified by the Engineer under 14.6, it is no more than an assessment of value at the time. A certificate already issued is not final: where a significant error or discrepancy is found, the Engineer may withhold or adjust in a subsequent Statement (14.6), and the Contractor may include amounts it considers due in its next Statement. The account closes only gradually, through the Statement at Completion (14.10) and the Final Statement (14.13). In short, FIDIC interim payment stays open to review and non-final, with finality reached at the Final Statement; a Chinese interim settlement document, once signed, is final and not re-audited at completion. The policy contrast is deliberate: China finalises stage by stage to cut post-completion disputes and arrears, while FIDIC keeps each period provisional with one concluding account so that correction rights survive.

Usage cautions

  1. Do not read each IPC as a settled account: certification does not extinguish later correction or claims, so correspondence should preserve room for supplementation and adjustment.
  2. Do not import Chinese finality wording into a FIDIC contract: it conflicts with the correction mechanism at 14.6 and the closing of the account at 14.13; redraft as “undisputed portions confirmed, final adjustment reserved”.
  3. Terminology and effect: the benchmark English term is interim settlement by construction stage, and a FIDIC certificate or statement is not a settlement agreement in the Chinese sense — its effect rests on the contract, not on the label.
Chinese TermEnglish TermFIDIC TermRelationNotes
施工过程结算interim settlement by construction stage无对应术语;近缘 Sub-Clause 14.3 Application for Interim Payment、Sub-Clause 14.6 Issue of Interim Payment CertificateabsentFIDIC 期中支付为账目式付款,可复核、非终局,最终由 Final Statement 与 14.13 最终付款证书收口;过程结算签认即终局,制度取向不同。
过程结算文件的终局性finality of the signed interim settlement documentSub-Clause 14.6 Issue of Interim Payment Certificate、Sub-Clause 14.13 Issue of Final Payment CertificatedistinctFIDIC 下已签发 IPC 仍可在后续报表扣减更正,承包人也得在最终报表主张余额;不存在签认后不可复核的节点结算。
竣工后不再重复审核no re-audit after completionSub-Clause 14.10 Statement at Completion、Sub-Clause 14.13 Issue of Final Payment Certificatedistinct14.10 报表是竣工时点的账目,14.13 最终付款证书才定案;中国过程结算签认后仅作汇总,两者终局时点与效力层次不同。

Updated 2026-09-13