Price reference time point for final account: adjust period by period per each measurement period's published price information (government guidance prices) during construction and aggregate; interim settlements by construction stage (China's 2020 milestone-based interim settlement system; no exact international equivalent) are incorporated without recomputation (not a single issue at the month of completion)

A final account has no 'single settlement-period price information': contractual agreement takes precedence; where adjustment is agreed, base price C0 locks the price for the period 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered works, 28 days before contract signing), while measurement-period price Ci is taken period by period using the published price information (government guidance prices) issued for the corresponding construction completion period (month/quarter), adjusted and accumulated period by period; confirmed interim settlements by construction stage are incorporated directly into the final account without re-measurement or re-pricing; where the published price information for a given period has not been issued, that period's published prices may be used provisionally, with subsequent payments adjusted on an actual basis.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2、Ch. 10、App. E.6.1
  • GB/T 50875-2013 工程造价术语标准
  • T/ZBD 100.1-2022 建设工程造价数据建设通用标准

Topic Positioning

The core principle of the price reference time point for the final account: it is not a "single issue of published price information (government guidance prices)" at the month of completion or the month in which the final account is processed, but rather contractual agreement takes precedence; where adjustment is agreed, prices are taken period by period according to the published price information corresponding to each measurement period during construction, adjusted period by period, and aggregated into the final account.

Core Conclusions

1 Contractual agreement takes precedence: the method for determining the final account price and the adjustment method follow the construction contract first; in the absence of agreement, they follow the pricing principles and the pricing bases published by cost administration agencies.

2 Where adjustment is agreed: base price C0 locks the price for the period 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered works, 28 days before contract signing) and remains fixed throughout; measurement-period price Ci takes the published price information (government guidance prices) issued for the corresponding measurement period (month/quarter) in which construction is completed; where construction spans N periods, the published price information for those N periods is used to calculate and accumulate the differences period by period (GB/T 50500-2024 Appendix A.2.1).

3 Where the published price information for a given period has not been issued, the published prices for that period may be used provisionally for calculation, and subsequent payments are adjusted according to actual prices (A.2.2); where multiple prices exist within a period, the arithmetic mean, the weighted average with completed quantities, or the price for the main consumption period may be adopted, as agreed by both parties (A.2.3); only the portion exceeding the risk band (no-adjustment tolerance, e.g. ±5%) is adjusted on an actual basis, and the basis for calculating the excess is determined by the relationship between the tender price and the base price (A.2.4).

4 Documents for interim settlement by construction stage (China's 2020 milestone-based interim settlement system; no exact international equivalent) signed and confirmed by both employer and contractor shall form part of the final account, and the final account shall not re-measure or re-price them (Clause 10.2.3); the final account shall be handled on the basis of the stage settlement documents during construction plus the quantities of the unfinished final period, accurate re-measurement of preliminaries/main contractor's attendance and coordination provisions, and outstanding adjustment matters (Clause 10.3.1).

5 Aggregation basis: in the final account summary table, adjustment for changes in costs is listed separately as "contract price adjustment amount", to be filled in after aggregating the period-by-period price adjustment results (Appendix E, Table E.6.1).

Applicable Boundaries

Applies to final accounts (and interim settlements by construction stage) of employer-contractor contracts that agree to adjustment according to published price information (government guidance prices); fixed lump-sum or non-adjustment contracts do not involve price taking. The source of the base price, the price-taking periods, and the risk band (no-adjustment tolerance, e.g. ±5%) shall all follow the tender documents and contractual agreement (A.2.1); where they are inconsistent with local pricing regulations, follow the contractual agreement and the local cost agency's basis.