GB 50500-2013 terms for measurement of the works and construction payment settlement (final account): definitions, clause anchors, side-by-side comparison, and the rules that carry confirmed measurements into the settlement summary, with the corresponding clauses of GB/T 50500-2024
GB 50500-2013 clause 2.0.43 defines 'measurement of the works' as the calculation and confirmation, by the employer and the contractor in accordance with the contract, of the quantities of the contract works completed by the contractor; clause 2.0.44 defines 'construction payment settlement' as the calculation, adjustment and confirmation of the contract price for the contract works during execution, upon termination and after completion (covering interim settlement, termination settlement and the final account); clause 2.0.51 gives the price-level term 'final account price'. Boundary: measurement answers 'how much is completed, is it acceptable, can it be paid' and is the basis for interim payment (mandatory clause 8.1.1 plus clause 10.3.1); settlement answers 'what is the total due and how is it closed out', handled after completion of the works under mandatory clause 11.1.1. The hinge is clause 11.2.6: measurement results and contract prices already confirmed during execution 'enter the final account directly', and clause 11.2.1 confirms there is no need 'to re-measure and re-price everything'; in lump-sum contracts let on approved drawings plus budgets, each item's quantity is the final quantity for settlement except for additions and omissions from variations (clause 8.3.2). GB/T 50500-2024 replaces these with clause 2.0.34 'interim settlement by construction stage' and clause 2.0.35 'construction payment settlement' (covering interim settlement by construction stage, settlement upon termination of the contract, the final account and closure of the works warranty account), with clauses 7.1.8, 10.2.3, 10.3.1 and 10.3.3 carrying the same logic and carving out exceptions for preliminaries and for the main contractor's attendance and coordination provisions.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.34、2.0.35、7.1.1、7.1.4、7.1.5、7.1.7、7.1.8、8.11.22、9.4.1、9.4.13、10.1.4、10.2.1、10.2.3、10.2.7、10.3.1、10.3.2、10.3.3、10.3.4、10.3.7、10.3.8、10.3.10、10.3.11、10.3.16条、Ch. 11
- GB/T 50875-2013 · Standard glossary of project costs 第3.4.3、3.4.9条
- GF-2017-0201《建设工程施工合同(示范文本)》第12.3.2、12.3.3、12.3.4项、第12.4.2、12.4.3、12.4.4项
- 建设部令第107号《建筑工程施工发包与承包计价管理办法》第十六条
What this card covers
Clarifies, within the pricing code, the hierarchy between 'measurement of the works' and 'construction payment settlement (final account)': the clause sources of both, four boundary differences, and how confirmed measurement results roll into the final account summary, with the corresponding clause numbers of GB/T 50500-2024 so that clauses can be cited correctly under the version agreed in the contract.
Core conclusions
1. Verbatim terms of GB 50500-2013
- Clause 2.0.43 measurement of the works: 'The employer and the contractor shall, in accordance with the contract, calculate and confirm the quantities of the contract works completed by the contractor.'
- Clause 2.0.44 construction payment settlement: 'The employer and the contractor shall, in accordance with the contract, calculate, adjust and confirm the contract price of the contract works during execution, upon termination and after completion. It covers interim settlement, termination settlement and the final account.'
- Clause 2.0.51 final account price: 'The total contract amount payable by the employer to the contractor when the contractor has completed all contracted work, determined under the relevant state laws, regulations and standards and as agreed in the contract, including the contract price adjustments made under the contract during its performance.'
Term-system note: the 2013 edition carries no separate term entry for 'final account' - it is a sub-category of clause 2.0.44 'construction payment settlement' (alongside interim settlement and termination settlement); the price-level counterpart is clause 2.0.51 'final account price'. Measurement of the works and construction payment settlement are therefore two functional stages within one system, not two parallel documents of equal rank.
2. Chapter and clause anchors
Chapter 8 Measurement of the works
- 8.1 General provisions: Clause 8.1.1 (mandatory provision) 'Quantities must be calculated in accordance with the measurement rules in the current national measurement standards applicable to the relevant works.' Commentary: 'Correct measurement is the precondition and the basis for the employer to pay the contract price to the contractor.' (this clause is a mandatory provision and must be strictly enforced)
- Clause 8.1.2 'Measurement of the works may be carried out monthly or in stages by physical progress, and the specific measurement period shall be agreed in the contract.' (where staged settlement is adopted, the boundaries of the stages of the works shall be agreed in the contract)
- 8.2 Measurement under unit-rate contracts: Clause 8.2.3 'The contractor shall submit to the employer, at the measurement period and time agreed in the contract, a report on the quantities completed in the current period. The employer shall verify the report within 7 days of receipt and notify the contractor of the verified measurement. If the employer fails to verify within the agreed time, the quantities stated in the contractor's measurement report are deemed to be the quantities actually completed by the contractor.'
- 8.3 Measurement under lump-sum contracts: Clause 8.3.2 'In a lump-sum contract let on the basis of construction drawings approved on review and the budget prepared therefrom, the quantity of each item of the works shall be the final quantity used by the contractor for settlement, except for additions to and omissions from quantities under the variation provisions.' (commentary: this is the most essential difference from unit-rate contracts)
Chapter 11 Final account and payment
- Clause 11.1.1 (mandatory provision) 'After completion of the works, the employer and the contractor must complete the final account of the works within the time agreed in the contract.' (this clause is a mandatory provision and must be strictly enforced)
- Clause 11.2.1 (seven bases for preparation and review): '1 this code; 2 the contract; 3 the quantities confirmed by both parties during performance and the contract prices settled thereon; 4 the contract prices added (deducted) after confirmed adjustments during performance; 5 the design documents of the construction project and related information; 6 the tender documents; 7 other bases.' Commentary: 'The records that both parties have measured, priced and certified during performance of the contract shall be used; there is no need to re-measure and re-price everything.'
- Clause 11.2.6 'The measurement results of the works and the contract prices already confirmed by both parties during performance of the contract shall enter the final account directly.' (except for disputed items, all shall go directly into the final account, streamlining the settlement process)
- Clause 11.3.1 'After completion of the contract works, the contractor shall compile the final account documents by summarising the interim price settlements confirmed by both parties, and shall submit them to the employer together with its application for taking-over. If the contractor fails to submit the final account documents within the time agreed in the contract and, after demand by the employer, still fails to submit them or give a definite reply within 14 days, the employer may compile the final account documents from the records already available, as the basis for settling the final account and paying the settlement monies, and the contractor shall accept them.'
3. Side-by-side comparison (two stages of the same project)
| Item | Measurement of the works (Chapter 8) | Settlement / final account (Chapter 11) |
|---|---|---|
| Purpose | Confirm the completed quantities actually executed by the contractor and due to be measured | Close out the whole contract price (including the roll-up of adjustment items from the process) |
| Timing | Period by period, per the measurement period agreed in the contract (monthly or staged by physical progress) (clause 8.1.2) | Handled after completion of the works, within the time agreed in the contract (clause 11.1.1); interim price settlement separately under clause 10.3.1 |
| Basis | The contract + the measurement rules of the current national measurement standards + completed acceptable work (clauses 8.1.1, 8.2.3) | The seven bases of clause 11.2.1: this code, the contract, quantities and settled prices confirmed during performance, confirmed added (deducted) prices, design documents, tender documents, others |
| Effect | Confirmed measurement is the precondition and basis for the employer to pay the contract price, serving as the basis for interim / progress payment (commentary on clause 8.1.1; clause 10.3.1) | Confirmed settlement is the basis for final payment (the final account price = the total contract amount payable by the employer to the contractor, clause 2.0.51) |
| Depth of work | Quantity check each period (the employer verifies within 7 days of receiving the report; overdue verification is deemed acceptance, clause 8.2.3) | Roll up the process records without repeating measurement and pricing (commentary on clause 11.2.1); confirmed parts enter directly (clause 11.2.6) |
4. Rules linking confirmed measurement into the settlement summary
- Measurement precedes payment: clause 8.1.1 establishes the measurement-payment chain; clause 10.3.1: 'The employer and the contractor shall, at the times, by the procedure and by the method agreed in the contract, settle interim prices and pay progress payments on the basis of the measurement results.'
- Confirmed results are carried in: clause 11.2.6 requires measurement results and contract prices confirmed during the process to enter the final account directly, with no second round of checking and confirmation.
- The review basis of settlement is the process certification records: clause 11.2.1 lists 'the confirmed quantities and the contract prices settled thereon' and 'the contract prices added (deducted) after confirmed adjustments' as bases for settlement, showing that settlement = the roll-up of process measurement results and process price adjustments, not a fresh calculation.
- Special link for lump-sum contracts: clause 8.3.2 provides that in lump-sum contracts formed on approved construction drawings and the budget thereof, the quantity of each item is, except for quantity changes caused by variations, the contractor's final quantity for settlement - the process measurement result locks the settlement quantity.
- Timing link: final account documents are submitted together with the application for taking-over; if not submitted within the agreed time and still not submitted within 14 days after demand, the employer may compile them from the available records and the contractor shall accept them (clause 11.3.1).
5. Corresponding clauses of GB/T 50500-2024
- Terms: clause 2.0.34 interim settlement by construction stage: 'the activities of calculating, adjusting, confirming and paying the contract price for the completed works at the interim settlement nodes, by the employer and the contractor under the laws and regulations and the contract'; clause 2.0.35 construction payment settlement: '...activities of calculating, adjusting, confirming and paying the contract price for the project items during execution of the contract works, upon termination of the contract and after completion, covering interim settlement by construction stage, settlement upon termination of the contract, the final account and closure of the works warranty account' (interim settlement by construction stage is also called interim settlement, covering monthly, quarterly, annual and physical-progress-node settlements; the final account is divided into three levels: unit works, single-item works and the construction project)
- Measurement: clause 7.1.1: 'The contract works shall be measured on what the contractor has completed as required by the contract and what is due to be measured. Quantities shall be calculated in accordance with the national and industry quantity standards for the relevant works agreed by both parties and with any supplementary measurement rules.'; clause 7.1.8: 'Measurement results signed and confirmed by both parties serve as the basis for adjusting the contract price and for settlement of the works, except where the contract provides otherwise, or the parties expressly limit them to a basis for progress payment, or the measurement result is a rough estimate.'
- Payment cycle: clause 9.4.1: '...progress payments for completed work are measured and paid at each measurement period, and the measurement period shall be consistent with the payment period. Where the progress payment measurement period is not clearly agreed in the contract, measurement and payment may be made monthly.'
- Settlement link: clause 10.2.3: 'Except as provided in clause 10.2.7 of this standard, interim settlement documents by construction stage signed and confirmed by both parties form part of the final account documents, and the final account shall not re-measure or re-price them.' (preliminaries and the main contractor's attendance and coordination provisions are provisional payments, adjustable under clause 10.3.3); clause 10.3.1: 'After completion of the works, both parties shall, as agreed in the contract and under clause 10.2.1 of this standard, and on the basis of all interim settlement documents signed and confirmed by both parties, compile and check within the agreed time ... the final account and interim settlement by construction stage are intrinsically linked: unless the contract provides otherwise, the interim settlement prices are the basis of the final account, and the final account price may be calculated by the following formula:' (the clause gives the formula for the final account price); clause 10.3.3: at the final account, preliminaries and the main contractor's attendance and coordination provisions must be re-calculated and determined under clause 7.3, Chapter 8 and clause 8.5, and the two amounts charged in interim settlements 'shall not serve as the basis for the final account of the works'.
- Key differences: the 2024 edition systematises 'interim settlement' into 'interim settlement by construction stage' and brings 'settlement upon termination' and 'closure of the works warranty account' within the outer bounds of construction payment settlement; the 2024 edition is a recommended standard (GB/T) and its clauses carry no 'mandatory provision' wording.
Applicable boundaries
- Versions: GB/T 50500-2024 is the current edition; legacy contracts that expressly adopt GB 50500-2013, and disputes traced back to it, are handled under the 2013 clauses. 'Mandatory provision' wording appears only in the 2013 edition (clauses 8.1.1 and 11.1.1) and must not be transplanted onto 2024 clauses.
- Clause 8.3.2 ('the quantity is the final quantity for settlement') applies only to lump-sum contracts let on approved construction drawings and the budget thereof; lump-sum contracts formed through BOQ tendering follow the measurement rules for unit-rate contracts (clause 8.3.1 of the 2013 edition).
- The premise of clause 11.2.1 ('no need to re-measure and re-price everything') is that the process records have been measured, priced and certified by both parties; disputed parts must still be re-verified.
- The 2024 edition carves out exceptions for preliminaries and the main contractor's attendance and coordination provisions within interim settlements (clauses 10.2.3, 10.3.3): these two items must be re-calculated at the final account, and 'interim settlement is not re-measured or re-priced' cannot be applied across the board.
- The clauses in this card follow the general BOQ pricing code for building and municipal engineering works; where sectoral works (highway, water conservancy, railway, etc.) have their own industry measurement rules, the measurement standard agreed in the contract governs.
Further reading
- GB 50500-2013 (code for BOQ pricing of construction works): Chapter 2 terms, clauses 2.0.43, 2.0.44, 2.0.51; Chapter 8 'Measurement of the works', 8.1 (8.1.1, 8.1.2), 8.2 (8.2.3), 8.3 (8.3.2); Chapter 10 'Interim payment of contract prices', clause 10.3.1; Chapter 11 'Final account and payment', 11.1.1, 11.2.1, 11.2.6, 11.3.1.
- GB/T 50500-2024 (standard for BOQ pricing of construction works): Chapter 2 terms, clauses 2.0.34, 2.0.35; Chapter 7 'Measurement of contract works', 7.1.1, 7.1.8; Chapter 9 'Interim payment of contract prices', 9.4.1; Chapter 10 'Settlement and payment', 10.2.3, 10.3.1, 10.3.3.
- Extensions: the deemed-acceptance rule for overdue measurement disputes (7-day verification under clause 8.2.3 of the 2013 edition), measurement under lump-sum contracts (clause 8.3), and the anti-duplication rule for rolling interim settlements into the final account (clause 10.2.3 of the 2024 edition).