Reconciling the three output-value bases of construction output, measured output and settlement output: item-by-item basis distinction, four classes of difference attribution, the disallowance-and-resubmission tests, and the tie-out with stage settlement documents

Construction output value (physical-progress statistics basis), measured output value (contract basis of qualified quantities certified by the supervising engineer or employer) and settlement output value (contract entitlement basis) are three non-overlapping measurement boundaries; the aim of reconciliation is not to make the three figures equal, but - anchored on the measured output value - to place every difference item by item into the accounts of (1) not yet submitted, (2) measurement period not yet reached, (3) quality not yet confirmed, (4) variations not yet priced held in suspense (plus basis differences and permanent removals), until the residual is zero. Disallowance or resubmission must simultaneously pass the measurement-conditions tests (within the BOQ, an approved variation or dayworks scope; quality qualified with acceptance complete; per the contract calculation rules; within the measurement period; the variation priced or on a provisional price; the Notice of Claim issued within 28 days). Payment of interim settlement by construction stage shall be no less than 80% of the current stage settlement total (GB/T 50500-2024 clause 10.2.4), and stage settlement documents signed and confirmed merge into the final account without re-measurement or re-pricing (clause 10.2.3).

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第7.1.5、7.1.7、7.1.8、8.9.1、8.11.3、8.11.21、9.4.1、9.4.9、9.4.13、10.1.6、10.2.1、10.2.3、10.2.4、10.2.8、10.3.2、10.3.14条
  • GB/T 50319-2013 · Code for Construction Project Supervision 第5.3.1、6.3.4条
  • DBJ41/T 208-2018 · Standard for Construction Project Supervision Work (Henan) 第7.3.2条
  • DB11/T 382-2017 · Specification for Construction Project Supervision (Beijing) 第5.3.5条
  • 国家统计局建筑业总产值指标解释:https://www.stats.gov.cn/zs/tjws/tjzb/202301/t20230101_1903951.html
  • 国家统计年鉴建筑业指标:http://www.stats.gov.cn/sj/ndsj/2021/html/zb14.htm

Positioning

This card sets out the item-by-item distinction among the three bases - construction output value (statistics basis), measured output value (contract measurement basis certified by the supervising engineer or the employer) and settlement output value (contract entitlement basis) - the attribution of differences, the disallowance and resubmission tests, and the tie-out with stage settlement documents, for three-basis reconciliation at monthly measurement and payment and at stage settlement nodes.

Core conclusions

1. Basic judgement: the three output values are not 'one figure at three points in time' but three non-overlapping measurement boundaries. The right reconciliation is not to force the three figures equal, but to anchor on the measured output value and place every difference item by item into an account with a clear destination, until the residual is zero.

2. Item-by-item distinction of the three bases

Distinguishing item Construction output value (statistics basis) Measured output value (contract measurement basis) Settlement output value (contract entitlement basis)
Object measured Physical quantities actually completed in the reporting period per physical progress (counted once done, including unaccepted portions) Completed qualified quantities meeting the measurement conditions (within the BOQ, approved variations, dayworks records) Contract BOQ + all confirmed adjustments - liquidated damages deductions
Price basis Completed quantity x budget rates, then percentage on-costs, profit and tax Contract BOQ all-in unit rates; variations converted by the same or similar rates or priced by negotiated build-up The same rates as the measured output value, but at final prices (provisional prices to confirmed prices; provisional sums adjusted as executed)
Time boundary The statistical reporting period (month / quarter), judged by physical progress The contract measurement period; the measurement period should be consistent with the payment period, and where the contract is silent, measurement and payment may be made monthly in instalments (GB/T 50500-2024 clause 9.4.1); local rules often set the 26th of the previous month to the 25th of the current month (DB11/T 382-2017 clause 5.3.5) The stage settlement nodes agreed in the contract, or after the works pass taking-over
Confirmation procedure Internal review by the enterprise, no counterparty sign-off The contractor submits in writing -> the employer replies in writing with the checking result within the agreed time; where the employer fails to provide the checking result within the agreed time, the measurement submitted by the contractor may be deemed accepted by the employer and, save as otherwise agreed in the contract, serve as the basis for calculating the works price, but it shall not serve as evidence that the relevant works have been accepted as qualified (clause 7.1.5); the parties sign on the measurement result they agree (clause 7.1.7), and failing agreement chapter 11 dispute resolution applies (clause 7.1.7); the measurement returns of successive periods are totalled and signed on the summary sheet (clause 9.4.13) Prepared by the contractor -> checked and confirmed by the employer (or the construction cost consultant it commissions); the stage settlement documents signed by both parties
Quality-unconfirmed portions Included (done by physical progress) Excluded: unaccepted or failing acceptance, incomplete inspection documents, non-conformity with the contract and design documents, rework attributable to the contractor, quantities beyond the measurement rules - none of these is measured (DBJ41/T 208-2018 clause 7.3.2) Excluded; quality disputes handled case by case under 'settle the undisputed part first' (clause 10.3.14)
How variations enter Executed portions counted by physical progress Only approved or confirmed variations; where the rate is unset, interim payment at a provisional price, the variation sum finally settling on the agreement reached between the employer and the contractor (GB/T 50319-2013 clause 6.3.4) All confirmed variation increases and decreases at the final prices
Claims / dayworks Generally not counted separately Confirmed amounts enter the progress or stage settlement payment of the same period (clause 8.11.21) All confirmed amounts
Deductions None (an output concept) No deduction of advance payment, retention money or liquidated damages (these are payment-side matters) The contractor's liquidated damages deducted (clause 10.2.1)
Basis documents The 'construction industry output value' indicator interpretation of the national statistics system The contract, the priced BOQ, the signed measurement returns The stage settlement documents, the final account documents

3. Enumerated difference sources and the direction of reconciliation

Difference class Test Direction Disposition
(1) Not yet submitted Completed, qualified, within contract, but not entered in this period's return A>B Submit next period; beyond the contract submission period, treated as late
(2) Measurement period not reached Progress made but falling in the next measurement interval A>B Hold; rolls into the next period automatically; flagged 'cross-period' in the register
(3) Quality not confirmed Unaccepted, failing acceptance, incomplete documents, rework A>B Not measured; resubmitted under the current rules once rectified; reworked portions permanently removed
(4) Variations unpriced, held in suspense Instruction issued, quantity confirmed, rate unset A>B Interim payment at the provisional price; reversed at settlement at the agreed price
(5) Basis differences Different rate bases (budget quota versus contract all-in unit rate), different on-costs or tax, free-issue materials, main contractor's attendance and coordination provisions Both directions Build a 'same-basis bridge'; explain, do not offset
(6) Permanent removal Beyond the construction drawings with no variation, unlawful subcontracting, beyond the measurement rules - Removed from A and B together

4. The disallowance and resubmission checklist (tick item by item; only when all are satisfied may the item be resubmitted)

  1. Within the contract BOQ items, an approved variation or a dayworks record;
  2. Meeting the quality requirements agreed in the contract, with complete acceptance procedures;
  3. Measured per the quantity calculation rules agreed in the contract (drawn dimensions / actual measurement / certified records);
  4. Within this measurement period;
  5. The variation with an approved instruction and a confirmed rate (unset rates on the provisional price);
  6. The claim notified by a written Notice of Claim within the period agreed in the contract after the event (28 days where the contract is silent) - late notice is dealt with per the contract and, save as otherwise agreed in the contract or otherwise provided by laws and regulations, may be treated as waiver of the relevant claim (clause 8.11.3);
  7. No permanent-removal ground such as works beyond the drawings, rework or unlawful subcontracting.

Flow of the conclusion: pass -> resubmit; fail but rectifiable -> held as 'pending resubmission'; not rectifiable -> disallowed, marked not to be resubmitted.

5. The tie-out with the stage settlement documents

  • The bases for compiling the stage settlement include: the construction contract documents and supplementary agreements (including the priced BOQ); this standard and the related measurement standards; the contract drawings, the actual construction drawings and the survey and design data; the contract specification and supplementary technical specifications; the bid and tender documents; the approved or confirmed variation, dayworks and claim documents; the quantities and prices both parties have confirmed for the current period; and the contract price adjustments confirmed for the current period (clause 10.2.1).
  • The stage settlement contains the relevant contract prices within the contract total for the settlement period or node, the contract price adjustments agreed by the parties, and the contractor's liquidated damages deductions as agreed in the contract (clause 10.2.1).
  • The payment percentage shall be agreed in the contract and shall be no less than 80% of the total of the current stage settlement (clause 10.2.4).
  • The stage settlement documents signed by both parties form part of the final account documents, and the final account shall not re-measure or re-price them; the preliminaries and main contractor's attendance and coordination provisions within them are of a provisional-payment nature, may be computed proportionally, and are re-measured accurately at the final account per the contract (clause 10.2.3).
  • Where the contractor fails to submit the stage settlement documents and, after the employer's reminder, still fails to submit as required or gives no clear reply, the employer may compile them from the available documents and ask the contractor to confirm; where the contractor confirms without objection or gives no clear reply within the agreed time, the documents compiled by the employer are deemed accepted and serve as the basis for the stage settlement and payment (clause 10.2.8).
  • Three reconciliation checks: A - B = the sum of the listed difference classes (the residual must be 0 - otherwise the differences are not exhausted and the monthly report must not be issued); B - C = the amounts measured but not yet in the stage settlement (preliminaries provisionally proportioned, variations outside the nodes, quantities short of a settlement node); current payable = C x the contract payment percentage (no less than 80%) - recovery of the advance payment - retention money - liquidated damages - withholdings; the payable is not C - do not mix them.

Application boundaries

  • Applies to three-basis reconciliation of interim payments, interim settlement by construction stage and the run-up to the final account under construction contracts priced on a BOQ basis; the measurement and payment certification procedure on the supervision side is in GB/T 50319-2013 clause 5.3.1 (the professional supervising engineer checks the quantities and payment amounts -> the chief supervising engineer reviews, certifies and reports to the employer -> the payment certificate is issued per the approval; the review covers the contract price of the works executed to date, variation increases and decreases, claim increases and decreases, advance payments and their recovery, retention money, and other adjustments).
  • Construction output value is a statistics-basis indicator, construed per the national statistics interpretation of 'construction industry output value' (covering building works output, installation works output and other output, excluding output beyond the border and counted by place of enterprise registration); it serves only statistical returns and internal assessment and must not be used directly as a basis for contract collection or settlement.
  • Not applicable: fixed-lump-sum contracts with no measurement procedure; output statistics of non-works categories; differences already in dispute review, mediation, arbitration or litigation - these move to a dispute register in suspense and are not offset in the reconciliation.
  • Quality objections must not be flatly resolved as 'unaccepted means uncounted': where the works have passed taking-over, or are complete but unaccepted yet put to premature use by the employer, quality disputes follow the warranty contract or clauses and the final account follows the contract; where the works are complete, unaccepted and unused, and for suspended or abandoned works, the disputed part may be tested and assessed or handled per the decision of the quality authority before the final account is settled, the undisputed part being settled per the contract (clause 10.3.14).
  • The amounts here are stated as formulas; substitute the payment percentages, recovery and retention rules of the specific contract.

Further reading

  • GB/T 50500-2024, the China national pricing standard for BOQ: clauses 7.1.5, 7.1.7 and 7.1.8 (submission and sign-off of measurement results, and their use as pricing basis); clause 8.9.1 (the five cases of setting all-in unit rates where variations or BOQ defects change items or quantities); clauses 8.11.3 and 8.11.21 (claims procedure and same-period payment); clauses 9.4.1, 9.4.9 and 9.4.13 (measurement period consistent with payment period; progress payment application and the cumulative-difference method; totalling and sign-off of successive measurement returns); clauses 10.1.6, 10.2.1, 10.2.3, 10.2.4, 10.2.8, 10.3.2 and 10.3.14 (bases and content of the stage settlement; merger into the final account without recalculation; the 80% payment percentage; compilation by the employer; final account listing; handling of quality objections).
  • GB/T 50319-2013 (code for supervision of construction works): clause 5.3.1 (measurement and payment certification procedure, progress payment review content, deduction of retention money); clause 6.3.4 (variation provisional prices and the basis of final settlement).
  • DBJ41/T 208-2018 (standard for supervision work): clause 7.3.2 (measurement scope, quality and acceptance requirements, non-measurable cases); DB11/T 382-2017 (supervision rules): clause 5.3.5 (measurement period preferably from the 26th of the previous month to the 25th of the current month; unforeseeable quantities measured as executed with photographic records kept).
  • National statistics interpretation of the construction output value indicator: https://www.stats.gov.cn/zs/tjws/tjzb/202301/t20230101_1903951.html ; yearbook construction indicators: http://www.stats.gov.cn/sj/ndsj/2021/html/zb14.htm