Determining the progress-payment ratio and the payment sign-off procedure (GB/T 50500-2024 §9.1/§9.4 + GB/T 50319-2013 §5.3.1)

The ratio is set by three layers — "contract agreement first -> national-standard floor -> local mandates": absent agreement, no less than 80% of cumulative completed value (9.1.7); current payable = cumulative completed price - cumulative paid - current deductions (9.1.6, 9.4.9); the work-safety measure advance is not recovered from progress payments (9.3.2); the procedure runs contractor applies -> specialty supervision rechecks -> chief supervision engineer endorses -> employer approves -> chief supervision engineer issues the certificate (GB/T 50319-2013 §5.3.1); the retention base excludes advances and price-adjustment amounts.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50319-2013 建设工程监理规范

Topic Positioning

Answers "how is the progress-payment ratio determined and what is the payment procedure": three rules (contract agreement -> national floor -> local mandates) plus the supervision payment sign-off flow.

Core Conclusions

The ratio follows "contract agreement first -> national-standard floor -> local mandates": agreed ratios apply; absent agreement, no less than 80% of cumulative completed value (GB/T 50500-2024 Clause 9.1.7); government-invested projects must also satisfy the local mandatory provisions. Amounts by the difference method: current payable = cumulative completed price - cumulative paid - current deductions (Clauses 9.1.6, 9.4.9); the cumulative completed value lists the 11 items per Clause 9.4.9 (including BOQ defects, provisional sums and prices, main-contractor service fee, dayworks, prices, regulation/policy, changes, new works, claims, and other adjustments). The work-safety measure advance is not recovered from progress payments (Clause 9.3.2); disputed items are certified and paid first on undisputed parts (Clause 9.4.11). Procedure (GB/T 50319-2013 Clause 5.3.1): specialty supervision rechecks quantities -> chief supervision engineer endorses for employer approval -> certificate issued; the retention base excludes advance payments and price-adjustment amounts.

Applicable Boundaries

"No less than 80%" is a recommended guiding floor, not a mandatory provision; government-invested projects must also satisfy local mandates. Absent an agreed measurement period, measure monthly in installments (Clause 9.4.1). Interim settlement by construction stage and final account listings are out of scope (interim settlement by construction stage has its own no-less-than-80% requirement, Clause 10.2.4).

Further Reading

GB/T 50500-2024 Chapter 9: 9.1.6, 9.1.7, 9.1.8, 9.4.9, 9.4.11; Section 9.2 advances, Section 9.3 work-safety measure fee (9.3.2: 50% prepaid within 28 days of commencement); Appendix F.3.1 payment application (approval) form. GB/T 50319-2013 Clause 5.3.1.