Determining the progress-payment ratio and the payment sign-off procedure (GB/T 50500-2024 §9.1/§9.4 + GB/T 50319-2013 §5.3.1)
The ratio is set by three layers — "contract agreement first -> national-standard floor -> local mandates": absent agreement, no less than 80% of cumulative completed value (9.1.7); current payable = cumulative completed price - cumulative paid - current deductions (9.1.6, 9.4.9); the work-safety measure advance is not recovered from progress payments (9.3.2); the procedure runs contractor applies -> specialty supervision rechecks -> chief supervision engineer endorses -> employer approves -> chief supervision engineer issues the certificate (GB/T 50319-2013 §5.3.1); the retention base excludes advances and price-adjustment amounts.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50319-2013 建设工程监理规范
Topic Positioning
Answers "how is the progress-payment ratio determined and what is the payment procedure": three rules (contract agreement -> national floor -> local mandates) plus the supervision payment sign-off flow.
Core Conclusions
The ratio follows "contract agreement first -> national-standard floor -> local mandates": agreed ratios apply; absent agreement, no less than 80% of cumulative completed value (GB/T 50500-2024 Clause 9.1.7); government-invested projects must also satisfy the local mandatory provisions. Amounts by the difference method: current payable = cumulative completed price - cumulative paid - current deductions (Clauses 9.1.6, 9.4.9); the cumulative completed value lists the 11 items per Clause 9.4.9 (including BOQ defects, provisional sums and prices, main-contractor service fee, dayworks, prices, regulation/policy, changes, new works, claims, and other adjustments). The work-safety measure advance is not recovered from progress payments (Clause 9.3.2); disputed items are certified and paid first on undisputed parts (Clause 9.4.11). Procedure (GB/T 50319-2013 Clause 5.3.1): specialty supervision rechecks quantities -> chief supervision engineer endorses for employer approval -> certificate issued; the retention base excludes advance payments and price-adjustment amounts.
Applicable Boundaries
"No less than 80%" is a recommended guiding floor, not a mandatory provision; government-invested projects must also satisfy local mandates. Absent an agreed measurement period, measure monthly in installments (Clause 9.4.1). Interim settlement by construction stage and final account listings are out of scope (interim settlement by construction stage has its own no-less-than-80% requirement, Clause 10.2.4).
Further Reading
GB/T 50500-2024 Chapter 9: 9.1.6, 9.1.7, 9.1.8, 9.4.9, 9.4.11; Section 9.2 advances, Section 9.3 work-safety measure fee (9.3.2: 50% prepaid within 28 days of commencement); Appendix F.3.1 payment application (approval) form. GB/T 50319-2013 Clause 5.3.1.
Keywords
- 工程进度款
- 支付比例
- interim payment
- 计量支付
- payment certificate
- 监理签证
- retention money
- 合同价款期中支付
Related Cards
- →
Contractor cash-flow risk control when progress-payment review runs overdue: deemed approval of measurements, payment of undisputed portions, and four-layer defense (GB/T 50500-2024)
Review deadlines are not bottomless: absent contractual deadlines, GB/T 50500-2024 Article 7.1.5 establishes "overdue silence = measurement accepted," Article 9.4.11 "undisputed portions paid first," and Article 9.1.7 payment no less than 80% of cumulative completed work value; overdue non-payment supports claims under 9.4.12, and in extreme cases priority-of-payment under Civil Code Article 807 (exercisable within 18 months) and the Regulation on Payment to SMEs. Defense deploys across four layers: contract clauses - process management - legal remedies - self-rescue financing.
- →
Quantifying advance-funding pressure when contract payment proportions are too low, and standard floors (GB/T 50500-2024: 80% progress payments, 10%-30% advance payment)
Every 10-point drop in the payment proportion adds roughly 10% of the contract amount in advance funding: peak advance = (1 - payment proportion) x contract amount; average advance ~= peak/2; annual financing cost ~= average advance x annual rate. GB/T 50500-2024: progress payments should not be below 80% of cumulative completed work value (9.1.7); in-process settlement not below 80% (10.2.4); advance payment not below 10% and not above 30% of contract price (9.2.2). Advance funding stacks migrant-wage, supply-chain, and tax-prepayment chain risks; the Regulation on Payment to SMEs (30/60-day terms and overdue interest) can be invoked for relief.
- →
Calculation of progress payments (GB/T 50500-2024 §9.1/§9.4): the cumulative-difference method, the 11-item composition of cumulative completed value, and payment/deduction rules
Current payable progress payment = cumulative completed value to date − cumulative paid price − current deductions (GB/T 50500-2024 Clauses 9.1.6, 9.4.9); absent an agreed ratio, payment should be no less than 80% of cumulative completed value (9.1.7); the cumulative value comprises 11 items — contract BOQ price, BOQ errors/omissions adjustments, provisional sums, adjustments of provisional prices after procurement, main contractor's attendance and coordination provisions, dayworks, changes in costs, regulation/policy changes, variations, additional works, claims; the statutory safety provisions advance may not be recovered from progress payments (9.1.7, 9.3.2), advances recovered per the agreement (9.2.6); disputed items certified and paid first on undisputed parts (9.4.11); payment applications must list construction workers' wages separately (9.4.9).
- →
Full workflow of agreeing and paying construction advance payments (GB/T 50500-2024 Section 9.2): nature, proportion, procedure, guarantee, and recovery
The construction advance payment (materials advance) is paid by the Employer before commencement for the Contractor's materials preparation - earmarked and interest-free. For labour-and-material contracts, the payment proportion should not be less than 10% of the signed contract price (net of provisional sums, dayworks and provisional sums for nominated specialist subcontract works) and should not exceed 30% of the signed contract price (for major multi-year projects, prepaid annually at the same proportion in accordance with the annual plan). The Contractor applies -> the Employer reviews and pays (an equal-value guarantee may be agreed); recovery is made as agreed in the contract, or, if not agreed, in one or more instalments; on termination of the contract, any unrecovered portion is recovered in full.
- →
Core differences between railway work-acceptance valuation and building progress payments: positioning, pricing basis, procedure, non-valuable list, and payment rules
Railway work-acceptance valuation is an investment-control tool (approved-estimate cap + supervisor review sign-off + investment completion reported level by level + five-item negative list of non-acceptable items + deduction of employer-supplied materials); building progress payment is a contract-price payment tool (the contract BOQ is the sole pricing basis; absent agreement, payment should not be below 80% of the cumulative completed value; undisputed portions paid first). Similar in function but entirely different in institutional foundation.
Cited By
- ←
Reconciling the three output-value bases of construction output, measured output and settlement output: item-by-item basis distinction, four classes of difference attribution, the disallowance-and-resubmission tests, and the tie-out with stage settlement documents
Construction output value (physical-progress statistics basis), measured output value (contract basis of qualified quantities certified by the supervising engineer or employer) and settlement output value (contract entitlement basis) are three non-overlapping measurement boundaries; the aim of reconciliation is not to make the three figures equal, but - anchored on the measured output value - to place every difference item by item into the accounts of (1) not yet submitted, (2) measurement period not yet reached, (3) quality not yet confirmed, (4) variations not yet priced held in suspense (plus basis differences and permanent removals), until the residual is zero. Disallowance or resubmission must simultaneously pass the measurement-conditions tests (within the BOQ, an approved variation or dayworks scope; quality qualified with acceptance complete; per the contract calculation rules; within the measurement period; the variation priced or on a provisional price; the Notice of Claim issued within 28 days). Payment of interim settlement by construction stage shall be no less than 80% of the current stage settlement total (GB/T 50500-2024 clause 10.2.4), and stage settlement documents signed and confirmed merge into the final account without re-measurement or re-pricing (clause 10.2.3).
- ←
What the four construction documents prove, who issues them and at which procedural stage - a comparison of the measurement sheet, the site instruction record, the variation order (variation instruction) and the progress payment certificate, with their documentary dependency chain and the time-limit requirements for certification
The four documents occupy four non-overlapping evidentiary layers. The variation order proves whether to vary and what to vary (the instruction fact; GF-2017-0201 Clauses 10.2 and 10.3). The site instruction record proves events outside the contract and the resulting cost facts (GB 50500-2013 Clauses 9.14.2 and 9.14.5; T/CAEC 006-2024 Clause 7.2.9). The measurement sheet proves the quantities of work actually completed (GF-2017-0201 Clause 12.3; GB/T 50500-2024 Clauses 7.1.5, 7.1.7 and 7.1.8) and states expressly that it 'shall not serve as the basis for the relevant works having been delivered as conforming'. The payment certificate proves the amount payable for the current period (GF-2017-0201 Clause 12.4.4; GB/T 50500-2024 Clause 9.1.11) and states that it 'does not indicate that the employer has agreed to, approved or accepted the part of the work completed by the contractor'. Issuing chain: the supervising engineer issues the variation instruction (which must be signed by the employer) -> the contractor submits the variation valuation application within 14 days -> monthly quantity reports are submitted (on the 25th of each month, with 7 days for supervisory review) -> the progress payment application (7 days of review by the supervising engineer, 7 days for the employer to approve and issue) -> payment within 14 days after issue.
- ←
Node division modes, payment percentage floors and post-confirmation re-review rules for interim settlement by construction stage: GB/T 50500-2024 Clauses 10.1.3/10.2.3/10.2.4/10.3.15/10.5.1, Cai Jian [2022] No. 183 and local implementation documents
Nodes, procedures and methods are governed by the contract (GB/T 50500-2024 Clause 10.1.3), and the forms may be monthly/quarterly/annual/physical-progress nodes (Clause 2.0.35); policy and local documents refine this into three modes: fixed cycle, physical-progress nodes, and sub-section/segment/specialism. The payment percentage of interim settlement shall not be lower than 80% of the total interim settlement amount for the current period (Clause 10.2.4). The payable final account amount = final account total price - retention money withheld - cumulative amounts actually paid beforehand (Clause 10.3.15); the cumulative retention money, or the bond amount where a bond substitutes for it, must not exceed 3% of the total settlement price of the works (Clause 10.5.1), so where 3% is retained a single payment reaches 97% of the settlement total price and the cumulative payment reaches 100% on expiry of the defects liability period. Interim settlement documents signed and confirmed by both parties form part of the final account documents, and the final account shall not re-measure or re-price them (Clause 10.2.3); Cai Jian [2022] No. 183 words this as 'in principle not reviewed again after completion', and the documents of Xinjiang, Zhejiang and other places read 'not reviewed again' or 'in principle not reviewed again'.
- ←
The "double 80%" rule for progress-payment and in-process settlement payment ratios: GB/T 50500-2024 Clauses 9.1.7 and 10.2.4 vs GB 50500-2013 Clause 10.3.7 (60%-90%)
GB/T 50500-2024 raises the payment floor from 2013's 60% to 80% and removes the 90% cap, forming "double 80%": progress payments (9.1.7) - where the contract is silent, preferably not below 80% of the cumulative completed work value; in-process settlement payments (10.2.4, new in 2024) - not below 80% of the current in-process settlement amount. The two 80s differ in force: the progress-payment one is a fallback when the contract is silent ("preferably not below"); the in-process one is a floor that contractual agreement cannot breach ("shall not be below").
- ←
Commencement conditions and the issuing procedure of the commencement order: GB/T 50319-2013 Article 5.1.8's four conditions and Beijing's pre-start checks (DB11/T 382-2017 Article 3.1.10)
GB/T 50319-2013 Code for Construction Project Management (Supervision), Article 5.1.8, sets the commencement conditions: design briefing and drawing review completed; the project execution plan signed by the chief supervising engineer; the builder's site quality and safety management systems established with staff, plant and materials in place; access roads and water, power and communications meeting commencement needs - and, upon the employer's approval, the chief supervising engineer issues the commencement order. Beijing adds DB11/T 382-2017 Article 3.1.10's pre-start checks: the construction permit issued; design briefing and drawing review done; the execution plan reviewed by the chief supervising engineer; survey control pegs checked and passed; special protection measures for adjoining buildings and underground pipelines in place.
- ←
Stepwise procedure, stage time-limits and measurement-dispute routes for progress payment measurement and payment (GB/T 50500-2024 Sections 7.1, 9.1 / 9.4, Chapter 11; comparison with GB 50500-2013)
Progress payment measurement and payment turns on measurement period = payment period, in four steps: 1 the contractor submits measurement outputs and the payment application per measurement period and payment verification date (GB/T 50500-2024 Articles 7.1.5, 9.4.9); 2 the employer checks in writing and the contractor confirms in writing or submits review comments; failure to provide check / re-check results in time deems the contractor's outputs (or comments) accepted (7.1.5, 7.1.6), sign-off per 7.1.7; 3 the payment certificate goes to the contractor for confirmation first (9.1.10); the employer issues the certificate after checking within a reasonable time, pays the undisputed part first where some items are disputed (9.4.11), and pays before the contractual latest payment date (9.1.11); 4 failing agreement after checking, review and re-check, Article 7.1.7 routes to Chapter 11 - negotiation, dispute review or mediation, then arbitration or litigation (11.1.1, 11.1.2). The 2024 edition mostly says agreed time; the concrete day-counts (7-day verification, 24-hour notice, 7-day objection and re-check, 14-day certificate) appear only in the repealed GB 50500-2013 Articles 8.2.3 / 8.2.4 / 8.2.5 / 8.3.5 and 10.3.9, for comparison only.
- ←
The full workflow of quality retention money retention and return (cap, retention methods, defects liability period commencement, and return procedure)
The retention money is reserved from payable amounts, capped at 3% of the total settlement price (the same cap applies to bank guarantees substituting for it); where performance security has been provided, or guarantee security or quality insurance is adopted, no further retention is allowed. Retention may be made in instalments from the first payment period or in one lump sum at final account; the computed base excludes prepayments and price-adjustment amounts. The defects liability period is generally 1 year and 2 years at most, running from the date of taking-over (completion acceptance) (where the employer causes delay in acceptance, it starts automatically 90 days after submission of the completion report). On expiry, and after verification, the money is returned within 14 days; failure to reply within that time is deemed acceptance of the application; no interest accrues on the returned remaining retention money.
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.
- ←
GB/T 50500-2024: both progress payments and process-settlement payments floored at 80% — the wording contrast between 9.1.7 "should not be lower" and 10.2.4 "shall not be lower"
Under GB/T 50500-2024, the payment-ratio floors for progress payments and construction-process settlement payments are both 80%, with different force: Clause 9.1.7 on progress payments — "where the contract does not state a payment ratio for the works value, the ratio should not be lower than 80% of the cumulative completed works value" — "should" is recommendatory: agreement prevails, the 80% floor applies only absent agreement; Clause 10.2.4 on process-settlement payments — "the payment ratio shall be agreed in the contract and shall not be lower than 80% of the current process-settlement total" — "shall not" is a prohibitive hard floor: even an agreed ratio below 80% fails the standard. The bases differ: progress payments on "cumulative completed works value", process-settlement payments on "current process-settlement total".
- ←
Return of the quality retention money: timing, procedure, and the final account interface (Jian Zhi [2017] No. 138 + GB/T 50500-2024 §10.5)
The retention money is returned when the defect liability period (generally 1 year, 2 years maximum) expires and the contractor has fulfilled its defect-repair duties, upon application; the period runs from completion acceptance, or — where acceptance is impossible for employer reasons — automatically 90 days after the contractor submits the completion acceptance report; the employer verifies within 14 days and returns within 14 days after verification absent an agreed return period; failure to respond within 14 days of the application, and again 14 days after a demand, is deemed acceptance; upon expiry, final account clearance proceeds per GB/T 50500-2024 §10.5.5, returning the guarantee or remaining retention money without interest.
- ←
Site instructions and certified records overview: applicable matters and prohibited items, the five-node handling procedure, graded signing authority, the 2024 standard basis and settlement application
Certification runs a five-node closed loop: assess reasonableness beforehand and survey the original conditions → at occurrence, measure on site, keep photos, have all parties sign the original vouchers → submit the certification file within the contract-agreed time → the supervising engineer reviews, the chief supervising engineer signs, the employer approves → participate in acceptance, confirm the completed content and compute the final cost. Signature authority: written documents signed by both parties' site management within their scope of duty are valid pricing vouchers (GB/T 50500-2024 cl. 12.2.1); the supervisor certifies facts strongly but prices weakly — priced certifications need the joint sign-off of employer, contractor and supervisor (T/CAEC 006-2024 cl. 7.2.9); a one-party signature binds only the signing party. With the 2024 code dropping the site-certification clause, off-contract work flows through three channels — variation, additional works and dayworks — and dayworks certification reports not verified in time are deemed accepted (cl. 7.5.5).
- ←
Old-vs-new rules on the advance payment ratio: GB/T 50500-2024 Clauses 9.2.2/9.2.3 vs GB 50500-2013 Clause 10.1.2 — the 10%–30% band and changed deduction bases
The 10%–30% payment band is retained in GB/T 50500-2024 but the deduction bases changed: the lower-bound base now deducts the provisional sum for nominated specialist subcontract works in addition to provisional sums; the upper-bound base is now 30% of the signed contract price with no deductions; the basis for computing the advance expressly deducts three items (provisional sums, dayworks amounts and the provisional sum for nominated specialist subcontract works); the lower-bound wording softens from "shall not be below" to "should preferably not be below" (the standard as a whole becoming a recommended national standard). Advances for major multi-year works are paid annually against the annual programme, with each year preferably not below 10% and not above 30% of that year's planned contract price for completion (excluding provisional sums and the provisional sum for nominated specialist subcontract works) (9.2.3).